Loading...
HomeMy WebLinkAbout19 - OB-1 - Citywide Parkway Concrete Repair and New - 9/5/2017CITY COUNCIL AGENDA REPORT MEETING DATE: SEPTEMBER 5, 2017 ITEM NUMBER: OB -1 SUBJECT: CITYWIDE PARKWAY CONCRETE REPAIR AND NEW SIDEWALK CONSTRUCTION PROJECT - CITY PROJECT NO. 14-12 DATE: AUGUST 20, 2017 FROM: PUBLIC SERVICES DEPARTMENT / ENGINEERING DIVISION PRESENTATION BY: RAJA SETHURAMAN, PUBLIC SERVICES DIRECTOR FOR FURTHER INFORMATION CONTACT: BALTAZAR MEJIA, CITY ENGINEER, (714) 754-5335 RECOMMENDATION: 1. Accept the work performed by C.J. Concrete Construction Inc. and authorize the City Clerk to file the Notice of Completion. 2. Release the Labor and Material Bond seven (7) months after the filing date; release the Faithful Performance Bond one (1) year after the filing date; and release the retention monies 35 days after the Notice of Completion filing date. BACKGROUND: On February 17, 2015, a construction contract in the amount of $575,430.00 was awarded to C.J. Concrete Construction, Inc., 10142 Shoemaker Avenue, Santa Fe Springs, California, 90670, for the repair of Parkway Concrete adjacent to streets scheduled to be rehabilitated and the construction of new sidewalk at specified locations. The project scope was specified in the contract documents and consisted of reconstruction of sidewalks, curb and gutter, cross gutters, spandrels, curb ramps, driveway approaches, and other incidental work needed to complete the project. Before Improvements After Improvements At the City Council meeting of August 1, 2017, a member of the public presented information pertaining to the condition of some of the parkway areas generally in the vicinity of where the subject contract work took place. After discussion, the Council voted to continue this item to the September 5, 2017 City Council meeting to allow staff time to research the work completed and to make sure all the specified work had been done. ANALYSIS: Staff reviewed all the locations that the contractor was contracted to repair (Attachment 1) and have found them to have been done to City Standards. However, there remained locations within the maintenance areas where existing parkway improvements had been grounded or ramped to provide a safe pedestrian path of travel. This was done in compliance with the Public Services Department parkway maintenance criteria (Attachment 2). One particular location presented by the resident was highlighted due to the existing ramping adjacent to what appeared to be new sidewalk (Attachment 3, 434 Elmhurst Lane) for further analysis. For this location the City had previously (under another contract) reconstructed the curb and gutter adjacent to the Magnolia tree in the parkway and this work required that the roots of the tree be pruned along the length of the new curb and gutter. The tree is healthy and is recovering well but the root structure will need more time for the roots to grow along a different path and anchor itself to the ground. In order to maintain good structural stability of the tree, it is common practice to wait at least five years before additional root pruning on the opposite side can be done as would be the case for this location or the tree would have to be removed. A survey of the rest of the block shows that the Magnolia tree is the predominant tree species and similar conditions are present. City staff attempts to protect existing trees in place and only request approval to remove trees when all other options have been exhausted. The City's Maintenance Division works extensively to maintain a safe path of travel by grinding or ramping that has reduced the number of claims to very low numbers. The balance of the locations (Attachment 3) presented by the resident generally fall into one of three categories: 1) Properties on streets not included in the original project scope but have since been temporarily ramped. These locations will be incorporated into the next parkway maintenance project which is currently under design. 2) Locations that do not meet the established parkway criteria for removal. These locations will be ground flush under separate contract and monitored for inclusion in a future parkway project when they meet established removal criteria. 3) Parkway drain at Wellesley Lane Cul-de-sac. This location requires a new parkway drain to be designed and includes work that is outside of the scope of the contracted services provided under this maintenance project. This work is scheduled to be performed under separate contract. The work required by the contract documents was completed on May 10, 2017, to the satisfaction of the City Engineer, with a final contract cost of $625,388.00. A report of the final costs is included herein as Attachment 4. A summary of the costs is as follows: Original Contract Cost: $ 575,430.00 Change Order No. 1: $ 50,000.00 Final Quantity Adjustments: ($ 42.00) Final Contract Cost: $ 625,388.00 I• The change order was for additional parkway locations added to the contract over the original project scope. The final contract price reflects a nine percent (9%) increase to the original contract as a result of the change order and final quantity adjustments. As of this date, there are no Stop Notices filed against the monies due to C.J. Concrete Construction Inc. ALTERNATIVES CONSIDERED: There were no alternatives considered for this item. FISCAL REVIEW: This project was funded with Measure M funds, Capital Improvement funds, and Gas Tax revenues. LEGAL REVIEW: There is no legal review required on this item. CONCLUSION: The Citywide Parkway Concrete Repair Project and New Sidewalk Construction Project, City Project 14-12, has been completed to the satisfaction of the City Engineer. It is recommended that the City Council authorize staff to file the Notice of Completion; release the remaining retention monies 35 days after the Notice of Completion filing date; and release the bonds accordingly. RAJA SETHURAMAN Public Services Director BALTAZAR MEJIA City Engineer ATTACHMENTS: 1 — Location Maps 2 — Parkway Maintenance Criteria 3 — Maintenance Area 10 — Example of Ramped Sidewalk 4 — Cost Summary DISTRIBUTION: City Manager Assistant City Manager City Attorney City Clerk Staff File 3 �N,fth CITY OF COSTA MESA ATTACHMENT 1 N.T.S. Public Services/Engineering ON PARSONS __e2 ILI SI.. "OUGO DARRELL CAPITAL ST. wum f` N`l SENATE ST, 1K55 ST. IT (j VICTORIA m.w VISTA WAD" P1 PARK PINE CA REAMS.. -1 19T. 11 [ ------------- '� T. !3T. WILLO OR COSTA MESA PARK jPARX DR. L ST PARKWAY CONCRETE REPAIR AND NEW SIDEWALK CONSTRUCTION PROJECT #14-12 (AS -BUILT) =PARKWAY REPAIR LOCATIONS WNEW SIDEWALK LOCATIONS — MAINTENANCE AREAS Poge 1 of 4 0! CITY OF COSTA MESA N.T.S. Public Services/Engineering ATTACHMENT 1 PARKWAY CONCRETE REPAIR AND NEW SIDEWALK CONSTRUCTION PROJECT #14-12 (AS -BUILT) =PARKWAY REPAIR LOCATIONS MAINTENANCE AREAS 5 Page 2 of 4 CITY OF COSTA MESA North) N.T.S. ---� Public Services/Engineering ATTACHMENT 1 PARKWAY CONCRETE REPAIR AND NEW SIDEWALK CONSTRUCTION PROJECT #14-12 (AS -BUILT) =PARKWAY REPAIR LOCATIONS NEW SIDEWALK LOCATIONS — MAINTENANCE AREAS 0 Page 3 of 4 or CITY OF COSTA MESA ATTACHMENT 1 N.T.S. Public Services/Engineering BAKER ST 0 o 0 o u � KAR Sl. F'1jGT vi 51 CLAR rr N [1R. u `' •[ J r VN E1iCpA 51. IryIIIIIT SANWA) RB, 44�PP...UULLIILIIFFWWllllII n cAUINn � �� I:L ffiulNp SMON(MA PSP. ,'P7K1r+A LIJ, 1 SN VAMON 51. ra C. a y a ` P r 20 f r DSM Hi CL � x i'k ESlpKI 3 PFi SlRIO 50. TMNKLE ZIP PARK c AS[L I]l G��n AN V � Nk pR. ti .w° _....... ................. / PARKWAY CONCRETE REPAIR AND NEW SIDEWALK CONSTRUCTION PROJECT #14-12 (AS -BUILT) =PARKWAY REPAIR LOCATIONS — MAINTENANCE AREAS h� 7 Page 4 of 4 PARKWAY PROJECT #14-12 (AS -BUILT QUANTITIES) BID ITEMS 4 1 2 3 4 5 R/R R/R R/R R/R R/R R/R CONCRETE CURB & CONCRETE CURB & CURB, SIDEWALK GUTTER CURB & GUTTER CURB & GUTTER GUTTER CURB & GUTT 4" PCC / 4" C-6 G8 THICKENED C-6 C-8 CMB TAC SLOT TAC SLOT GUTTER PLATE VAC SLOT VAC SLOT L.F. L.F. L.F. L.F. L.F. Aoce PARKS ONLY L.F 6 7 8 9 10 11 RIR R/R R/R R/R SPANDREL WORK 48 CONCRETE CONCRETE CONCRETE a m CURB, SIDEWALK SIDEWALK DRIVEWAY / MISC HORIZONTAL GUTTER 4" PCC / 4" 6" PCC / I DRIVEWAY 16 PLATE, CMB NATIVE ' APPROACH PAVEMENT CURB CUT AC (@ RAMPS) 12 PARKS ONLY L.F S.F- S.F ST TON L.F. I 12 13 RIR 32 X -GUTTER ADDITIONAL SPANDREL WORK 48 ITEMS S -F. F.A. a m Lu � 1123 AVIEMORE TER 32 J 2090 BALMORAL PL 49176 1137 GLENEAGLES TER 0 48 v J d 32---.._-_--... a m 1157 GLENEAGLES TER 1119 AVIEMORE TER TOTAL 110 0 0 0 0 0 522 0 0 0 0 95 J 1161 GLENEAGLES TER 16 1133 GLENEAGLES TER 44 TOTAL 1131 AVIEMORE TER 0 0 0 01 87 1 0 0 0 0 1 0 TOTAL 12 0 0 1 0 0 1 0 156 0 0 1 0 0 1141 AVIEMORE TER 34 142 Lu a TOTAL 66 0 0 1 0 0 0 202 0 0 0 0 Lu 1086 GLEN CIR 2087-2095 BALMORAL PL 61 0 346 J 2090 BALMORAL PL 49176 1137 GLENEAGLES TER �w 00 48 v J d 10 a m 1157 GLENEAGLES TER 64 TOTAL 110 0 0 0 0 0 522 0 0 0 0 Lu 1086 GLEN CIR 1125 GLENEAGLES TER 39 1094 GLEN CIR 1137 GLENEAGLES TER 48 v 1156 GLENEAGLES TER 10 z 1157 GLENEAGLES TER 64 w 1185 GLENEAGLES TER_ 95 J 1161 GLENEAGLES TER c� 1133 GLENEAGLES TER 44 TOTAL 0 0 0 0 01 87 1 0 0 0 0 1 0 City of Costa Mesa Page 1 08/29/2017 1125 GLENEAGLES TER 32 1137 GLENEAGLES TER 16 w 1156 GLENEAGLES TER 10 1157 GLENEAGLES TER 64 Lu 1185 GLENEAGLES TER_ 95 O 1161 GLENEAGLES TER a Lu z 1133 GLENEAGLES TER 44 w J O 1120 GLENEAGLES TER 7 TOTAL 52 0 0 1 0 0 1 0 156 0 0 1 0 0 City of Costa Mesa Page 1 08/29/2017 PARKWAY PROJECT #14-12 (AS -BUILT QUANTITIES) City of Costa Mesa Page 2 9 08/29/2017 BID ITEMS 1 2 3 4 5 6 7 8 9 10 11 12 13 R/R CURB & GUTTER C-6 TAC SLOT L.F. R/R CURB & GUTTER C-8 TAC SLOT L.F. R/R CURB & GUTTER THICKENED GUTTER PLATE L.F. R/R CURB & GUTTER C-6 VAC SLOT L.F. R/R CURB & GUTTER C-8 VAC SLOT L.F. R/R CURB, GUTTER PLATE, AC (Q RAMPS) L.F R/R CONCRETE SIDEWALK 4" PCC / 4" CMB S.F R/R CONCRETE SIDEWALK + 6" PCC / NATIVE I PARKS ONLY S.F. RIR CONCRETE DRIVEWAY / DRIVEWAY APPROACH S.F- MISC PAVEMENT TON HORIZONTAL CURB CUT L.F. RIR X -GUTTER SPANDREL S.F. ADDITIONAL WORK ITEMS F.A. w OPPOSITE 2098 VALLEY RD > O 1136 SEA BLUFF DR 17 ..... — ..... — ...- m 1140-1144 SEA BLUFF DR 84 7 U- LL 2095 BALMORAL PL SEA BLUFF DR SIDE m2095 VALLEY RD SEA BLUFF DR 409 a _ ...._ 2098 VALLEY RD SEA BLUFF DR) 62 twig 1128 SEA BLUFF DR TOTAL 163 0 0 0 0 0 409 7 0 0 0 1106-1108 VALLEY CIR 67 J1100-1102 VALLEY CIR 94 I� 1107-1101 VALLEY CIR 105 V 1114 RIDGECREST CIR VALLEY RD SIDE 38 Valley Rd side TOTAL 266 38 0 0 0 0 0 0 0 0 0 D 0 2094 VALLEY RD 104 } 2066 VALLEY RD w J J Q TOTAL 0 0 0 0 0 104 0 0 0 0 0 1796 ANAHEIM AVE 58 526 1780 ANAHEIM AVE 28 240 280 1776 ANAHEIM AVE 31 76 200 596 PARK DR ANAHEIM AVE SIDE 23 550 140 597 PARK DR ANAHEIM AVE SIDE 22 230 n 1762 ANAHEIM AVE 24 440 204 Lua 1781 ANAHEIM AVE 116 a 1769 ANAHEIM AVE 126 174 1763 ANAHEIM AVE 16 1753-1755 ANAHEIM AVE 108 1747 ANAHEIM AVE AUTO SERVICE) 50 591 395 250 629 TERMINAL WAY 55 230 503 453 1731 ANAHEIM AVE(MICHAEL'S) 437 TOTAL 0 0 0 291 0 0 3,670 0 1.912 0 0 703 0 City of Costa Mesa Page 2 9 08/29/2017 PARKWAY PROJECT #14-12 (AS -BUILT QUANTITIES) Q 401 HAMILTON ST BID ITEMS 4 1 2 3 4 5 6 7 8 9 10 11 12 13 0 0 0 145 0 0 901 0 513 0 0 761 0 0 0 20 20 0 0 266 j 0 0 0 0 0 0 172 R/R R/R R/R R/R R/R R/R R/R R/R R/RI R/R CURB & CURB & CONCRETE CONCRETE CONCRETE GUTTER CURB & GUTTER CURB & GUTTER GUTTER CURB & GUTTER CURB, SIDEWALK SIDEWALK DRIVEWAY / MISC HORIZONTAL X -GUTTER ADDITIONAL GUTTER 4" PCC / 4" 6" PCC / DRIVEWAY C-6 C-8 THICKENED C-6 C-8 PLATE, CMB NATIVE APPROACH PAVEMENT CURB CUT SPANDREL WORK ' AC (@ I TAC SLOT TAC SLOT GUTTER PLATE 1' AC SLOT 1' AC SLOT RAMPS) PARKS ONLY ITEMS L.F. L.F. L.F. L.F. L.F. L.F S.F S.F. S.F. TON L.F. S.F F.A. 126 23RD ST 20 68 N 122-124 23RD ST 60 41 64 _ a 114 23RD ST 268 W a 2300 NEWPORT BLVD FEEDBARN 84 951 313 127-141 23RD ST 23 472 207 145 23RD ST 69 TOTAL 0 0 80 285 0 0 1,691 0 584 0 0 0 0 2108 STERLING AVE 184 2120 STERLING AVE 160 52 2128-2136 STERLING AVE 20 68 352 386 Q 2115-2111 STERLING AVE 10 19 116 TOTAL 0 0 30 87 0 0 812 0 438 0 0 0 0 Q 401 HAMILTON ST 20 20 2126 THURIN AVE 84 Q 2127 THURIN AVE. 145 204 241 Lu w 2135 THURIN AVE. 153 272 Q THURIN AVE/RALCAM PL 460 761 66 TOTAL 0 0 0 145 0 0 901 0 513 0 0 761 0 Q 401 HAMILTON ST 20 20 49 128 Lu 393 HAMILTON ST w 460 a TOTAL 0 0 0 49 0 0 588 1 0 0 0 0 0 0 I 2214 RUTGERS DR 20 20 r 2222 RUTGERS DR 56 w 2230 RUTGERS DR 68 Q 2223 RUTGERS DR 76 Q 2211 RUTGERS DR 66 TOTAL 0 0 20 20 0 0 266 j 0 0 0 0 0 0 I City of Costa Mesa Page 3 08/29/2017 2527 BOWDOIN PL 26 80 105 r 2515 VASSAR PL 120 2516 BOWDOIN PL 94 70 247 2516 VASSAR PL 24 16 150 2511 BOWDOIN PL 176 106 Q 2507 BOWDOIN PL 197 TOTAL 0 0 0 47 r 0 0 353 0 260 0 2512 BOWDOIN PL 172 TOTAL 0 0 0 120 0 0 695 0 458 0 0 0 0 City of Costa Mesa Page 3 08/29/2017 2528 VASSAR PL 23 110 r 2515 VASSAR PL 120 2516 VASSAR PL 24 16 150 Q 2507 VASSAR PL 184 2524 VASSAR PL 33 TOTAL 0 0 0 47 r 0 0 353 0 260 0 0 0 0 City of Costa Mesa Page 3 08/29/2017 PARKWAY PROJECT #14-12 (AS -BUILT QUANTITIES) City of Costa Mesa Page 4 06/29/2017 BID ITEMS 1 2 3 4 5 6 7 8 9 10 11 12 13 R/R CURB & GUTTER C-6 TAC SLOT L.F. R/R CURB & GUTTER G8 TAC SLOT L.F. R/R CURB & GUTTER E THICKENED `I GUTTER PLATE L.F. R/R CURB & GUTTER C-6 1- AC SLOT L.F. R/R CURB & GUTTER C-8 VAC SLOT L.F. R/R CURB, GUTTER PLATE, AC (@ RAMPS) L.F. R/R CONCRETE SIDEWALK 4" PCC / 4" CMB S.F. R/R CONCRETE SIDEWALK 6" PCC / NATIVE PARKS ONLY S.F. R/R CONCRETE DRIVEWAY / DRIVEWAY APPROACH S.F. MISC PAVEMENT TON HORIZONTAL CURB CUT L.F. R/R X -GUTTER SPANDREL S.F ADDITIONAL WORK ITEMS F.A. 241 HANOVER DR ON COLUMBIA i ! 26 200 110 BUCKNELL RD/COLUMBIA DR ! 310 74 231 208-212 WELLESEY LN 128 219 WELLESEY LN _ 184 0 223 WELLESEY LN 136 w 2547 COLUMBIA DR 24 250 a 2550 COLUMBIA DR 63 382 2563 COLUMBIA DR 33 70 2572 COLUMBIA DR 48 2575 COLUMBIA DR 2520 COLUMBIA DR. 20 63 80 230 TOTAL 0 0 20 194 63 0 1970 0 184 0 0 231 0 201 PRINCETON DR 52 207 PRINCETON DR 140 208 PRINCETON DR 52 212-218 PRINCETON DR 176 222 PRINCETON DR 36 229 PRINCETON DR 20 60 394 258 239 PRINCETON DR 20 40 318 110 554 248 PRINCETON DR 23 72 265 PRINCETON DR 140 259 PRINCETON DR 60 276 PRINCETON DR 23 44 281 PRINCETON DR 33 291 PRINCETON DR 74 188 322 PRINCETON DR 61 0 Q 352 PRINCETON DR 160 w a 355 PRINCETON DR 96 a 356 PRINCETON DR 84 84 388 PRINCETON DR 34 392 PRINCETON DR 70 397 PRINCETON DR 61 176 400 PRINCETON DR 62 401 PRINCETON DR 43 407 PRINCETON DR 70 416 PRINCETON DR 128 426 PRINCETON DR 86 437 PRINCETON DR 252 438-442 PRINCETON DR 60 141 228 454 PRINCETON DR 72 457 PRINCETON DR 14 2585 GREENBRIAR ON PRINCETON) -110 128 333 WESTBROOK PL 134 212 TOTAL 0 0 40 46 690 0 3,409 0 456 0 0 812 0 City of Costa Mesa Page 4 06/29/2017 0 I:2 City of Costa Mesa PARKWAY PROJECT #14-12 (AS -BUILT QUANTITIES) BID ITEMS 41 1 2 3 4 5 6 7 8 9 10 11 12 13 kRNEGIE AVE/BUCKNELL F 2502-2510 CARNEGIE AVE 2510-2518 CARNEGIE AVE 2526 CARNEGIE AVE 2532 CARNEGIE AVE 2531 COLBY PL 2518 COLBY PL 2513 COLBY PL 2525 COLBY PL 2507 COLBY PL 2530 COLBY PL 2531 LEHIGH PL 2530 LEHIGH PL 2531 LEHIGH PL UCKNELL RD/FORDHAM D 2531 FORDHAM DR 402 BUCKNELL RD 420 BUCKNELL RD 424 BUCKNELL RD 426 BUCKNELL RD TOTAL R/R R/R R/R R/R R/R R/R R/R R/R R/R 2528 VASSAR PL - 2527 BOWDOIN PL R/R CURB & CURB & 110 2527 BOWDOIN PL CONCRETE CONCRETE CONCRETE 104 2528 BOWDOIN PL 67 26 96 GUTTER CURB & GUTTER CURB & GUTTER GUTTER CURB & GUTTER CURB, SIDEWALK SIDEWALK DRIVEWAY t MISC HORIZONTAL X -GUTTER ADDITIONAL 20 230 104 2528 DUKE PL 36 18 GUTTER 4" PCC / 4" 6" PCC / DRIVEWAY 41 56 195 20 75 C-6 C-8 THICKENED C-6 C-8 PLATE, CMB NATIVE APPROACH PAVEMENT CURB CUT SPANDREL WORK 263 BUCKNELL RD 126 1,106 216 40 AC (@ 41 310 2528 LITTLETON PL 31 80 TAC SLOT TAC SLOT GUTTER PLATE VAC SLOT VAC SLOT RAMPS) PARKS ONLY 164 15 12 ITEMS 414 L.F. L.F. L.F. L.F. L.F. L.F S.F. S.F S.F. TON LF S.F. F.A. kRNEGIE AVE/BUCKNELL F 2502-2510 CARNEGIE AVE 2510-2518 CARNEGIE AVE 2526 CARNEGIE AVE 2532 CARNEGIE AVE 2531 COLBY PL 2518 COLBY PL 2513 COLBY PL 2525 COLBY PL 2507 COLBY PL 2530 COLBY PL 2531 LEHIGH PL 2530 LEHIGH PL 2531 LEHIGH PL UCKNELL RD/FORDHAM D 2531 FORDHAM DR 402 BUCKNELL RD 420 BUCKNELL RD 424 BUCKNELL RD 426 BUCKNELL RD TOTAL 758 104 862 1 0 2527 VASSAR PL 60 500 168 20 86 168 2528 VASSAR PL - 2527 BOWDOIN PL 110 2519 VASSAR PL 237 110 2527 BOWDOIN PL 80 76 92 104 2528 BOWDOIN PL 67 26 96 110 2527 ANDOVER PL 20 44 25 99 2528 ANDOVER PL 35 322 58 2527 DUKE PL 20 230 104 2528 DUKE PL 36 18 136 110 2515 LOYOLA PL 20 41 56 195 20 75 21 282 2519 LOYOLA PL 71 13 278 174 2527 LOYOLA PL 96 230 263 BUCKNELL RD 126 1,106 216 40 68 41 310 2528 LITTLETON PL 31 80 2525 LITTLETON PL 36 2525 LITTLETON PL 164 15 12 414 2519 LITTLETON PL 168 72 0 0 95 485 312 0 4.036 0 1,253 0 0 758 104 862 1 0 2527 VASSAR PL 232 168 2528 VASSAR PL 348 2528 VASSAR PL - 2527 BOWDOIN PL 0 2519 VASSAR PL 184 245 2527 BOWDOIN PL 80 23 92 2528 BOWDOIN PL 26 80 110 2527 ANDOVER PL 20 44 230 2528 ANDOVER PL 35 322 2527 DUKE PL 20 230 2528 DUKE PL 18 298 2515 LOYOLA PL 20 41 44 195 2518 LOYOLA PL 21 2519 LOYOLA PL 20 13 2527 LOYOLA PL 64 263 BUCKNELL RD 184 2529 LITTLETON PL 41 600 2528 LITTLETON PL 31 570 2525 LITTLETON PL 124 2525 LITTLETON PL 178 2524 LITTLETON PL 100 2519 LITTLETON PL 168 72 2518 LITTLETON PL 336 is Page 5 08/29/2017 PARKWAY PROJECT #14-12 (AS -BUILT QUANTITIES) BID ITEMS 4 1 2 3 4 5 6 7 8 9 10 11 12 13 R/R CURB & GUTTER C-6 TAC SLOT L.F. R/R CURB & GUTTER C-8 TAC SLOT L.F. R/R CURB & GUTTER THICKENED GUTTER PLATE L.F. R/R CURB & GUTTER C-6 VAC SLOT L.F. R/R R/R R/R CONCRETE CURB & GUTTER CURB, SIDEWALK GUTTER 4" PCC 14" C-8 PLATE, CMB AC (@ VAC SLOT RAMPS) L.F. L.F. S.F. R/R CONCRETE SIDEWALK 6" PCC / NATIVE PARKS ONLY S.F. R/R CONCRETE DRIVEWAY / DRIVEWAY APPROACH S.F. MISC PAVEMENT TON HORIZONTAL CURB CUT L.F. R/R X -GUTTER SPANDREL S.F ADDITIONAL WORK ITEMS F.A. Q 2513 LITTLETON PL 144 230 231 241 BUCKNELL RD 250 BUCKNELL RD 20 20 49 28 124 40 254 BUCKNELL RD 260 BUCKNELL RD 104 264 BUCKNELL RD 112 268 BUCKNELL RD 124 272 BUCKNELL RD 13 88 278 BUCKNELL RD 42 288 BUCKNELL RD 20 9 292 BUCKNELL RD 120 296 BUCKNELL RD 88 20 300 BUCKNELL RD 108 312 BUCKNELL RD 120 316 BUCKNELL RD 136 328 BUCKNELL RD 20 11 160 168 332 BUCKNELL RD 224 182 342 BUCKNELL RD 72 126 324 BUCKNELL RD 56 64 338 BUCKNELL RD 20 10 76 68 320 BUCKNELL RD 80 64 350 BUCKNELL RD 80 354 BUCKNELL RD 80 216 380 BUCKNELL RD 116 64 402 BUCKNELL RD 34 160 TOTAL 0 0 240 509 0 0 6,882 0 1,906 0 0 231 0 RUTGERS DR/WAKE FOREST RD 2316 RUTGERS DR 290 379 N 2372 RUTGERS DR 60 2391 RUTGERS DR 52 tQ Q 2381 RUTGERS DR 72 2365 RUTGERS DR 64 2355 RUTGERS DR 320 2317 RUTGERS DR 338 379 TOTAL 0 0 0 0 0 0 1,196 0 0 0 0 758 0 276 VILLANOVA RD 50 334 VILLANOVA RD 100 N 356 VILLANOVA RD 76 2390 CORNELL DR 20 8 Q 2390 RUTGERS 13 315 VILLANOVA RD 180 272 VILLANOVA (SCHOOL) 520 TOTAL 0 0 20 21 0 0 926 0 0 0 0 0 0 City of Costa Mesa Page 6 08/29/2017 PARKWAY PROJECT #14-12 (AS -BUILT QUANTITIES) BID ITEMS 4 1 2 3 4 5 6 7 8 9 10 11 39 230 R/R CURB & GUTTER C-6 TAC SLOT L.F. R/R CURB & GUTTER C-6 TAC SLOT L.F. R/R CURB & GUTTER THICKENED GUTTER PLATE L.F. R/R CURB& GUTTER C-6 VAC SLOT L.F. R/R CURB & GUTTER C-8 VAC SLOT L.F. R/R CURB, GUTTER PLATE, AC(@ RAMPS) L.F R/R CONCRETE SIDEWALK 4" PCC / 4" CMB S.F R/R CONCRETE SIDEWALK 6" PCC / NATIVE PARKS ONLY S.F R/R CONCRETE DRIVEWAY / DRIVEWAY APPROACH S.F. MISC PAVEMENT TON HORIZONTAL CURB CUT L.F. Q 2268 FORDHAM DR 80 TOTAL 2240 RALEIGH WAY 0 25 214 2228 RALEIGH WAY 14 199 2224 RALEIGH WAY 12 66 Q 2220 RALEIGH WAY 15 104 Lu Q 2210 RALEIGH WAY 48 2198 RALEIGH WAY 31 24 178 2194 RALEIGH WAY 25 143 2225 RALEIGH WAY 29 178 TOTAL 0 0 0 151 0 0 152 0 1.082 0 0 12 R/R X -GUTTER SPANDREL S.F 0 13 ADDITIONAL WORK ITEMS F.A. 0 N 2252 FORDHAM DR 39 230 Q w 360 W WILSON ST 39 230 Q 2268 FORDHAM DR 88 TOTAL 0 0 0 78 0 0 548 0 0 0 0 0 0 City of Costa Mesa Page 7 ``�__ 08/29/2017 ATTACHMENT 2 CITY OF COSTA MESA Department of Public Services/Engineering Division PARKWAY MAINTENANCE CRITERIA Whenever a location is being considered for parkway maintenance, Engineering staff will survey the entire block for other possible locations that may need repair. If other locations are found in need of repair within the same block, they will be made a part of the project, provided funds are available, based on the following criteria. If the relative displacement between two sidewalk slabs is in excess of one and one half inches (1 — 1/2"), the uplifted/depressed portion of the sidewalk will be removed and reconstructed to the nearest weakened plane or expansion joint. 2. When two sidewalk slabs have been displaced relative to each other, from one half inch (1/2") up to and including one and one half inches (1 — '/2"), the displacement shall be ramped or ground flush to provide for a smooth transition to eliminate the tripping hazard. Displacements of less than one half inch (1/2") need not be reworked. The length of the ramp or grind shall vary from a minimum of six inches (6") for a '/2" differential to a minimum of eighteen inches (18") for a one and one half inch (1 — '/2") differential. Sidewalks which are ramped or receive grinding shall be placed on a list for more permanent repairs once all locations meeting the criteria of #1 (above) are completed citywide. 3. Engineering staff will compile a list of areas where grinding or ramping will occur. The Assistant Street Superintendent will schedule this work using City crews prior to award of the maintenance contract. The decision to ramp or grind shall be made by the Assistant Street Superintendent. If City crews cannot accommodate the workload, the grinding and/or ramp work will be included in the contract bid documents by the Engineering Division. 4. Deep root barriers will not be installed if existing concrete improvements are to be left in place. 5. Raised or sunken curb and gutter shall be removed and replaced unless the standing nuisance water does not extend into the asphalt pavement area. In this case, a raised gutter may receive grinding. 6. Existing concrete improvements shall be removed at joints (expansion, cold or weakened plane), where practical. A minimum of six (6) lineal feet of sidewalk or eight (8) lineal feet of curb and gutter shall be removed to avoid floating sections. Undisturbed adjacent sections shall also have a similar minimum length requirement to existing joints. 7. A curb which is depressed adjacent to a driveway apron shall be protected in place provided that water is contained within the concrete gutter and the driveway apron does not necessitate removal. A maximum relative displacement between the curb and the apron of one inch (1") will be allowed when either the apron or the curb has settled/raised. 15 ATTACHMENT 2 8. Sunken sidewalk shall be reconstructed only if there is evidence of water ponding on it and it creates a slipping liability due to algae growth. If a lip or step displacement of one half inch (1/2") or more has formed, and no slipping or ponding occurs, apply Item Nos. 1 and 2 above. 9. No parkway maintenance work will be performed on private property in areas where adjoining private improvements are less than one inch (1") lower or higher than existing sidewalk grade. Existing private improvements and sidewalk may be protected in place as long as a tripping hazard does not exist along the public right-of-way/sidewalk path of travel. When private and public improvements are vertically displaced from each other more than one inch (1"), and the sidewalk and/or driveway meets the removal criteria set herein, a minimum twenty-four inch (24") long section will be reconstructed on private property to provide for an appropriate transition. (Right of entry must be obtained by Public Services staff prior to performance of work.) 10. Damaged homeowner -installed walkways perpendicular to the sidewalk, between the curb and public right-of-way (ROW) line and within the parkway greenbelt area, shall be removed and replaced to a width of four feet (4'), with four inch (4") PCC over four inch (4") CMB when adjacent sidewalk and/or curb/gutter necessitates removal. 11. Concrete (not walkway) within the greenbelt area (between curb and ROW line), which must be removed to facilitate tree removal or sidewalk and/or curb/gutter replacement, shall be replaced with compacted top soil and seeded or sodded as necessary. 12. At corner properties where repairs are done along one frontage per these requirements, the construction may be continued around the corner if needed per this Parkway Maintenance Criteria. The intent is that the corner property undergo repairs on its street frontages only one time. 13. For horizontal separation of existing sidewalk and driveway approaches, reconstruction will be required if existing crack or joint is wider than one inch (1"). Smaller cracks should be filled with epoxy or appropriate filling material to minimize water penetration and liability to the City. 16 Ws, -ms y 1 ATTACHMENT 3 324 Bucknell Rd 372 Bucknell Rd 18 ATTACHMENT 3 IV 2507 Lehigh PI * ,. ter•. '.!� °` :�. 2513 Lehigh PI 19 2512 Lehigh PI 2512 Lehigh PI ri l 2515 Lehigh PI .�S 2519 Lehigh PI 2513 Colby PI ...... ..... 2530 Colby PI N N s " 1. a�•.'. �.-.�' �'- � •.moi. i''� 7 - ..+� _ ? 3��" .. - t � . e�. 0 '►i PARKWAY CONCRETE REPAIR AND NEW SIDEWALK CONSTRUCTION PROJECT #14-12 (AS -BUILT) (AREA 10) 1 12 13 14 LLOOP 2 3 4 3 e 7 T RACT 412 406 490 39651f4 !7r37r 364 DRIVE 1¢a 1 ! 10 11 12 M]FI21 ee2 M so 7s 76 77 76 7S 64 63 62 161 so 5! 59 eT ACT "54 S3 s2 51 sQ 4f T A T 31D .1 330 Sar 3r0 .1'316 119 30f 104 ,7tl❑ ;g6 292 28B 284 2Ta 272 260 264 960 P54 P30 244 S40 234 PPB p!i P/f 2/? 206 P00 HANOVER T DRIVE 341 ,� 3a/ J/L 3/1 sos 301 1 a1r rr1 trr rr3 sial Ars t99 28J r4D a4s r41 1611 tat ttt tN r►3t4748 60 +67 so 69 66 67 d90 71 72 3 I Z 3 4 4344 43 46 TO �tj: ■ a3 62 sl 60 59 56 57 S6 35 34 53 52 BI 510 49 0 4241 40 37 ,a 71 C 66 ��`�c Afro* 451 It �1 64 7 ' 51nf Sot s f 9 gra tf0 rr4 770 r "� tt a/1 rIr .._.� _ GREEN DR. -i a WELLESLEY LN, WESTBROOK Pt 2 • 4 S d 7 • 1 t1J I Off a13 T ars 430 4512 4a6 Ott 4 61 64 4.?f} 441: �0"- -0 PRINCETON - 42 1 463 457 447 441 s!r n 56 1433 lAi IS 17 Id 19 20 21 55 ' J 21 26 2'S 24 23 22 m n 54 462 ".get446 44P 436 (SWARTHMORE LN. ti 4S1 443 441 436 M2 y 35 461 4$5 It 6d 51 40 25 ! 43 28 29 30 31 32 33 „ 26 50 SO 36 37 36 35 23 22 14 7 20 460 456 ti 49 17 E36 MId 450 4 -f 41 44-9143 J4 ljoll ELMHURST LN. 46 1 SOOL 457 451" 447 443 t9 14 rTf 46 b 47 ret 4 40 41 42 43 4i 45 46 Iia 145 OZ 7 13e 135 n '^ - �y a 426 42 1 12 13 14 LLOOP 2 3 4 3 e 7 T RACT 412 406 490 39651f4 !7r37r 364 DRIVE 1¢a 1 ! 10 11 12 M]FI21 ee2 M so 7s 76 77 76 7S 64 63 62 161 so 5! 59 eT ACT "54 S3 s2 51 sQ 4f T A T 31D .1 330 Sar 3r0 .1'316 119 30f 104 ,7tl❑ ;g6 292 28B 284 2Ta 272 260 264 960 P54 P30 244 S40 234 PPB p!i P/f 2/? 206 P00 HANOVER T DRIVE 341 ,� 3a/ J/L 3/1 sos 301 1 a1r rr1 trr rr3 sial Ars t99 28J r4D a4s r41 1611 tat ttt tN r►3t4748 60 +67 so 69 66 67 d90 71 72 3 I Z 3 4 4344 43 46 TO �tj: ■ a3 62 sl 60 59 56 57 S6 35 34 53 52 BI 510 49 0 4241 40 37 ,a 71 C 66 ��`�c Afro* 451 It �1 64 7 ' 51nf Sot s f 9 gra tf0 rr4 770 r "� tt a/1 rIr .._.� _ GREEN DR. -i a WELLESLEY LN, WESTBROOK Pt LEGEND: Jos yos 301 207 t1J I Off a13 BUCKNELL - ars RD. toy BUCKNELL n SIJ ti 32 35 36 It 38 39 40 25 26 43 28 27 26 24 23 22 14 7 20 LL 16 17 E36 MId 5106 ljoll rsf 294 1 SOOL 5111 t9 14 rTf d�I see ret 4 W Iia 145 13e 135 n O al w 2Q 15 �. 24 27 a ae 60 a w 6O' ti IID n Z �• 3 W ry 1+14 w a m a 77 a e 21 tF 23'29 a � 149 2 `" 143 ® ti 140 W ti 76 "+ n 22 17 �3 22 M 9 o a 1 U 150 141 ry Si 75 a ti m 18 Z3 N 4 t 130 m 0 142 Q C3a nh ❑ o ❑ n i9� ri 2031 a 460 440 60,?+ h 4i v 372 N 61 w 8 FAIR LEGEND: Jos yos 301 207 t1J I Off a13 ass ars mo toy n ti 32 35 36 37 38 39 40 41 42 43 28 27 26 24 23 22 2I 20 19 16 17 3/t 5106 ljoll rsf 294 1 SOOL 5111 81! rTf rrn see ret d 47 3 , MAU ?7F-- 23 2212 24 .�I o 21 25 20 a J h 26 19 � rr3 �� x/■.. t13 32 33 3427U L-31 bV I rt2 2/! S/t t0f SOS DRIVE '9 PHOTO LOCATIONS — — SIDEWALK REPAIR LOCATIONS (SEE ATTACHED FOR AS—BUILT QUANTITIES) CURB & GUTTER REPAIR LOCATIONS (SEE ATTACHED FOR AS—BUILT QUANTITIES) SCALE: NTS a5 CITY OF COSTA MESA DATE: 06121117 CJ CONSTRUCTION INC. 10142 SHOEMAKER AVENUE SANTA FE SPRINGS, CA 90670 PROJECT: 2014-2015 CITYWIDE PARKWAY CONCRETE REPAIR AND NEW SIDEWALK PROJECT CITY PROJECT 14-12 HEM BID UNIT PREVIOUS QUANTITY TOTAL+]UANTFTY PREVIOUS AMOUNT TOTAL I CONTRACT NO OUANTnY DESCRIPTION PRICE QUANTITY THIS ESTIMATE TO DATE AMOUNT THIS EST TO DATE PRICE 1 1,830 LF Remove and Reconstruct Curb and Gutter (C-6) (with 3' AC $44.00 0 LF 0 LF 0 LF $0.00 $0.00 $0.00 $80,520.00 Slot Pave 2 42 LF Remove and Reconstruct Curb and Gutter (C-8) (with TAC $50.00 0 LF 0 LF 0 LF $0.00 $0.00 $0.00 $2,10000 Slot Pave 3 427 LF Remove and Reconstruct Curb & Thickened Gutter (101 both $50.00 601 LF 0 LF 601 LF $30,050.00 $0.00 $30,050.00 $21,350.00 side of e)dsting treel 4 1,320 LF Remove and Reconstruct Curb & Gutter (C-6) (with TAC Slot $40.00 3,507 LF 0 LF 3,507 LF $140,280.00 $0.00 $140,280.00 $52,800.00 Pavel 5 168 LF Remove and Reconstruct Curb & Gutter (C-8) (with 1' AC Slot $45.00 1,065 LF 0 LF 1,065 LF $47,925.00 $0.00 $47,925.00 $7,560.00 Pave) 6 1,500 LF Remove and Reconstruct Curb, Gutter Plate, & AC (at $0.00 0 LF 0 LF 0 LF $0.00 $0.00 $0.00 $0.00 Wheelchair Ramo locations 7 30 000 SF Concrete Sidewalk (4" P.C.C./ 4" C.M.B) $6.00 29r112 SF 0 SF 29,112 SF $174,672.00 $0.00 $174,672.00 $180,000.0c 8 5,000 SF Concrete Sidewalk (6" P.C.C./ Native) at Park locations only) $800 2,023 SF 0 SF 2,023 SF $16,184.00 $0.00 $15,184.00 $40.000-00 9 4,275 SF Concrete Driveway/Driveway Driveway/DrivewayApproach $800 9,305 SF 0 SF 9,305 SF $74,440.00 0.00 $74.440.00 $34,200.00 10 25 TON Miscellaneous AC Pavement $150.00 0 TON 0 TON 0 TON $0.00 50.00 $0.00 $3,750.00 11 95 LF Horizontal Curb Cut $50.00 0 LF 0 LF 0 LF $0.00 $0.00 $0.00 $4,750.00 12 8,200 SF Remove and Reconstruct Concrete Cross Gutter, Spandrel $12.00 5,619 SF 0 SF 5,619 SF $67,428.00 $0.00 $67,428.00 $98,400.00 Local Deoression and Concrete Pad 13 11 FA Additional Work Items $50,000.00 36% FA 0% FA 36% FA $18,280.00 $0.00 $18,280.00 $50,000.00 Parkway RePalr (ZONE 1- Gior-Mles Tarrace, Avlemore Terrace, Sea StuffCOi $50,000.00 Drive, Balmoral Piaco} 14.1 697 LF Remove and Reconstruct Curb & Gutter (C-6) (6" CMB with a $50.00 LF 697 LF 697 LF $0.00 $34,850.00 $34,850.00 TAC Slot Pave) 14.2 126 1 LF Remove and Reconstruct Curb & Gutter (C-8) (6" CMB with a $55.00 LF 126 LF 126 LF $0.00 $6,930.00 $6,930.00 3' AC Slot Pave) T4.31 1.600 1 SF Concrete Driveway/Driveway Approach ;8.25 Sr- 1,6_12_ SF 1.612 SF $0.00 $13.299.00 $13 299.00 14.41 7 I TON Miscellanoue AC $1.50.00 TON 7 TON 7 TON 50.0 .00 $1 050.1)0 PROJECT TOTAL: ___L1,050 $569.259.00 $56,129.00 $625,388.001 $625.430.00 N a�