HomeMy WebLinkAbout22 - NB-1 - Consideration of the New Donald Dugan Li - 11/17/2015CITY COUNCIL AGENDA REPORT
MEETING DATE: NOVEMBER 17, 2015 ITEM NUMBER: NB -1
SUBJECT: CONSIDERATION OF THE NEW DONALD DUNGAN LIBRARY,
NEIGHBORHOOD COMMUNITY CENTER, AND PARK IMPROVEMENTS
PROJECT AT LIONS PARK.
DATE: NOVEMBER 9, 2015
FROM: THOMAS R. HATCH, CHIEF EXECUTIVE OFFICER
PRESENTATION TAMARA S. LETOURNEAU, ASSISTANT CHIEF EXECUTIVE
BY: OFFICER
FOR FURTHER INFORMATION ALMA REYES, RECREATION SUPERVISOR AT
CONTACT: 714-754-5636
RECOMMENDATION:
Staff recommends that the City Council approve the Donald Dungan Library, Neighborhood
Community Center, and Park Improvements Project, specifically regarding the following:
Review and approve the recommended option to build new library building; renovate
existing Donald Dungan library to serve as the new Neighborhood Community Center
(NCC); demolition of the NCC; and proposed parking and landscape developments in two
(2) phases.
2. Review and approve in concept for further development funding option 3 as described in
the Fiscal Review section of this report and Attachment 1 C Part 3 including Fire Station 1
and direct staff to return with an update on the funding options as part of the FY 15-16
mid -year budget report.
3. Authorize the Mayor to execute a second professional services agreement with Johnson
Favaro for architectural services for the new Donald Dungan Library, NCC, and Park
Improvements Project at Lions Park (City Project No. 800015), in the amount of
$2,991,287, for a five (5) year term, and execute the option for a two-year extension if
needed.
BACKGROUND:
At the January 20, 2015 City Council meeting, the City Council awarded a professional services
agreement to Johnson Favaro, 5898 Blackwelder Street, Culver City, CA 90232, for the
preliminary design phase of the Donald Dungan Library and Neighborhood Community Center
(NCC) projects, including the outdoor space surrounding these sites.
The contract included services related to Phase I- Preliminary Design of the Donald Dungan
Library and the NCC scope of work including 1) A complete a feasibility study; 2) Assessment of
the current open space surrounding these facilities and integration into a common theme that will
promote a welcoming and friendly environment that Costa Mesa residents of all ages can enjoy;
3) Complete a stakeholder process to determine the needs of the users/customers and
stakeholders; 4) Provide preliminary project cost estimates; and 5) Prepare proposed concept
plans. The goals of the Donald Dungan Library and Neighborhood Community Center Feasibility
Study include:
• Improve library services and create quality programming and event space.
• Increase facility use for both the library and meeting center.
• Improve outdoor space associated with all facilities in Lions Park.
• Create a space that promotes education, community and civic engagement.
The five month Feasibility Study included three principal phases of work and was commenced on
February 1, 2015. The three phases of the study:
1. Review and Assessment of Existing Conditions
2. Library and Community Meeting Center Programming and Option Development
3. Final Recommendation and Cost Estimates
Stakeholder Outreach
During the study, through -out all phases, the architect engaged in extensive stakeholder outreach
in order to better understand existing conditions, constraints and opportunities; reviewed
alternative options for completing project goals and solicited input and direction. A total of three
community workshops were conducted on March 5th, April 16' and June 18th. At the first
workshop on March 5th the architect outlined the purpose of the study, presented a preliminary
assessment of existing conditions, library service area demographics, Neighborhood Community
Center (NCC) utilization and library and meeting center program needs. Also presented were
Orange County Public Library guidelines and benchmarks for new library construction.
At the second workshop on April 16th the architect identified stakeholder outreach conducted
during the Review and Assessment phase, a summary of the condition of the existing buildings,
an in-depth study of NCC meeting space utilization and presented for review alternate options for
achieving project goals with a focus on two recommended options for consideration:
1. Renovation of the existing NCC to become the new library and renovation of the Dungan
Library to become the new community meeting center; expansion and improvement of
existing park space and street front improvements to include new on -street parking.
2. Demolition of the NCC and construction of a new library building and renovation of the
Dungan Library to become the new community center; expansion and improvement of
existing park space and street front improvements to include new on -street parking.
At the third workshop on June 18th, the architect presented an overview of the project findings to
date, reviewed the two options for consideration including estimates of probable construction cost
for each option and concluded with a final recommendation for consideration.
Review and Assessment of Existing Conditions
Lions Park totals approximately 10 acres and includes within its boundary the two principal
subjects of the feasibility study: the 22,742 SF NCC built in 1981 (34 years old) and the 8,080 SF
1►
Donald Dungan Library built in 1986 (29 years old). Also located in the park are the Downtown
Recreation Center and the Costa Mesa Historical Society. Adjacent to the park is the Park Fire
Station.
Parking is provided for 295 cars in surface lots within the park and by way of on -street parking
surrounding the park. Un -programmed open space within the park totals approximately 2.8 acres.
Building and site assessment included an updated survey of the site area around the Dungan
Library and NCC and a review and report of the existing condition of mechanical, electrical and
plumbing systems for both the Dungan Library and the NCC.
Library Programming
A Library Planning Working Group was established to complete an assessment of existing library
services and preparation of a proposed new library program. The Library Planning Working
Group included senior administration of the Orange County Public Library (OCPL), Donald
Dungan Library branch library staff, City of Costa Mesa staff, the architect and the library planning
consultant, Linda Demmers.
The Working Group identified current library service deficits including:
• Stacks full to capacity limiting collection growth (68,000 volumes)
• Single meeting room seats less than 40 limiting size of programs such as children's story
time and the summer reading program.
• No teen area
• No space for tutoring
• No space for literacy program
• No homework center
• 15 internet PC's for public use
• Lack of acoustical separation between adult and children's areas.
• No group study rooms
• Limited Friends of the Library support space
Input Measures and Benchmarks
The Library Service Area for the Dungan Library is approximately 55,000 residents based on
information provided by the California State Library and OCPL. The Working Group identified
OCPL benchmarks and guidelines which identify square footage, reader seats and collection
items per capita and evaluated the Dungan Library relative to current benchmarks. In summary,
the existing library is approximately 40% the size identified by the benchmarks for a library serving
the residents of this Library Service Area.
Proposed Library Program
The program developed as a result of this Feasibility Study identifies a new community library of
approximately 20,000 SF to include:
• A Children's Library separated from adult reading areas and collections
• A dedicated Teen Area
• Increase in collection items from 68,000 to 95,000 items.
• Increase in reader seats from 55 to 160 seats
• Increase in PCs from 15 to 36 PCs
• A popular library or "Marketplace" within the library for the most popular parts of the
collection including browsing, new arrivals and self-service holds.
• Self -check machines and space dedicated to an Automated Materials Handling System
(AMHS)
3
Four group study rooms
Two meeting rooms: One room seating 125 persons totaling 1,500 SF and a second
room totaling 400 SF and seating 30 persons.
A Friends of the Library book sale and work area
The Donald Dungan Library at Lions Park serves two key constituencies of all community libraries
within walking distance of the park:
• Seniors living at the Tower on 19th Senior Community and utilizing the nearby Costa Mesa
Senior Center
• Residential neighborhoods with a high population of school age children located between
Whittier Elementary School and Lions Park
Community Meeting Room Center Programming
In order to evaluate meeting center program requirements the architect reviewed detailed meeting
space activity records and interviewed frequent long-time users of NCC meeting space that
include: NMUSD, Pat Allen Seminars, Yellowstone, American Cetacean Society, and OC Soccer
Referee Association.
The Parks and Community Services Department maintains detailed records of all meeting space
activity in all City -operated meeting space including identification of rented, non -rented and City
meeting use for all facilities.
A summary of the findings of this study include:
• Other meeting space in better condition than the NCC meeting space is available in City -
operated meeting space: 16,143 SF in eight rooms city-wide as compared to 9,607 SF in
eight rooms in the NCC.
• The NCC is inefficient. NCC meeting space is utilized at 30% capacity, but is maintained
by the City at 100%.
• An event/meeting seating capacity of 300 seats in both lecture or banquet format satisfies
event/meeting demand.
• Use of the NCC will continue to decrease unless it becomes more competitive (updated
systems, new finishes and state-of-the-art technology are required).
Existing Building Assessment
The Architect's Team included engineers in the following disciplines: structural, mechanical,
electrical and plumbing. The engineering team completed a building systems evaluation for the
Dungan Library and the NCC. The buildings are well-maintained and have served their purpose
for many years. The NCC is 34 years old and the Donald Dungan Library is 29 years old.
Conclusions of the report include:
Neighborhood Community Center
• Mechanical equipment and some electrical panels have reached the end of useful life and
need to be replaced.
• In the event of any renovation all lighting fixtures/controls must be replaced to comply with
current California Title 24 energy standards.
• Roof membrane needs to be replaced.
• In the event of any renovation, the roof structural diaphragm needs to be strengthened to
current code standards.
M
• Exterior doors and windows do not meet current California Title 24 energy standards and
must be replaced in the event of renovation.
• Kitchen is outdated and the grease trap must be completely replaced
• Plumbing waste system must be replaced
• Audiovisual/Information Technology systems are outdated.
Donald Dungan Library
• Mechanical equipment, electrical panels and plumbing systems have reached the end of
useful life and need to be replaced.
• In the event of any renovation all lighting fixtures/controls must be replaced to comply with
current California Title 24 energy standards.
• In the event of any renovation, the building seismic resisting lateral bracing system must
be strengthened.
• Exterior doors and windows do not meet current California Title 24 energy standards and
must be replaced in the event of renovation.
• Audiovisual/Information Technology systems are outdated.
ANALYSIS:
With the review and input from City staff, Orange County Public Library and Dungan Library staff
and community stakeholders the architects identified three projects required to address program
needs and community goals. The three projects are:
1. LIBRARY: A new or renovated library totaling approximately 20,000 SF.
2. COMMUNITY MEETING CENTER: A renovated community meeting center including the
following: one meeting/event room seating 300 in either banquet or lecture format with a
stage; one 700 SF meeting room seating 40 and a catering kitchen to support events.
3. PARK IMPROVEMENTS: Park improvements include expansion of park open space in
order to better connect all facilities to the surrounding park. With more efficient street -front
parking and efficient building areas, park open space is increased by 1 acre.
Improvements are to include plantings to reduce water usage and to replace impermeable
building area and site area with permeable open space to facilitate improved storm water
management.
Two options emerged for completing the three projects for consideration:
RENOVATE: Renovation of the existing NCC to become the new library and renovation of
the Dungan Library to become the new community meeting center; expansion and
improvement of existing park space and street front improvements to include new on -
street parking. Total project cost for this option (including estimated project soft costs) is
$29M.
2. NEW/RENOVATE: Demolition of the NCC and construction of a new library building and
renovation of the Dungan Library to become the new community center; expansion and
improvement of existing park space and street front improvements to include new on -
street parking. Total project cost for this option (including estimated project soft costs) is
$34.5M.
Soft costs include fixtures, furnishings and equipment for both buildings, professional services
fees, project management fees, permit costs and City contingencies and costs.
5
Recommended Option
New construction of a library has several benefits over renovation of an existing building including:
1. Elimination of potentially costly unknowns on top of high renovation costs associated with
significant renovation of the NCC.
2. Design of a new efficient library is not constrained by the existing footprint, structure and
configuration of the NCC.
3. Replacement of the NCC with a "blind side" service alley with a new library that views both
ways into the park greatly enhances security in the new park.
For these reasons and in light of comparable project costs for the renovation and new
construction options the "New Construction" option is recommended. At Community Workshops
# 2 and #3 both options and project costs were presented and the "New Construction" option was
preferred by a majority of those in attendance.
New Donald Dungan Library and Community Meeting Center
The Feasibility Study does not include design of either the Community Meeting Center or new
Library. Should the project move forward both facilities would be subjects of a multi -phase,
iterative and public design process including Schematic Design through Construction Documents
phases.
However, to complete the feasibility study and to confirm that project program and functional goals
can be met in the proposed facilities, preliminary plans have been developed to confirm general
contents and organization of both facilities. These preliminary plans, along with site plans were
the basis for a detailed line -item cost estimate prepared by a professional cost estimator that was
part of the architect team.
Parking
The Feasibility Study does include an initial assessment of parking for Lions Park and for
proposed and existing facilities. A total of 295 spaces are provided at Lions Park in surface
parking lots and at street -front parking surrounding the park. The proposed recommended option
proposes the removal of the surface lot to the east of the existing NCC and replacement of that
parking with efficient street -side parking adjoining the park and facing the new library. The
proposed new parking totals 296 spaces. In addition to the new street front parking, a new
surface lot is proposed on Anaheim Avenue in front of the existing Costa Mesa Historical Society.
A more detailed parking study and analysis will be completed during successive design phases
should the project move forward.
Implementation
The Feasibility Study concludes that the project must be implemented in at least two and possibly
three phases. A multi -phased construction project provides the city flexibility to implement the
individual projects in a time frame that suits political will and financial capability. This approach
also ensures that no building is demolished before its replacement is completed.
A single phase project is not feasible or recommended as it would remove library services from
Lions Park for the period of construction or for a period lasting between 18 to 24 months.
Construction or renovation of temporary library facilities is an expensive proposition that would off-
set any savings in condensing the project to a single phase and is also not recommended.
X
In a three phase process, The Phase 1 Library construction would take place in the site area to
the south of the existing NCC and would be completed by October 2018. Phase 2 includes
renovation of the Dungan Library would start in November of 2018 and be completed by
November 2019. The third phase Park Improvements project would begin at completion of the
Dungan Library renovation and would start with demolition of the NCC. Phase 3 would be
complete in December of 2020.
Design
Design of the buildings is not a part of the Feasibility Study. Images and floor plans presented are
intended to illustrate how a design process might unfold and the tools used to convey the design
and to communicate throughout the design process with this community.
We will look around us for what is successful and what is not. We can and should turn to history
as there is a material wisdom and common sense in the tradition of architecture that developed in
Southern California during its early settlement. We should not just look back but should also look
forward as this building must serve this community for at least 50 years and probably more.
A clear goal for any successful design is to understand thoroughly the unique and complex
environment the project occupies. Costa Mesa is a unique community in a very particular place
and no other library or community meeting center will fit this unique set of circumstances. It is the
iterative design process, completed with the entire community of stakeholders — completed by
way of trial and error, through speculation and evolution - that will define what is right for this
community and for this site.
FISCAL REVIEW:
At this time the total project cost is estimated at $34.5 million which includes professional
services fees, construction cost. Additionally, of the $34.5 million approximately $5.7 million will
be set aside for other soft costs associated with the project including:
1. Fixtures, furniture and equipment for both buildings
2. Permit fees, Utility connection fees that are not a part of the general contractor scope,
etc.
3. Any City costs attributed to the project
4. Construction Contingency
5. Other professional services to be contracted by the city for the project such as:
• Third party cost estimator
• Project/Construction Management during construction
• Hazardous materials investigation/abatement
Funding options
Funding options for this project are discussed in the attached Library/Community Center/Park
Improvement Projects Funding Options September 2015 document. Three options are
presented:
1. Funding without debt: Pay as you go which provides $34,500,000 by FY 19-20
(Attachment 1C Part 1). This uses, for the next four fiscal years, all annual budget
allocation of CIP funds, all Capital Facilities funds, some gas tax funds, some park fee
revenue and one year of funds that would then no longer be needed on the 2003 COPS
debt service. No new debt would be incurred.
7
2. Funding with debt: Debt financing for an early start project. Approximately $29,728,000
in debt financing would be needed. (Attachment 1 C Part 2) For rough pricing purposes
for each, we have assumed 30 year financing of $29,728,000 at 4.5% interest with an
annual payment of $1,807,529.
3. Front -load one year to reduce debt: This option would employ a strategy of
accumulating additional funds during FY 16-17 in order to reduce the amount of debt
required (Attachment 1 C Part 3). The lower debt amount to achieve this strategy would
be $25,258,131 with an annual payment of $1,535,751. The annual payment would
initially be made using budgeted Capital Facilities funds. By FY 19-20, when the 2003
COP is completed, the funds that had been used for the 2003 COP payment could then
be used for the new debt service payment; CIP and Capital Facilities funds would be
freed up for other purposes.
Option 3 is recommended with the addition of including funding for Fire Station 1 in the
financing plan. It is also recommended that the Finance advisory Committee review these
funding options. Finance staff would return with an update of the funding options in the FY 15-
16 mid -year budget report.
Architectural Services
On January 20, 2015, the City awarded a professional services agreement to Johnson Favaro in
the amount of $125,125 for the first phase of the project. During fiscal year 2014-2015, the City
Council approved funding in the amount of $386,100 for the project. Currently in fiscal year 2015-
16, funding has been appropriated to the subject project in the amount of $4 million dollars.
The architectural services have been evaluated and projected for the remainder of the project.
The cost of architectural services is in the amount of $2,991,287. After staff's analysis of the
architectural services and remaining work of the project, it has been determined that funds be
appropriated to continue procuring the services of the firm through the completion of the project.
Entering into a second professional services agreement to a five (5) year professional services
agreement with an option for one (1) two-year extension will enable Johnson Favaro to continue to
provide architectural services through the completion of the project.
Operational Costs
The operation and financial responsibilities of the two facilities will remain intact. The OCPL will
continue to be financially responsible for all staffing cost necessary for the operation of the new
library, while staffing cost for the operation of the NCC will continue to be the responsibility of the
City.
LEGAL REVIEW
Legal has prepared and reviewed the second Professional Services Agreement as to form.
ALTERNATIVES TO CONSIDER
The City Council could choose to terminate the contract with Johnson Favaro upon exhaustion of
the encumbered funds and direct staff to rebid the remaining services for the Donald Dungan
Library and NCC project. This would require the City to undergo the RFP process and is
anticipated to take approximately 120 days including City Council review.
To date, Johnson Favaro has successfully completed Phase I (Feasibility Study) of the project.
Based on qualifications and high level of services provided thus far, Johnson Favaro, has
demonstrated the ability to continue with the execution of this project. It is staff's recommendation
that the City Council consider amending the existing professional services agreement with
Johnson Favaro to allow this project to proceed.
CONCLUSION:
The building of a new Donald Dungan Library and renovation of a facility serving as the new
community center provides the basis for the upgrade of City facilities. Furthermore, the new park
and street front improvements will not only enhance the esthetics of Lions Park, but also create a
welcoming environment for all. Staff is recommending that the City Council: 1) Review and
approve the recommended option to build new library building; renovate existing Donald Dungan
library to serve as the new Neighborhood Community Center (NCC); demolition of the NCC; and
proposed parking and landscape developments in two (2) phases; 2) Review and approve in
concept funding option 3 including Fire Station 1; and 3). Authorize the Mayor to execute the
second professional services agreement with Johnson Favaro for architectural services for the
new Donald Dungan Library, NCC, and Park Improvements Project at Lions Park (City Project
No. 800015), in the amount of $2,991,287, for a five (5) year term, and execute the option for a
two-year extension if needed.
TAMARA S. LETOURNEAU
Assistant Chief Executive Officer
ERNESTO MUNOZ
Director of Public Services
ALMA REYES
Recreation Supervisor
ATTACHMENTS:
THOMAS R. HATCH
Chief Executive Officer
STEPHEN DUNIVENT
Interim Director of Finance
1. Library and NCC Park Funding Options (Attachment 1)
2. Bond Payable Worksheet (Attachment 1 A)
3. Existing Debt Narrative (Attachment 1 B)
4. Library and NCC Park Funding Options 30 years (Attachments
1 C,1 D, and 1E)
5. Second Professional Services Agreement
6. Scope of Work from Johnson Favaro for Architectural Services
E