HomeMy WebLinkAbout06 - CC-5 - Citywide Parkway Concrete Repair and New - 8/1/2017CITY COUNCIL AGENDA REPORT MEETING DATE: AUGUST 1, 2017 ITEM NUMBER: CC -5 SUBJECT: CITYWIDE PARKWAY CONCRETE REPAIR AND NEW SIDEWALK CONSTRUCTION PROJECT - CITY PROJECT NO. 14-12 DATE: JULY 20, 2017 FROM: PUBLIC SERVICES DEPARTMENT / ENGINEERING DIVISION PRESENTATION BY: RAJA SETHURAMAN, PUBLIC SERVICES DIRECTOR FOR FURTHER INFORMATION CONTACT: BALTAZAR MEJIA, CITY ENGINEER, (714) 754-5335 RECOMMENDATION: 1. Accept the work performed by C.J. Concrete Construction Inc. and authorize the City Clerk to file the Notice of Completion. 2. Release the Labor and Material Bond seven (7) months after the filing date; release the Faithful Performance Bond one (1) year after the filing date; and release the retention monies 35 days after the Notice of Completion filing date. BACKGROUND: On February 17, 2015, a construction contract in the amount of $575,430.00 was awarded to C.J. Concrete Construction, Inc., 10142 Shoemaker Avenue, Santa Fe Springs, California, 90670, for the Citywide Parkway Concrete Repair and New Sidewalk Construction Project. The project scope consisted of reconstruction of sidewalks, curb and gutter, cross gutters, spandrels, curb ramps, driveway approaches, and other incidental work needed to complete the project in accordance with the contract documents. The list of parkway improvement locations within the scope of work of this contract is included as Attachment 1. Before Improvements After Improvements ANALYSIS: The work required by the contract documents was completed on May 10, 2017, to the satisfaction of the City Engineer, with a final contract cost of $625,388.00. A report of the final costs is included herein as Attachment 2. A summary of the costs is as follows: Original Contract Cost: $ 575,430.00 Change Order No. 1: $ 50,000.00 Final Quantity Adjustments: ($ 42.00) Final Contract Cost: $ 625,388.00 The change order was for additional parkway locations added to the contract over the original project scope. The final contract price reflects a nine percent (9%) increase to the original contract as a result of the change orders and final quantity adjustments. As of this date, there are no Stop Notices filed against the monies due to C.J. Concrete Construction Inc. ALTERNATIVES CONSIDERED: There were no alternatives considered for this item. FISCAL REVIEW: This project was funded with Measure "M2" Fairshare funds, Capital Improvement funds, and Gas Tax revenues. LEGAL REVIEW: There is no legal review required on this item. CONCLUSION: The Citywide Parkway Concrete Repair Project and New Sidewalk Construction Project, City Project 14-12 has been completed to the satisfaction of the City Engineer. It is recommended that the City Council authorize staff to file the Notice of Completion; release the remaining retention monies 35 days after the Notice of Completion filing date; and release the bonds accordingly. RAJA SETHURAMAN Public Services Director ATTACHMENTS: DISTRIBUTION 1 - Location Map 2 - Cost Summary City Manager Assistant City Manager City Attorney City Clerk Staff File BALTAZAR MEJIA City Engineer I• CITY OF COSTA MESA ATTACHMENT 1 North N.T.S. Public Services/Engineering ION PARSONS � ESTANCIA U JOANN ST. RABUCO s > Q g CIR. DARRELL ODJE KA > CI A z Q • > CAPITAL Q ST.F ]-,2 O� 1 0 GPS P�, SENATE sT. WILSON 3 cP� 5 CONGRESS m ST. CON( �c c eP gMEPoCAN GOVERNOR IT, Pl. VICTORIA ST. VISTA - > m - 'a VALLEY- Q ¢ EPINE CIR. GLEN w { VICTORIA J IDGECRES g VIG10 VA PARK > GIR. SEA CIR. BLUFF DR. 3 �• �. PL. GLENEAGLES a OAK ST. 0 F F LINDEN PL K TER< - o cRovE PL t' ST, LA PLUMER ST CENTER ST. WELLO DR, SCOTT T GT S �{ I 19TH I I IT, �O� ST Q Q' JQ' 0 P' COSTA MESA a CENTER TOWNE ST. PL o5 Q PARK DR. 0 W SHALIMAR 3 w z PARK VJy O� BR PJ. PARK Q QO 95 RSCH�Sl 0 DR FR Ny �O w S NEWTON WY, TERMINAL WY. CNB B ST, Q Pcl �O Cy SPT sT FR F—] di PARKWAY CONCRETE REPAIR AND NEW SIDEWALK CONSTRUCTION PROJECT #14-12 (AS -BUILT) =PARKWAY REPAIR LOCATIONS ®NEW SIDEWALK LOCATIONS MAINTENANCE AREAS Page 1 of 4 CITY OF COSTA MESA ATTACHMENT 1 North N.T.S. Public Services/Engineering PRINCETON HANOVER D R. WARTHMORE p BOWLING GREEN WELLESLEY 0 N. DR. N. 0 ELMHURST WESTBROOK i a DR. LN. PL a BUCKNEILL RD, w a ID U AIR R. !F, ! o o� Q m a a p LITTLETON Rp. NASSAU CIR. w RD. VILLANOVA 0 DART GUTH COLLEGE PARK pL. 0 9�F TULANE RD24 . PL. A MHERST RD. PL AKE FOREST RD. JOANN JOANN ST. > a a oDARRELL ST o Q a � z o 0 -SON a CAPITAL ST. a - a SENATE ST.F1 AVOCADO ST_ ST. CONGRESS 9 ST GOVERNOR - 5 T a J VICTORIA ST. 0 o RALCAM o � o 0 2 _ a � a PL. a 2 HAMILTON HAMILTON w ST. J�F Q J a � F7 WLllllllG _ a KNOWELL PL w JSP POMONA REA CENTER a i o � PARKWAY CONCRETE REPAIR AND NEW SIDEWALK CONSTRUCTION PROJECT #14-12 (AS -BUILT) =PARKWAY REPAIR LOCATIONS — MAINTENANCE AREAS Page 2 of 4 CITY OF COSTA MESA ATTACHMENT 1 North N.T.S. Public Services/Engineering P� Q 0� O �F C) s 0 P� 4�0 OT Ol P ST CIO PARKWAY CONCRETE REPAIR AND NEW SIDEWALK CONSTRUCTION PROJECT #14-12 =PARKWAY REPAIR LOCATIONS NEW SIDEWALK LOCATIONS — MAINTENANCE AREAS Page 3 of 4 CITY OF COSTA MESA ATTACHMENT 1 North N.T.S. Public Services/Engineering m o m BAKER ST. mLLI 0 a i o t & c� o EL BEAR ST. POST ST a h '': •: PAULARINO•:::;: 0 MISSION : CHANIN ST. CLAIR a N DR' ST. Q J 3 0 VALENCIAST. F 2hSANTIAGO RD. � RAN DOL EL CAMINO m SONORA EL CAMINO DR. SONORA RD. CORONA LN. O � � ? SONO R Q 9 S w COR PS � 20 DOR o SALVAST. R � S 40 0 0 P2 0 0 o 'D Q 20o a o zo SERRA O CORT 0 WY. DR. PRESI D w PRESIDIO SQ_ � ae CL TEWINKLE F eq LOST%ESA �o PARK Sia ARLINGTON Av. S VJY, SP LESLEY N. R. JO 0 �iFsq FAIR DR. A0� Sq CLEARS ROOK ,Q. PARKWAY CONCRETE REPAIR AND NEW SIDEWALK CONSTRUCTION PROJECT #14-12 =PARKWAY REPAIR LOCATIONS — MAINTENANCE AREAS Page 4 of 4 CITY OF COSTA MESA CJ CONSTRUCTION INC. 10142 SHOEMAKER AVENUE SANTA FE SPRINGS, CA 90670 PROJECT: CITYWIDE PARKWAY CONCRETE REPAIR AND NEW SIDEWALK PROJECT CITY PROJECT 14-12 ATTACHMENT 2 DATE: 06121117 ITEMBID UNIT PREVIOUS QUANTITY TOTAL QUANTITY PREVIOUS AMOUNT TOTAL CONTRACT NO QUANTRY DESCRIPTION PRICE QUANTITY THIS ESTIMATE TO DATE AMOUNT THIS EST TO DATE PRICE 1 1,830 LF Remove and Reconstruct Curb and Gutter (C-6) (with 3' AC $44.00 0 LF 0 LF 0 LF $0.00 $0.00 $0.00 $80,520.00 Slot Pave) 2 42 LF Remove and Reconstruct Curb and Gutter (C-8) (with 3' AC $50.00 0 LF 0 LF 0 LF $0.00 $0.00 $0.00 $2,100.00 Slot Pave 3 427 LF Remove and Reconstruct Curb & Thickened Gutter (10' both $50.00 601 LF 0 LF 601 LF $30,050.00 $0.00 $30,050.00 $21,350.00 side of existing tree) 4 1,320 LF Remove and Reconstruct Curb & Gutter (C-6) (with VAC Slot $40.00 3,507 LF 0 LF 3,507 LF $140,280.00 $0.00 $140,280.00 $52,800.00 Pave 5 168 LF Remove and Reconstruct Curb & Gutter (C-8) (with VAC Slot $45.00 1,065 LF 0 LF 1,065 LF $47,925.00 $0.00 $47,925.00 $7,560.00 Pave) 6 1,500 LF Remove and Reconstruct Curb, Gutter Plate, & AC (at $0.00 0 LF 0 LF 0 LF $0.00 $0.00 $0.00 $0.00 Wheelchair Ramp ocations 7 30,000 SF Concrete Sidewalk 4" P.C.C./ 4" C.M.B $6.00 29,112 SF 0 SF 29,112 SF $174,672.00 $0.00 $174,672.00 $180,000.00 8 5,000 SF Concrete Sidewalk 6" P.C.C./ Native at Park locations only) $8.00 2,023 SF 0 SF 2,023 SF $16,184.001 $0.00 $16,184.00 $40,000.00 9 4,275 SF Concrete Driveway/Driveway Driveway/DrivewayApproach $8.00 9,305 SF 0 SF 9,305 SF $74,440.00 $0.00 $74,440.00 $34,200.00 10 1 25 TON jMiscellaneous AC Pavement $150.00 0 TON 0 TON 0 TON $0.00 $0.00 $0.00 $3,750.00 11 95 LF Horizontal Curb Cut $50.00 0 LF 0 LF 0 LF $0.00 $0.00 $0.00 $4,750.00 12 8,200 SF Remove and Reconstruct Concrete Cross Gutter, Spandrel $12.00 5,619 SF 0 SF 5,619 SF $67,428.00 $0.00 $67,428.00 $98,400.00 Local Depression and Concrete Pad 13 1 FA Additional Work Items $50,000.00 36% FA 0% FA 36% FA $18,280.00 $0.00 $18,280.00 $50,000.00 C01 Parkway Repair (ZONE 1- Gleneagles Terrace, Aviemore Terrace, Sea Bluff $50,000.00 Drive, Balmoral Place) 14.1 697 LF Remove and Reconstruct Curb & Gutter (C-6) (6" CMB with a $50.00 LF 697 LF 697 LF $0.00 $34,850.00 $34,850.00 3' AC Slot Pave) 14.2 126 LF Remove and Reconstruct Curb & Gutter (C-8) (6" CMB with a $55.00 LF 126 LF 126 LF $0.00 $6,930.00 $6,930.00 3' AC Slot Pave) 14.3 1,600 SF Concrete Drivewav/DrivewavApproach $8.25 SF 1,612 SF 1,612 SF $0.00 $13,299.00 $13,299.00 14.4 7 TON Miscellanoue AC $150.00 TON 7 TON 7 TON $0.001 $1,050.001$1,050.001 PROJECT TOTAL: 1 $569,259.001 $56,129.001 $625,388.00 $625,430.00