HomeMy WebLinkAbout05 - CC-5 - Harbor Blvd. Improvements from South Co. - 12/1/2015CITY COUNCIL AGENDA REPORT
MEETING DATE: DECEMBER 1, 2015 ITEM NUMBER: CC -5
SUBJECT: HARBOR BOULEVARD IMPROVEMENTS FROM SOUTH COAST DRIVE TO
SUNFLOWER AVENUE, CITY PROJECT NO. 14-07 - CHANGE ORDER NO. 3
DATE: NOVEMBER 19, 2015
FROM: PUBLIC SERVICES DEPARTMENT/ENGINEERING DIVISION
PRESENTATION BY: ERNESTO MUNOZ, PUBLIC SERVICES DIRECTOR
FOR FURTHER INFORMATION CONTACT: FARIBA FAZELI, CITY ENGINEER, (714) 754-5335
RECOMMENDATION:
1. Approve Contract Change Order (CCO) No. 3 (Attachment No. 1) in the amount of
$80,812.65
2. Approve Budget Adjustment Authorization No. 16-008 (Attachment 2) in the amount of
$30,000.00
3. Authorize the Chief Executive Officer to execute the Contract Change Order
BACKGROUND:
The Harbor Boulevard Improvements Project consists of adding a fourth northbound travel lane
from north of South Coast Drive to Sunflower Avenue. In addition, the project includes traffic
signal modifications to intersections of Harbor/Sunflower and Harbor/Law Court. The project
will meet the recommended roadway widths/geometrics as specified in the Harbor Boulevard
Smart Street Study as well as the Orange County Transportation Authority (OCTA) Master Plan
of Arterial Highways (MPAH).
On June 17, 2014, the City Council awarded a construction contract to All American Asphalt,
P.O. Box 2229, 400 E. Sixth Street, Corona, California 92878, in the amount of $769,769 for
the construction of Harbor Boulevard Improvements.
ANAI YSIS-
To date, the contractor has completed the construction of new curb & gutter, sidewalk, driveways
and traffic signals. The street lights have been relocated to their ultimate location.
During construction, the roadway grades had to be revised to match the existing field conditions.
Change Order No. 1 (Attachment No. 3), in the amount of $3,510.99, was issued to the contractor
to cover the cost of this additional work
Change Order No. 2 (Attachment No. 4), in the amount of $49,850, addressed utility conflicts
encountered during the widening of the roadway and the construction of the traffic signal
foundations.
Pursuant to Council Policy No. 700-1, the Chief Executive Officer (CEO) approval is required for
contract change orders up to $50,000, or 5% of the original contract price, whichever is greater.
Therefore, Change Order No. 2 is being processed for CEO's approval. City Council Policy No.
1
700-1 also restricts the total Change Orders approved by the CEO to 10% of the original contract
amount.
Due to changes requested by Southern California Edison (SCE) to the scope of the work for the
electrical conduits for street lighting, the contractor is submitting a claim for the following extra
work to be performed in the amount of $55,812.65:
• Removal of electrical facilities servicing the existing street lights
• Construction of new street lighting conduit in lieu of utilizing the existing system
• Revisions to the point of connection to SCE facilities
In addition, in the immediate vicinity of the Harbor Boulevard Widening project, City staff has been
monitoring a section of South Coast Drive, east of Harbor Boulevard, which has experienced
settlement due to underground water migration and unstable subgrade soils. Within the past
three months, this condition has led to major settlements within the roadway. In order to provide a
safe travel lane, a portion of South Coast Drive, east of Harbor Boulevard must be milled and
repaved with new asphalt. Since All American Asphalt is working in the immediate vicinity, staff
successfully negotiated to have the extra work performed by All American Asphalt at the existing
competitive contract unit prices. A price comparison with other contractors indicate that this will
result in the work being performed more cost effectively than if we were to issue a separate
contract. The additional cost to repair the roadway settlement along South Coast Drive is
estimated at $25,000.
The total additional cost, excluding Change Order Nos. 1 and 2, adds up to a total of $80,812.65
or 10.5% of the original contract. Therefore, approval of Change Order No. 3 (Attachment 1) by
the City Council is being requested in accordance with Council Policy No. 700-1.
If approved, the total for Change Orders Nos. 1, 2 and 3 will increase the original contract amount
to $903,942.64 or 17.4% of the original contract price.
ALTERNATIVES CONSIDERED:
No alternatives are being considered for this item
FISCAL REVIEW:
Funding for the Harbor Boulevard widening project is available from the OCTA Measure M2 grant,
Air Quality Management District (AQMD) funds and Traffic Impact Fees. The attached budget
adjustment (BA No. 16-008) appropriates $30,000.00 from Traffic Impact Fee Funds towards the
requested contract change order. Funding for the emergency repairs to the roadway on South
Coast Drive, east of Harbor Boulevard is available from Gas Tax Funds. The balance of this
contract change order will be covered with appropriated grant funds.
LEGAL REVIEW:
There is no legal review required for this item.
CONCLUSION:
Unforeseen conditions during the construction of the Harbor Boulevard Improvements project
resulted in extra work beyond the original contract scope of work. In addition, an emergency
pavement repair is required on South Coast Drive east of Harbor Boulevard, near the IKEA store
to prevent a potential sink hole within the roadway.
Ir
To date, per City Council Policy No. 700-1, the Public Services Director has approved Change
Order No. 1 in the amount of $3,510.99 and Change Order No. 2, in the amount of $49,850 is
being processed for CEO's approval.
However, additional funding for unanticipated extra work for this contract is required to complete
this project. Therefore, staff is recommending that the City Council approve Change Order No. 3
in the amount of $80,812.65; Budget Adjustment Authorization No. 16-008 for $30,000.00, and
authorize the Chief Executive Officer to execute the contract change order.
ERNESTO MUNOZ
Public Services Director
FARIBA FAZELI
City Engineer
ATTACHMENTS: 1. Change Order No. 3 - $ 80,812.65
2. BA No. 16-008 for $30,000.00
3. Change Order No. 1 - $ 3,510.99
4. Change Order No. 2 - $ 49,850.00