HomeMy WebLinkAbout28 - PH-1 - Annual Review of the Citywide Traffic - 12/1/2015CITY COUNCIL AGENDA REPORT
MEETING DATE: DECEMBER 1, 2015 ITEM NUMBER: PH -1
SUBJECT: ANNUAL REVIEW OF THE CITYWIDE TRAFFIC IMPACT FEE PROGRAM
DATE: NOVEMBER 17, 2015
FROM: PUBLIC SERVICES DEPARTMENT/TRANSPORTATION SERVICES DIVISION
PRESENTATION ERNESTO MUNOZ, PUBLIC SERVICES DIRECTOR
BY:
FOR FURTHER INFORMATION CONTACT: RAJA SETHURAMAN, TRANSPORTATION SERVICES
MANAGER (714) 754-5032
RECOMMENDATION:
Adopt the Resolution (Attachment 1) to approve the recommendations by the Traffic Impact Fee Ad
Hoc Committee and staff as follows:
1. Continue the current traffic impact fee of $181 per Average Daily Trip (ADT);
2. Continue the incentive program for new developments by assessing traffic impact fees on an
incremental basis for the first 100 trips; and
3. Approve the annual accounting of the Citywide Traffic Impact Fee Program.
BACKGROUND:
Pursuant to California Government Code Section 66000 et seq., and the Costa Mesa Municipal
Code, a traffic impact fee study is required by the City to establish a basis for the imposition of
Citywide traffic impact fees on new and expanding developments within the City. The purpose of
the fee is to fund the necessary transportation/circulation improvements which are related directly
to the incremental traffic impacts imposed on the City's transportation system by the development
of new and/or changing commercial, industrial, and residential uses as permitted by the General
Plan. The fee also maintains compliance with the eligibility requirements of the Orange County
Transportation Authority's (OCTA) Measure "M" Program (Measure "M").
The City Council has reviewed the Citywide Traffic Impact Fee Program each year since the fee
program was first adopted in 1993. The City Council, in July 1993, also approved the formation
of an Ad Hoc Committee consisting of representatives from various stakeholder groups to work
with staff on all aspects related to the revision and updating of traffic impact fees.
The City Council subsequently appointed an Ad Hoc Committee consisting of members
representing large and small developers, the Chamber of Commerce, citizens -at -large, as well as
members representing the City Council and the Planning Commission, to assist staff in the
development and review of the traffic impact fee.
The current Ad Hoc Committee members and their representation are as follows:
Mayor Pro Tem James M. Righeimer City Council Liaison
Colin McCarthy Planning Commission Representative
Kyle Woosley Chamber of Commerce
George Sakioka Major Developers' Representative
Kerry Smith Small Developers' Representative
Brett Rosol At -Large - Representing Costa Mesa Residents
Walter Davenport At -Large - Representing Costa Mesa Residents
In January 1999, the City Council approved a recommendation by the Traffic Impact Fee Ad Hoc
Committee to establish an incentive program for all new residential, commercial, and industrial
developments in Costa Mesa. The incentive was based upon the assessment of traffic impact
fees on an incremental basis for the first 100 trips generated by new developments.
The last major update of the Traffic Impact Fee Study was completed in September 2005. The
update took into account the most recent land use and circulation information contained in the
2002 General Plan update and subsequent amendments. Several variations of improvement
options were considered, and it was determined that trip fees in the range of $164 per ADT
through $300 per ADT could be justified. On September 20, 2005, the City Council adopted
Resolution 05-70, approving a traffic impact fee of $181 per Average Daily Trip (ADT). The City
Council also approved the continuation of the incentive program for new developments.
The traffic impact fee calculation was re -visited again in 2011, resulting in the update of the
improvement costs using the most recent data as well as accounting for several completed
improvements (Attachment 2). The net effect of the changes yielded a revised calculation of
traffic impact fees of $184 per ADT. However, the traffic impact fee of $181 was continued by the
City Council due to low development activity as a result of ongoing economic conditions, as well
as the schedule of projects in the Capital Improvement Program (CIP).
A chronology of actions taken by the City Council on the Citywide Traffic Impact Fee Program
between the years of 1993 and 2014 is included in Attachment 3.
ANALYSIS:
The City Council, in June 2012, authorized a comprehensive review of the City's General Plan,
including the Land Use and Circulation Elements. As part of this effort, the traffic impact fee
program will undergo significant review early next year. In consideration of this, a majority of
Traffic Impact Fee Ad Hoc Committee members recommended the continuation of the current
traffic impact fee of $181 per Average Daily Trip (ADT) and the continuation of the incentive
program for the first 100 trips.
The City will initiate meetings with the Traffic Impact Fee Ad Hoc Committee early next year
following completion of the updated traffic model and a preliminary review of future transportation
conditions with updated land use information.
Incentive Program:
The incentive program for the first 100 trips of development applies to all developments
throughout the City. Several residential developments and smaller commercial developments
have benefited from this incentive program. Therefore, the Traffic Impact Fee Ad Hoc Committee
has recommended continuation of this program. The maximum amount of discount awarded to
any one project is $12,075. Based on development projects approved over the past several years,
staff has estimated that on an annual basis, this incentive has saved the development community
approximately $75,000.
V
Annual Accountina of the Traffic Impact Fee:
California Government Code Section 66001(d) requires an annual review, findings, and
accounting of the Citywide Traffic Impact Fee Program. Attachment 4 depicts the opening
balance, the ending balance on June 30, 2015, interest earned, revenues, expenditures, and
unexpended funds from the Citywide Traffic Impact Fee Account. This attachment also shows
that there are no funds unexpended or uncommitted in the account five (5) or more years after
deposit and that no administrative costs have been charged to the fee account.
As required by the Government Code, the updated Capital Improvement Plan (CIP) is contained
in the Fiscal Year 2015-16 adopted budget and remains valid for the current traffic impact fee
review. The traffic impact fee account information, including the interest earned, shown in
Attachment 4, is available for public review.
ALTERNATIVES CONSIDERED:
The City Council has the option to choose a traffic impact fee rate anywhere in the range of $164 per
ADT to $300 per ADT, based on the most recent update of the traffic impact fee analysis. An
additional alternative is to not have a Citywide Traffic Impact Fee Program at all. This alternative,
however, would make the City ineligible to receive funds from any of the competitive grant programs
processed through the Orange County Transportation Authority's Combined Transportation Funding
Programs. The City Council also has the option of modifying or suspending the incentive program
for new developments.
FISCAL REVIEW:
The traffic impact fees fund only a portion of the required Citywide improvements, and alternative
funding sources such as Measure `M,' federal funds, and other City funds may be needed to fully fund
the transportation improvements as required in the City's General Plan Circulation Element.
The continuation of incentives for new development projects would result in a decrease in traffic
impact fee revenues than would otherwise be received. The total amount of incentives in any given
year would be difficult to estimate. However, based on development projects approved over the past
several years, staff has estimated that on an annual basis the total amount of incentives would be
approximately $75,000. Given that the proposed incentive program may be effective until the next
annual update, and the unlikelihood that new development projects will trigger the need for circulation
improvements based on existing traffic conditions, it is not necessary to identify an alternate funding
source at this time. The "incentive" shortfall will be added to the City -funded portion. If the incentive
program is made permanent in the future, further analysis may be necessary to identify a funding
source, other than Measure 'M' funds, to complete circulation improvements attributed to new
development projects.
LEGAL REVIEW:
The City Attorney's Office has reviewed and approved the Resolution (Attachment 1) for establishing
the City's traffic impact fee and continuing the incentive program for all new developments in Costa
Mesa by assessment of traffic impact fees on an incremental basis.
A101 163 ��1;ILOUF
The Citywide Traffic Impact Fee Program estimated in 2005 was updated in 2011 based on the most
recent cost information and accounting for completed projects, as well as considering the available
balance in the Traffic Impact Fee Account. As the City has recently initiated a comprehensive update
of Land Use and Circulation Elements of the General Plan, the Traffic Impact Fee Ad Hoc Committee
recommended that the current traffic impact fee of $181 per ADT and the incentive program for new
developments be continued. Staff recommends City Council's approval of the Traffic Impact Fee Ad
Hoc Committee's recommendation.
3
ERNESTO MUNOZ
Public Services Director
STEPHEN DUNIVENT
Interim Finance Director
RAJA SETHURAMAN
Transportation Services Manager
ATTACHMENTS: 1 - Traffic Impact Fee Resolution
2- Revised Traffic Impact Fee Calculation
3- Chronology of City Council Actions
4- Traffic Impact Fee Accounting Summary
DISTRIBUTION: Chief Executive Officer
Assistant Chief Executive Officer
Economic & Dev. Svs. Director
City Clerk Division
Staff
File
M