HomeMy WebLinkAbout16 - CC-9 - Apparatus Room Extension and Rescue Vehi - 7/21/2015CITY COUNCIL AGENDA REPORT
MEETING DATE: JULY 21, 2015
ITEM NUMBER: CC -9
SUBJECT: APPARATUS ROOM EXTENSION AND RESCUE VEHICLE STORAGE BUILDING -
FIRE STATION NO. 4 -CITY PROJECT NO. 15-10
DATE: JUNE 26, 2015
FROM: PUBLIC SERVICES DEPARTMENT / ENGINEERING DIVISION
PRESENTATION BY: ERNESTO MUNOZ, PUBLIC SERVICES DIRECTOR
FOR FURTHER INFORMATION CONTACT
RECOMMENDATION:
FARIBA FAZELI, CITY ENGINEER, (714) 754-5335
Adopt plans, specifications, and working details for the Apparatus Room Extension and
Rescue Vehicle Storage Building at Fire Station No. 4, City Project No. 15-10.
2. Accept the withdrawal of the bid submitted by Marjani Builders, Inc. at 26091 Ravenna Road,
Mission Viejo, CA 92692.
3. Award the construction contract to St. George Construction, Inc. at 7839 Adwen St., Downey,
CA 90241, in the amount of $690,000.00 (base bid plus additive item AD1).
4. Authorize the Mayor and the City Clerk to execute the Public Works Agreement.
BACKGROUND:
The existing condition of Fire Station No. 4, as well as the needs of the Fire Department,
requires the City to expand this facility and construct needed upgrades in order to maintain it
in working order and to comply with the Americans with Disabilities Act (ADA) accessibility
requirements. This project will extend the existing Apparatus Room at Fire Station No. 4 and
will add a detached vehicle storage building to the site. The existing bathroom will be upgraded
to comply with ADA requirements. New accessible parking stalls and an accessible path of
travel will also be part of the scope of this work. In addition, a new emergency generator will be
installed in order to maintain critical services to Costa Mesa residents during times of power
outages.
ANALYSIS:
The scope of the Apparatus Room Extension and the new Rescue Vehicle Storage Building
includes adding 800 square feet to the existing building; constructing a 1,024 square foot
detached rescue vehicle storage building; upgrading the existing restroom to meet ADA
accessibility requirements; creating new accessible parking stalls with an accessible path -of -
travel to the building; and installing a new emergency generator.
The City Clerk received and opened seven (7) bids for this project on April 28, 2015. However,
Marjani Builders, Inc., the apparent low bidder, has since requested to withdraw its bid from
consideration on this project due to a clerical error made in the bidding documents, as allowed
under California Public Contract Code Section 5101(b). Therefore, it is recommended to
accept the withdrawal of their bid. The second apparent low bidder, St. George Construction,
Inc., submitted a base bid proposal in the amount of $670,000, and is recommended for award.
The Engineer's estimate for this work was $290,000; and the average of the remaining six (6)
base bids received amounted to $862,148.33. An analysis of the bids indicates that the
recommended apparent low bidder, St. George Construction, Inc. submitted a base bid
proposal that is approximately two hundred thirty-one (231%) percent higher than the
Engineer's Estimate. The Bid Abstract is included as Attachment 1.
Staff has reviewed all of the bids submitted by the contractors and have determined that the
bids reflect the scope of work to be performed. The Engineer's estimate omitted the inclusion
of all of the costs to complete the work on the plans and when corrected was in line with the bid
proposal submitted by the lowest apparent bidder.
In addition to the base bid, the bid solicitation included one additive bid (Item AD1) to address
painting the entire exterior of the building in order to avoid noticeable paint transitions between
areas of new work and the existing building. The bids for this item of work are in line with the
revised Engineer's estimate.
The license and references of St. George Construction, Inc. were checked and staff has found
them to be in good standing. In 2012, St. George Construction, Inc. successfully completed the
Corporation Yard Fire Damage Restoration Project (2310 Placentia Avenue, Costa Mesa).
ALTERNATIVES CONSIDERED:
The first alternative is to award a contract for the base bid only. The removal of the additive
item to paint the entire exterior of the building from the contract is not recommended since it is
more feasible to paint the entire building at one time instead of sections where there will be a
noticeable paint transition between areas of new work and the paint on the existing building.
Adequate funds are currently appropriated to accomplish this alternative.
The second alternative to this Council action would be to reject all of the bids and rebid the
project. Staff believes that re -advertising and rebidding the project will not result in lower bids.
Canceling the project is not recommended because Fire Station No. 4 needs to remain
operational and is in immediate need of the proposed work.
FISCAL REVIEW:
In Fiscal Year 2014-2015 and 2015-2016, City Council allocated a total of $1,090,000 towards
the design and construction of this project. The design phase has been completed and the
construction documents have been prepared. There is sufficient funding to complete the
construction phase.
LEGAL REVIEW:
St. George Construction, Inc. has furnished the necessary bonds and insurance, which were
approved as to form by the City Attorney. After the award and subsequent execution of the
contract, a "Notice to Proceed" will be issued.
2
CONCLUSION:
The City has received bids for the Apparatus Room Extension and new Rescue Vehicle Storage
Building - Fire Station No. 4 Project, City Project No. 15-10. Staff has evaluated all of the bids
and recommends that the City Council adopt the plans, specifications, and working details for said
project; accept the withdrawal of the bid submitted by Marjani Builder, Inc.; award a contract to the
apparent low bidder, St. George Construction, Inc. in the amount of $690,000.00 (base bid plus
additive bid item AD1); and authorize the Mayor and the City Clerk to execute the Public Works
Agreement.
ERNESTO MUNOZ
Public Services Director
ATTACHMENTS:
DISTRIBUTION
Bid Abstract
Chief Executive Officer
Fire Chief
Battalion Chief
City Attorney
City Clerk
Staff
File
FARIBA FAZELI
City Engineer
3