HomeMy WebLinkAbout97-67 - Approving Certain Energy Conservation MeasuresRESOLUTION NO. 91- 62
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF COSTA MESA, CALIFORNIA, APPROVING CERTAIN
ENERGY CONSERVATION MEASURES, AUTHORIZING
EXECUTION OF AN AGREEMENT WITH LIGHTING
TECHNOLOGY SERVICES, INC., AND MAKING OTHER
DETERMINATIONS FOR RETROFITTING OF LIGHTING
AT THE CIVIC CENTER.
THE CITY COUNCIL OF THE CITY OF COSTA MESA DOES HEREBY
RESOLVE AS FOLLOWS:
WHEREAS, the City Council of the City of Costa Mesa (the "City") is
authorized, pursuant to Sections 4217.10 through 4217.18 of the California
Government Code (the "Act") to enter into energy conservation contracts pursuant
to which the City may acquire and finance equipment and services to reduce energy
use or to make a more efficient use of energy; and
WHEREAS, pursuant to the Act, the City proposes to enter into a professional
services agreement with Lighting Technology Services, Inc., as set forth in Exhibit 1,
incorporated herein by this reference; and
WHEREAS, the energy conservation measure set forth in the proposed
agreement by and between Lighting Technology Services , Inc., and the City will
result in a projected net cost savings to the City by avoidance of energy that would
have been consumed by the City in the. absence of the project; and
WHEREAS, the City Council of the City of Costa Mesa held a public hearing
with adequate noticing and has considered all public comments;
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Costa
Mesa, California, hereby authorizes the City Manager to execute the agreement with
Lighting Technology Services, Inc.
PASSED AND ADOPTED this 21st day of Jt
ATTEST:
T
Deputy Cit' Jerk of the City of Costa Mesa
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss
CITY OF COSTA MESA )
Mayor of the City of
ROVED AS TO FORM
CITY ATTORPJEY
I, MARY T. ELLIOTT, Deputy City Clerk and ex -officio Clerk of the City Council
of the City of Costa Mesa,' hereby certify that the above and foregoing
Resolution No. 97- &7 was duly and regularly passed and adopted by the said City
Council at a regular meeting thereof held on the 21st day of July, 1997.
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the Seal of
the City of Costa Mesa this 22nd day of July, 1997.
T
Deputy Cit Clerk and ex -officio Clerk of
the City Council of the City of Costa Mesa
a
PROFESSIONAL SERVICES AGREEMENT
THIS AGREEMENT, July .2 11 , 1997, is made by the CITY OF COSTA MESA,
a political subdivisio,`i of the State of California, (CITY) and LIGHTING
TECHNOLOGY SERVICES, INC., a California Corporation (CONSULTANT).
WITNESSETH:
WHEREAS, CITY proposes to have the mentioned firm perform lighting
retrofit and occupancy sensor control in the City Hall and PoliceDepartment
facilities as described in Exhibit "A" of this contract; and
WHEREAS, CONSULTANT represents that it has that degree of specialized
expertise contemplated within California Government Code, Section 37103, and
holds all necessary licenses to practice and perform the services herein
contemplated; and
WHEREAS, CITY and CONSULTANT desire to contract for specific services
in connection with the project described above; and
WHEREAS, no official or employee of CITY has a financial interest, within
the provisions of California Government Code, sections 1090-1092, in the subject
matter of this Agreemeni; and
WHEREAS, the parties desire to set forth their rights, duties and liabilities in
connection with the services to be performed;
NOW, THEREFORE, the parties agree as follows:
1. CONSULTANT shall provide all services described in Exhibit "A" and
shall be paid in accordance with the fee schedule set forth in Exhibit "B"; the work
shall be completed in accordance with the time schedule set forth in Exhibit "C".
Exhibits "A", "B" and "C" are all attached hereto and made a part of this
Agreement.
2. This Agreement constitutes the entire Agreement between the parties
with respect to any matter referenced herein and supersedes any and all other
prior writings and oral negotiations. This Agreement may be modified only in
writing, and signed by the parties in interest at the time of such modification. The
terms of this Agreement shall prevail over any inconsistent provision in any other
contract document appurtenant hereto.
3. The term of thi::; Agreement shall end on December 31, 1997.
4. CONSULTANT shall attend and assist in all coordination meetings
called by CITY.
5. CONSULTANT shall designate a Project Manager who shall represent
it and be its agent in all consultations with CITY during the term of this
Agreement.
6. All original drawings, reports, field and office notes, correspondence,
calculations, maps, and other documents shall be turned over to and become the
property of CITY upon completion of the project. Ten percent (10%) of the
contract amount will be withheld by the CITY until such time as all work under this
Agreement is completed and all of the above-mentioned documents are received
by the CITY.
E
7. No regular employee of CITY will be employed by CONSULTANT
while this Agreement is in effect.
8. In performing this Agreement, CONSULTANT will not engage in, nor
permit its agents to engage in, discrimination in employment of persons because of
their race, religion, calor, national origin, ancestry, physical handicap, medical
condition, marital status or sex, except as permitted pursuant to Section 12940 of
the Government Code. Violation of this provision may result in the imposition of
penalties referred to in Labor Code, Section 1735.
9. CONSULTANT shall protect, defend, indemnify and hold harmless
CITY and its elected and appointed boards, officers, and employees from any and
all claims, liabilities, expens:;s, or damages of any nature, including attorney fees,
for injury to or death of any person, and for injury to any property, including
consequential damages of any nature resulting therefrom, arising out of or in any
way connected with the negligent performance of this Agreement by act or
omission, by or on behalf of CONSULTANT, or resulting from any violation by
CONSULTANT of any statute, law, regulation, or other legal requirement
concerning a safe place of employment for workers.
10. CONSULTANT shall perform the services herein contemplated in
compliance with California laws concerning minimum hours and wages (California
Labor Code, Sections 1171 et seq.), occupational health and safety (29 U.S.C.
651 et seq. and California Labor Code, Sections 6300 et seq.), fair employment
practices (29 U.S.C. 201 et seq. and California Government Code, Sections 12900
et seq.), Worker's Compensation Insurance and Safety in Employment (Divisions 4
3
and 5 of the California Labor Code) and all amendments thereto, and all similar
State or Federal laws :o the extent that they are applicable; and CONSULTANT
shall indemnify and hold harmless CITY from and against all claims, demands,
payments, suits, actions, proceedings, and judgments of every nature and
description, including attorney's fees and costs, presented, brought, or recovered
against CITY, for or on account of any liability under any of the above-mentioned
laws, which may be incurred by reason of any work performed by CONSULTANT
under this Agreement.
11. CONSULTANT shall obtain and maintain during the life of this
Agreement all of the following insurance coverages issued by insurance
organizations authorized by the Insurance Commissioner to transact the business
of insurance in the state of California unless otherwise approved by the City
Attorney
(a) Comprehensive general liability, including premises -operations,
products/completed operations, broad form property damage, and blanket
contractual liability, and each of the following except as may be stricken out by
CITY'S Project Manager: independent contractors, personal injury; and
(b) Automobile liability for owned vehicles, and each of the following,
except as may be stricken out by CITY'S Project Manager: Hired, and non -owned
vehicles. Endorsements shall be obtained for the policies providing the above
insurance for the following three provisions:
(i) Additional Insureds:
4
"The City of Costa Mesa and its elected and appointed boards,
officers, agents, and employees are additional insureds with respect to this subject
project and contract with CITY."
(ii) Notice:
"Said policy shall not terminate, nor shall it be canceled,
nor the coverage reduced, until thirty (30) days after written notice is given to
CITY."
(iii) Other Insurance:
"Any other insurance maintained by the CITY OF COSTA
MESA shall be excess and not contributing with the insurance provided by this
policy." The policy limits on all the above shall be not less than $1,000,000,
combined single limits, per occurrence and aggregate.
12. In addition to the insurance coverage in Paragraphs 11 and 12,
above, CONSULTANT ::;hall obtain and maintain, during the life of this Agreement,
Workers' Compensation Insurance in statutory amount.
13. CONSULTANT shall provide to CITY certificates of insurance showing
the insurance coverages described in Paragraphs 11, 12 and 13, above, in a form
and content approved by Cfli(, prior to beginning work under this Agreement.
14. CONSULTANT is and shall be acting at all times as an independent
contractor and not as an employee of CITY. CONSULTANT shall secure, at his
expense, and be responsible for any and all payment of Income Tax, Social
Security, State Disability Insurance Compensation, Unemployment Compensation,
and other payroll deductions for CONSULTANT and its officers, agents, and
5
employees, and all business licenses, if any are required, in connection with the
services to be performed hereunder.
15. CITY shall asskn a Project Manager or his designee to work directly
with CONSULTANT.
16. In the event of written authorization by CITY'S Project Manager of
changes from the work as indicated in Exhibit "A", or of other written permission
authorizing additional work riot contemplated herein, additional compensation shall
be allowed for such extra work; but extra compensation shall not exceed ten
percent (10%) of the total contract amount.
17. CONSULTANT shall submit monthly invoices to CITY'S Project
Manager for approval, specifying the areas where work was completed and the
associated time for completion. On or before the last Monday of each and every
month during the performance of the work, CONSULTANT shall provide invoices
to CITY for services rendered. Work performed at the request of CITY other than
as specified in this Agreement is to be designated "EXTRA WORK" on monthly
invoices. Work performed in connection with authorized written change orders
will be so designated on all invoices.
18. Any work relating to soils engineering, foundation engineering,
geological surveys or reports, soil investigations, soil testing, or compaction
certification, except for the services outlined on Exhibit "A", is specifically
excluded from the services proposed herein and must be contracted for by CITY
under separate contract.
0
19. All work shall be done in a good and workmanlike manner, and CITY
reserves the right to terminate services at any time with or without cause, and
whether or not the work has been completed. Any termination and any special
instructions from the CITY shall be made through its Project Manager, in writing,
and may be delivered in person to CONSULTANT or mailed to CONSULTANT'S
present business address. In the event this Agreement is terminated, all drawings,
designs, specifications, and appurtenant data prepared for the project shall
become the property of CITY and may be used by CITY without additional cost to
CITY. Should CITY decide to terminate this Agreement for any reason,
CONSULTANT shall be entitled to payment on an hourly basis in accordance with
the rate schedule herein for work completed prior to written notification.
20. This is a personal service contract, and the supervisory work shall not
be delegated to any person or entity without the consent of CITY; but
CONSULTANT may employ field crews, crew chiefs, and other personnel to
perform actual services hereunder.
21. CONSULTANT shall not voluntarily or by operation of law assign,
transfer, sublet or encumber all or any part of CONSULTANT'S interest in this
Agreement without CITY'S prior written consent. Any attempted assignment,
transfer, subletting or encumbrance shall be void and shall constitute a breach of
this Agreement and cause for termination of this Agreement. Regardless of
CITY'S consent, no subletting or assignment shall release CONSULTANT of
CONSULTANT'S obligation to perform all other obligations to be performed by
CONSULTANT hereunder for the term of this Agreement.
7
22. In the event that litigation is brought by any party in connection with
this Agreement, the prevailing party shall be entitled to recover from the opposing
party all costs and expenses, including attorney's fees, incurred by the prevailing
party in the exercise of any of its rights or remedies hereunder or the enforcement
of any of the terms, conditions or provisions hereof.
23. DRUG-FREE WORKPLACE POLICY:
CONSULTANT, upon notification of contract award, shall establish a Drug -
Free Awareness Program to inform employees of the dangers of drug abuse in the
workplace, the penalties that may be imposed upon employees for drug abuse
violations occurring in the workplace, and the employee assistance programs
available to employees. Each employee engaged in the performance of a CITY
contract must be notified of this Drug -Free Awareness Program, and must abide
by its terms. CONSULTANT shall conform to all the requirements of CITY'S Policy
No. 100-5, attached hereto as Attachment No. 1. Failure to establish a program,
notify employees, or inform the CITY of a drug-related workplace conviction will
constitute a material breach of contract and cause for immediate termination of the
contract by the CITY.
CITY OF COSTA MESA,
a municipal corporation
Dated:_ 7-,2I-47 By:
City anager
Dated: %- ;t_aq7
Dated:
APPROVED AS TO FORM:
[6 e --P-5-1
City Attorney
LightingTechnologySvcs.97
6
By: 7 --
Deputy Cit Jerk
of the City of Costa Mesa
CONSULTANT
Title:
Address: 5/2-..fn
Telephone: 7-,( 55"D -7?-4-3
APPROVED AS TO CONTENT:
Project Manager
EXHIBIT A
CITY OF COSTA MESA
CITY HALL
EXECUTIVE OVERVIEW
City of Costa Mesa
City Hall
Basis
A mutual applications survey of all areas designated was conducted by Lighting Technology
Services, Inc.
A lighting load audit/inventory was conducted during the applications survey in all designated
areas. The existing lamps, ballasts and proposed changes are detailed in our scope of work room
list. Current operating costs are based upon all existing loads and proposed costs are based upon
recommended changes.
Several operating lighting day hours were used to calculate operating costs, existing and
proposed, please refer to Scope of Work Room List or Cost Avoidance Savings pages for a
detailed list of those hours.
Energy saving calculations are based upon the average cost of $.10 per kilowatt hour of the SCE
rate schedule.
Cost and Savings
Based on the quantity of the fixtures referenced on our scope of work room lists, our proposal
included all lamps, ballasts, miscellaneous materials, labor, tax, permit fees, disposal and
equipment necessary for full implementation of the project. The total cost is $68,564.56. The
annual energy/operational savings for this project is $25,184.73 which will yield a 2.72 year
payback.
Scope of Work
The scope of work includes retrofitting of all T12 Fluorescent lamps and magnetic ballasts with
new T$ Lamps and Electronic Ballasts, replacement of all incandescent fixtures with new
compact fluorescent lamps or fixtures, and install occupancy sensors in selected spaces. In
addition to the energy savings r--ferenced below, the facility will save substantial maintenance
and lamp replacement costs.
Lighting Technology Services, Inc. will provide, install and render fully operational all control
systems components, lighting fixtures, lamps, ballasts and fixture conversions. Included in our
quotation is all materials, labor, supervision, direct job expenses and/or equipment necessary to
fully execute the project scope reference and enumerated in our quotation.
Construction Schedule
Professional crews will work at night to avoid any disruption. Individual offices or areas will be
completed in one (1) night to ensure a smooth transition. Estimated time to complete is 7-10
working days.
SCOPE OF WORK DESCRIPTION
City of Costa Mesa
City Hall
Basis
A mutual applications survey of all areas designated was conducted by Lighting Technology
Services, Inc.
A lighting load audit/inventory was conducted during the applications survey in all designated
areas. The existing lamps, ballasts and proposed changes are detailed in our scope of work room
list. Current operating costs are based upon all existing loads and proposed costs are based upon
recommended changes.
A twelve (12) hour lighting day, five (5) days per week, fifty two (52) weeks per year were
incorporated into operating calculations.
Energy saving calculations are based upon the average cost of $.10 per kilowatt hour of the SCE
rate schedule. Additional savings will be obtained as utility rates rise since it is unlikely they
will remain constant in future years. A (3%) three percent increase was included in the Financial
Analysis.
EPA approved disposal of all lamps and ballasts. Method of disposal is incineration of
hazardous parts and recycling of balance of materials. Certificate of destruction will be provided
for incineration of hazardous parts, as applicable. If PCB ballasts are found to exist, then an
additional cost of $3.50 ea. will be required for proper EPA disposal.
Occupancy Sensor Room Selection Criteria
The following factors are taken into consideration when LTS makes a selection of whether or not a room
or area gets an occupancy sensor and which type of sensor may be utilized in the selection process.
1. The net resulting wattage - post lighting retrofit: As a general guideline 100 watts minimum for a
wall sensor, 300-350 watts minimum for a ceiling sensor.
2. Hours of operation - weekly, monthly or annually.
3. Cost of kilowatt hours.
4. Room shape or size and ceiling construction (suspended T -Bar vs non T -Bar i.e. plaster, concrete,
spline tile or open) dictates the type and model or sensor required.
5. Payback period or ROI required by customer.
6. Wall Sensor - room size generally 250 sq. ft. or less, room shape - wall switch must face into the
room.
7. Ceiling Sensors; a) rooms that, due to obstructions, cannot use a wall sensor and meet minimum
load, hours, kWh costs; b) rooms that meet minimum ceiling sensor requirements of numbers 1, 2, 3
and 4 above.
8. Ceiling construction - This significantly impacts installation costs due to access difficulty of non T -
Bar. A room with non T -Bar ceiling requiring a ceiling sensor with items 2 and 3 being equivalent
will require greater wattage (item No. 1) for justification.
Page 1
Qualifications
• Project quotation is limited to rooms or areas stipulated in Scope of Work description.
• Any items or fixtures missed in an LTS surveyed / audited room or area are provided at no
cost.
• Rooms or areas not included in project scope can be added and Lighting Technology
Services, Inc. will be happy to provide a quotation for rooms or areas not included in this
proposal.
• Any improper wiring of fixtures, switches or circuits that pre-existed LTS' performance of
this scope of work, will be customers responsibility. LTS will submit a written change to
correct any improper wiring before proceeding with any work in the immediate area of the
problem.
• If asbestos is found to exist above the ceiling, customer will provide LTS with current
certified airborne particle count for verification of safety and LTS will quote the extra cost
for working in an area where asbestos is present.
Customer Responsibility
• Access to facility - To fully execute scope customer will need to grant LTS full access to
work areas at a reasonable time period. All installation will be performed evenings or off
hours at no extra cost.
• Parking - Availability of parking will need to be supplied to Lighting Technology Services
installation staff for duration of installation of project.
Page 2
IMPLEMENTATION PLAN
Project Management
LTS believes that quality project management provides the necessary foundation to successfully plan, organize,
implement, control and begin commissioning a lighting retrofit project in three distinct phases: 1) project
initiation; 2) project implementation; and 3) project termination.
LTS' management and its Team Service Providers pride themselves on our thoroughness and attention to
detail. The Management Team is made up of experienced professional project managers. Each Team Provider
has a Project Manager that works closely with the overall team leader to insure that all schedules are met and
no detail is overlooked.
Project Initiation Phase
A very important first step is to ensure that all of the customers wants and needs are clearly established and
understood. We plan to accomplish this with an in-depth review and discussion of the project basis, scope of
work, design options, retrofit strategies selected and preliminary equipment recommended. The goal here is to
be certain of a clear understanding by both the Customer and LTS of exactly what shall be included, and
excluded from the scope of work, what strategies will be followed and what equipment will be acceptable or
not.
Once the scope of work and design options are designated by the Customer then the design phase will
commence for any infrastructure upgrades desired by the Customer. Upon completion of the designs they are
presented to the customer for their input and approval. This process of "value engineering" involves any
professional consultants and the customer to provide an informed comparative analysis of the different design
options of each measure to ensure the option and equipment meet the expectation of the customer as well as the
overall goals of the project.
Once the final project scope is established and budgets are fixed the Team meets to prepare and finalize the
commissioning plan and the production schedule / timelines to meet the installation requirements of the
project.
An integral part of the scheduling process is the establishment of specific milestones within the schedule, to
monitor the progress of the project and provide measurable goals for determining the efficiency of the
installation and insure on-time completion.
Schedule
• The schedule is the conversion of the project plan into an operating timetable and becomes a key input in
establishing the monitoring and control systems for the project and shows the interdependence of all tasks, work
packages, and work units.
• It shows the expected project completion date and identifies critical activities, which if delayed, will delay the
project completion date.
• It will also show the activities with slack that can be delayed for specified periods without penalty.
• It determines the dates on which tasks may be started — or must be started if the project is to stay on schedule.
• It may, depending on the task allow an estimate of probability of project completion by various dates, or the date
corresponding to a particular priority probability.
After the customer has approved the schedule and milestones then LTS will internally accomplish the following:
a) Establish Project Management Construction Files
b) Estimate review and manpower analysis
c) Computerized Job Estimate / Costing / Bill of Materials "package" prepared by Project Manager
d) Schedule a project kick-off meeting with LTS Sales Engineer, Director of Field Operations and LTS Field Foreman
along with the customer project manager to review in detail the scope of work, project schedule and general
information; i.e., parking, equipment storage and any problem or sensitive areas of customer concerns.
e) Accommodate any special scheduling request or any last minute changes the customer may have to the sequence of
work
f) Establish exact date and space work will commence.
Construction Phase
Monitoring & Measurement
The project implementation phase will begin with the appropriate measurement and verification per the plan approval
by the Customer. It should be noted that Measurement & Verification could occur in conjunction with design phase for
upgrade options and / or finalizing scope of work phase.
Construction
The management team begins the construction process by finalizing the necessary plans and specifications needed for
plan check and permits. Once the permits are obtained, the construction begins. Construction progress meetings are
held weekly to measure the progress of the project. Coordination with each task and the customer are discussed to
maximize production and minimize customer interruption. When working in occupied buildings, coordination and work
scheduling are vital for the success of the project. To that end, project management's main focus is the close
supervision of the work crew and their interface with the occupants of the facility under going up -grades.
To begin the actual construction, LTS' project manager will accomplish the following:
a) Finalize any pre -field engineering for any special requirements.
b) Expedite equipment and material delivery
c) Schedule labor
d) LTS will then schedule with the customer project manager mobilization of project equipment, material orders, and
commence project based upon an agreed schedule and place.
e) Daily and weekly productivity reports to the Director of Field Operations are required of all LTS foremen to
properly monitor project progress.
f) The Director of Field Operations and the foreman will regularly communicate with the customer project manager at
the agreed upon intervals to ensure a successful project.
It should be noted that any required inspections will occur on initial basis of any portion of the scope of work
requiring inspection to assure compliance from the onset.
Daily Work Plan
LTS begins each day with the Project Manager and set-up man arriving at the project site each day one (1) hour
before the scheduled crew starting time. During this period all the lamps, ballasts, fixtures, ladders, etc. are
taken to the area being worked that day. Lamps, ballasts, fixtures, etc. are distributed to each room, this allows
the crew to start work immediately upon arrival. As crew members arrive, the Project Manager will assign
each one an area he will be responsible for. Each crew member prepares the space or area for work by moving
and / or covering equipment and furniture. The work is executed. As each room or area is completed the
foreman is responsible for checking quality of workmanship and accuracy of fixture counts, creating an "as
built" scope of work.
At the end of each shift the Project Manager will do a complete walk through to assure that all rooms .are
dusted and vacuumed, lights checked in each room for proper operation, any fixtures that are not operating
correctly will be repaired before the crew is dismissed. Before the Project Manager leaves he will leave a list
of rooms completed during that shift for the customer project manager to review each day and the area planned
to be worked on the next shift.
It is LTS' policy to complete a room in its entirety in one work shift and return the room to full service each
day.
Housekeeping Practices
LTS always takes responsibility for relocating and replacing furniture, equipment etc. and covering said
equipment / furniture with white sheets as necessary to perform specified work. Any furniture or equipment
that cannot be moved for installation / retrofit above it will be covered with padded furniture pads in addition
to sheets and a scaffold set-up over it to perform the work. LTS shall also provide all tools and cleaning
equipment (vacuums, broom, dust pans and waste containers) required for our personnel to completely clean
each area retrofitted at the completion of each shift.
LTS, upon installation of either a new fixture, or in the case of lamp and / or ballast replacements in a existing
fixture LTS shall clean reflector cones, reflectors, lenses, louvers, lamps and decorative elements. To prevent
static build-up on lenses and reflectors, LTS cleans with manufacturer's recommended destaticizing and non-
abrasive cleaning solutions. All fixtures are to be either air dried or carefully dried with a soft cotton cloth.
Any fixtures or diffusers not cleaned satisfactorily will be re -cleaned.
LTS shall be responsible for and include all costs for portable on-site storage to secure all new lamps, ballasts,
fixtures and equipment as well as provide for security of all hazardous waste or disposal materials. LTS shall
also include portable disposal container for proper disposal of all removed fixtures, as specified.
Project Termination Phase
At the end of the construction phase of the project, the Project Manager meets with the commissioning team to
setup their schedule and begins the commissioning process. Once this phase is completed, the project
management team meets with the customer to review the installation. The Project Manager and the customer
representative actually walk the project and review each installation for completeness and operation. After the
customer is satisfied with the installation and the commissioning, the Project manager arranges for the final
training of the operating personnel.
Once the scope of work has essentially been completed any electrical inspection required will be asked to
complete final inspection.
It should be noted the termination phase will be executed on a building by building or location by location
basis.
Upon Certificates of Completion being signed off on each project site the on-going Measurement &
Hazardous Waste Disposal
LTS has proper EPA identification number (#CAL000121367) for handling or removal and proper EPA
disposal of all existing lighting system components containing hazardous waste.
Such waste may include, but is not limited to, ballasts containing polychlorinated biphenyl's (PCB's) and
lamps containing mercury.
The only method LTS uses for disposal of hazardous waste is incineration. The balance of non -hazardous
components are recycled. Certificates of destruction are provided for the incineration.
All PCB ballasts shall be properly removed; packed; labeled and shipped for incineration and recycling.
Copies of manifests evidencing proper shipment will be provided.
Verification will commence.
WARRANTY TERMS AND CONDITIONS
CITY OF COSTA MESA
CITY HALL AND POLICE DEPARTMENT
LIMITED WARRANTY.- All products, sold by "LTS" and identified with another
manufacturers name, except lamps, are guaranteed to be free from defects in material and
workmanship for a period of five (5) years. Lamps in the City Hall and Police
Department will be warranted for two (2) years, ballasts and sensors will be warranted for
five (5) years. "LTS" will, cause to have repaired or replaced, at its discretion, any
products found to be defective. Every part of the work herein described shall be executed
in strict accordance with the description of work in the most sound, workmanlike, and
substantial manner. All workmanship shall be of the best of its several kinds, and all
quantities to facilitate the proper and expeditious execution of the work, and shall be new
and the best of their respective kinds, except such materials as may be expressly provided
for in the description of work to be otherwise. Damage resulting from fire, accident,
misuse or improper installation by others, abuse, negligence or alteration are not
warranted. "LTS" responsibility under this warranty extends only to its own repair or
other replacement of defective parts and no other charges from purchasing or installing
party other than "LTS" will be honored.
VALUE
Value is a combination of three (3) primary factors: Quality, Service and Price. There are many
reasons why LTS is the lighting service company which will provide the greatest value.
Energy cost reduction equipment must be applied, utilized and installed correctly for proper function and
maximum savings. This must be done without disruption of productivity or sacrifice to the occupant. To
properly implement a lighting system retrofit, essential design elements must be taken into consideration.
♦ Existing Lighting System
♦ Space Utilization
♦ Level and Quality of Lighting
♦ Lighting System Design
♦ Product Technology
♦ Payback and R.O.I. Requirements
Lighting Technology Services' "Applied Systems" approach of incorporating all essential design
elements along with including both efficiency and control measures, assures an optimum lighting system
and the best overall value.
LTS' unique package of design and function guarantees offers exceptional value not provided by other
lighting companies.
♦ Confidence
LTS is a company you can trust. Many significant End Users have relied on the knowledge and
straight forward business approach of LTS' management.
+ No Inconvenience to Occupants
Occupant satisfaction and productivity is maintained. Proper lighting system design and function are
guaranteed. Installations are done during off hours. All areas are vacuumed upon completion.
♦ Project Support Guarantee
All LTS projects receive ownership supervision and full-time project management. This combined with
follow-up service assures direct management access, project success and customer satisfaction.
• Quality and Reliability Guarantee
LTS provides only the highest quality lighting services and products available. LTS provides only
products with less than a 1% failure rate.
♦ Full Product Lines
Various products are designed to fit the requirements of each building and space needs. Incorporating
the proper strategy in each area assures an optimum lighting system for both energy savings and
occupant satisfaction.
• Local 5 Year Warranty Service
Our direct warranty service does not leave the End User dependent on only a manufacturers' product
exchange. LTS provides a minimum five (5) year field service warranty on everything it sells. This is
unequaled in the industry.
• Savings Guarantee
LTS will assure load reduction and reduction of operating hours to solidify savings and R.O.I
commitments. Monitored savings verifications are included.
• Sensor Coverage Guarantee
LTS assures 100% coverage to completely cover the controlled area to accommodate all occupancy
habits of single or multiple occupants at any location within the room(s). LTS will add, change or
relocate any sensors(s), as required, for proper coverage at no cos to the customer.
• System Performance Guarantee
LTS assures no nuisance "turn-offs" or "ghost turn -ons" and LTS will provide adjustments, as required,
at no cost.
`�` GAN B�SERVEY .
!4 B�nfiYL +: �Nee�gtlH: _
♦ No -Cost Follow-up Adjustments
Every LTS sensor, control system project is completed with sensor -by -sensor time and sensitivity
follow-up adjustment to assure proper operation as sensor controls are affected by various conditions
and these must be accommodated.
+ System Design Guarantee
LTS will provide proper quantity, quality and distribution of light. All design changes are measured and
piloted before implementation. Changes required for customer satisfaction are at no cost.
♦ Scope of Work Guarantees
A. Any items or rooms missed in an LTS survey/audit are provided at no cost.
B. LTS includes new lenses, when required, in remaining fixtures. Providing new lenses will allow
you to take full advantage of the T8/Electronic Ballast light level enhancement as well as giving
a uniform, improved appearance. This is a detail often overlooked.
C. LTS replaces incandescents with new compact fluorescent fixtures, in almost all situations.
New compact fluorescent fixtures offer a number of benefits, including assuring the new
technology will continue to be used and not reversed by re -installation of old style lamps at a
later date. Also, you will realize the maximum energy savings - now and for many years to
come.
D. LTS will accommodate specific customer fixture requirements. Flexibility to meet special
requirements means that you can be certain your needs will be met.
E. LTS includes extensive photo cell or timeclock control of outdoor lighting. Our understanding
of the use and application of controls means that you get the best design and greatest savings.
F. LTS will repair or replace damaged or deteriorated fixtures which solves deferred maintenance
items.
LTS will handle your needs from concept to design through construction and complete warranty service to
successfully "bridge the gap" from the Manufacturers to the End Users' real world building needs.
With 14 years experience, LTS' management has the expertise to properly apply, engineer and install
your lighting or control systems(s). Combined with the highest level of customer support and service
available in the market, this will assure project success and customer satisfaction. WE GUARANTEE IT!
CITY OF COSTA MESA 9410165 Workbook Revised
CITY HALL
EXISTING FIXTURE PROPOSED FIXTURE
LEGEND LEGEND
Sum of # Fixt
Total
Fixt/Lamp Desc.
1' Battery B/U
15
1' F20T12 Strip
21
1X4 Pris.
4
1x4 Rec. Pris.
5
1x4 Wrap
1
2x2
30
2x2 Parabolic
3
2x2 Pris.
173
2x4
129
2x4 Parabolic
6
2x4 Pris.
574
2x4 Pris.
4
2x4 Pris. 41 K
9
2x4 Wrap
6
4' F40T12 Strip
21
4' Rec. Pris.
91
4' SM Strip
21
4' Wrap
11
8' F40T12 Strip
127
A -Lamp Eyeball
2
ER
8
PAR Lamp
11
Rec. ER (dimmer)
43
Soffetts
20
(blank)
0
Grand Total
1335
Sum of # Fixt2
Total
Strategy Desc.
1LEBF017LP
21
1LEBF032LP
29
2LEBF032HP
154
2LEBF032LP
272
2LEBFBO32
8
2LEBFBO32LP
180
4LEBF032HP
562
4LEBF032LP
26
4LEBFBO32LP
4
ER30-600
8
No Change
71
(blank)
0
Grand Total
1335
Page -1- -- -
CITY OF COSTA MESA 9410165 Workbook Revised
CITY HALL
EXISTING & PROPOSED LIGHTING SYSTEM
-3117197 - Page 1 12:35 PM
Existing Lighting
Proposed Lighting System
# Fixt
TotalTotal
Lamps Fixt/Lamp Desc.
# Fixt
Lamps Strategy Desc.
21
21 1' F20T12 Strip Total
21
21 1 LEBF017LP
21
21 4' F40T12 Strip Total
21
21 1 LEBF032LP
8
8 4' Rec. Pris. Total
8
8 1LEBF032LP
43
150 2x4 Total
43
86 2LEBF032HP
971
388 2x4 Pris. Total
97
194 2LEBF032HP
8
16 14' Rec. Pris. Total
8
16 2LEBF032HP
6
12 4' SM Strip Total
6
12 2LEBF032HP
4
8 1x4 Pris. Total
4
8 2LEBF032LP
5
10 1 x4 Rec. Pris. Total
5
10 2LEBF032LP
1
2 1x4 Wrap Total
1
2 2LEBF032LP
241
48 2x2 Pris. Total
24
48 2LEBF032LP
7
28 2x4 Pris. Total _
7
14 2LEBF032LP
70
140 4' Rec. Pris. Total
70
140 2LEBF032LP
3
6 4' SM Strip Total
3
6 2LEBF032LP
11
22 4' Wrap Total
11
22 2LEBF032LP
127
254 8' F40T12 Strip Total
127
254 2LEBF032LP
20
20 Soffetts Total
20
20 2LEBF032LP
4
8 2x2 Pris. Total
4
8 2LEBFB032
4
8 2x4 Pris. Total
4
8 2LEBFB032
30
60 2x2 Total
30
60 2LEBFB032LP
3
6 2x2 Parabolic Total
31
6 2LEBFB032LP
134
268 2x2 Pris. Total
134
268 2LEBFB032LP
3
6 2x4 Total
3
6 2LEBFB032LP
10
20 2x4 Pris. Total
10
20 2LEBFB032LP
9
18 2x2 Pris. Total
9
18 4LEBF032HP
83
332 2x4 Total
83
166 4LEBF032HP
6
24 2x4 Parabolic Total
6
12 4LEBF032HP
4491
1,790 2x4 Pris. Total -
449
898 4LEBF032HP
91
36 2 x4 P ris. 41 K Total
9
18 4LEBF032HP
61
12 2x4 Wrap Total
6
12 4LEBF032HP
9
2012x4 Pris. Total
9
20 4LEBF032LP
5
1014' Rec. Pris. Total
5
10 4LEBF032LP
12
24 4' SM Strip Total
12
24 4LEBF032LP
2
4 2x2 Pris. Total
2
4 4LEBFB032LP-
2
4 2x4 Pris. Total
2
4 4LEBFB032LP
8
8 ER Total
$
8 ER30-600
15
15 1' Battery BIU Total
15
15 No Change
2
2 A -Lamp Eyeball Total
2
2 No Change
11
11 PAR Lamp Total
11
11 No Change
43
43 1 Rec. ER (dimmer) Total
43
43 No Change
-3117197 - Page 1 12:35 PM
PROPOSED LIGHTING SYSTEM LEGEND
CITY OF COSTA MESA - CITY HALL
The following retrofits or replacements will be accomplished as detailed in the enclosed room lists.
Code
Description
T - T -Bar Ceiling
A - Wrap Around Fixt.
2LEBF017
Convert 2 Lamp F20T12 to F017T8 & Electronic Ballast
1 LEBF032
Convert 1 Lamp F40T12 to F032T8 & Electronic Ballast
2LEBF032
Convert 2 Lamp F40T12 to F032T8 & Electronic Ballast
4LEBF032
Convert 4 Lamp F40T12 to F032T8 & Electronic Ballast
XLEBF032LP
Convert F40T12 to F032T8 & Low Power Electronic Ballast
XLEBF032HP
Convert F40T12 to F032T8 & High Performance Electronic Ballast
2LEBFBO32
Convert 2 Lamp FB40T12 to FB032 & Electronic Ballast
XLEBFB032
Convert FB40T12 to FB032 & Low Power Electronic Ballast
ER30-600
Convert 75w ER Ceiling/Wall Fixture to 13 watt Ceiling/Wall Fixture
WS I WI
Wattstopper Wall Switch Occupancy Sensor
W500
Wattstopper Ceiling Occupancy Sensor
W1000
Wattstopper Ceiling Occupancy Sensor
W2000
Wattstopper Ceiling Occupancy Sensor
W2000H
lWattstopper Hallway 1 Corridor Ceiling Occupancy Sensor
A120\277
IlPowerpack (needed to operate all ceiling sensors)
SCOPE OF WORK ABBREVIATIONS
EB - Electronic Ballast
HB - Hybrid Ballast
TW - Tandem Wire
E5 - Energy Saving
SI - Screw -In Comp. Fluor.
HW - Hardwired Comp. Fluor
CF - Compact Fluorescent
DL - Down Light
JJ - Jelly Jar Fixt.
TI_ - Track Light ET - Electronic Timer
T - T -Bar Ceiling
A - Wrap Around Fixt.
WP - Wall Pack TC - Time Clock
SM - Surface Mount
OS - Open Strip Fixture
CP - Ceiling Pack PC - Photo Cell
BC - Break Circuit
PB - Porcelain Base Fixture
VP - Vandal Proof
NT - Non T -Sar
PH - Pendant Hung Fixt.
RD- Round
T - T -Bar Ceiling
NF - New Fixture
RC - Recessed
PP - Power Pack
DF - Drum Fixture
SF - Square Fixture
PR - Porcelain Round Fixture
NL - New Lens
SCOPE OF WORK
City of Costa Mesa - City Hall
9410165 Workbook i .5-5-97
518197 Page 1 10:45 AM
Existing Lighting
Proposed Lighting System
Proposed Control System
Control
Tyre
# PP Ceiling Sensor Scope
Fir Room Name
#
Al Fixt
Lam
ps
Total
Lamps jUrnp
Walls I Fixt/Lamp
Desc.
Total Walls
Foot
Candle
#
# Fixl
Lain
pi
Total
Lamps
Walt% l
Lamp Strategy Desc.
# Ret
# TW Total Walls I
Qty_ Type
Type
# PP Ceiling LBC I Zone IS,,
5 City Mgr.
6
4
24
35.5 2x4 Pris.
852
114
6
2
12
39 4LEBF032HP
3 468
1 VV500
2 T
5 City Mgr. (cont'd)
3
2
6
35.5 2x2 Pris_
213
3
2
6
77 2LEBF032LP
162
Secretarial
8
4
32
35.2 2x4 Pris.
1,126
114
8
2
16
39 4LEEF032HP
4 624
1 W100
2 T 1
5 A. Gyben
2
4
8
35.5 2x4 Pris.
284
2
2
4
39 2LEBF032HP
156
5 A. Gyben (cont'd)
2
2
4
35.5 2x2
142
55
2
21
4
27 2LEBFB032LP
108
1 WS
5 Once
2
4
8
35.5 2x4 Pris.
284
59
2
2
4
39 4LEBF032HP
1 156
1 jVVS
5 Office (cont'd)
4
2
8
35.5 2x2 Pris.
284
4
2
8
27 2LEBF8032LP
216
5 Office
4
4
16
35.5 2x4 Pris.
568
72
4
2
8
39 4LEBF032HP
2 312
1 W500
1 T
5 Office (cont'd)
2
2
4
35.5 2x2 Pris.
142
2
2
4
27 2LEBFBO32LP
108
Short Hall
3
2
6
35.514- Rec. Pris.
213
22
31
2
fi
27 2LEBF032LP
162
5 CopylFile Rm.
2
4
8
35.5 2x4 Pris.
284
22
2
2
4
39 2LEBF032HP
156
1 W500
1 T
5 Copy/File Rm. (cont
2
2
4
35.5 2x2 Pris.
142
2
2
4
27 2LEBFBO32LP
108
Devpt. Services
8
4
32
35.5 2x4 Pris.
1,136
51
8
2
16
39 2LESF032HP
624
1 W100
1 T
Devpt. Srvcs. (cont'
6
2
12
35.5 2x2 Pris.
426
6
2
12
27 2LEBFB032LP
324
5 M. Berman
4
4
16
35.5 2x4 Pris.
568
99
4
2
8
39 2LESF032HP
312
1 WS
Redevpt. Recept.
4
2
8
35.5 2x2 1
284
30
4
2
8
27 2LEBFB032LP
216
1 1hl100
1 T
Redevpt. Recp. (co
2
4
8
35.5 2x4
284
2
2
4
39 2LEBF032HP
156
5 Restrooms
1
2
2
35.5 1x4 Wrap
71
40
1
2
2
27 2LEBF032LP
54
1 WS
5 Mens RIR
4
2
8
35.5 1x4 Pfis.
284
18
4
2
8
27 2LEBF032LP
216
1 W500
1 NT
5 Main Hall
3
2
6
35.5 4' Rec. Pris.
213 2-14
3
2
6
27 2LEBF032LP
162
5 Mayor
8
4
32
35.5 2x4 Pris.
1,136
1351
8
2
16
39 2LEBF032HP
1 624
1 W500
1 T
5 Mayor (cont'd)
2
2
4
35.5 2x2 Pris.
142
2
2
4
27 2LEBFB032LP
108
5 Elev. Lobby/Hall
2
4
8
35.5 2x4 Pris.
284
15
2
2
4
39 2LEBF032HP
156
5 Elev. Lobby/Hall (co
7
2
14
35.5 4' Rec. Pris.
497
7
2
14
27 2LEBF032LP
378
5 Elev, Lobby/Hall (co
4
1
4
75 ER
300
4
1
4
13 ER30-600
52
5 Elev. Lobby/Hall (co
1
2
2
35.5 2x2
71
1
2
2
27 2LEBFBO32LP
54
5 Short Hall
1
2
2
35.5 4' Wrap
71
28
1
2
2
27 2LEBF032LP
54
5 Ladies Rm.
1
4
4
35.5 2x4 Pris.
142
28
1
4
4
24.5 4LEBF032LP
98
1 WS
5 Ladies Rm.
5
2
10
35.5 1x4 Rec, Pris.
355
49
5
2
10
27 2LEBF032LP
2701
1 Vy500
1 NT
5 Breakroom
4
4
16
35.5 2x4
568
80
4
2
8
39 2LEBF032HP
312
1 W500
1 T
5 Breakroom (cont'd)
1
2
2
35.5 2x2
71
1
2
2
27 2LEBFBO32LP
54
5 City Att. Sec.
4
4
16
35.5 2x4 Pris.
568
58
4
2
8
39 4LEBF032HP
2 312
1 W500
1 T
5 City Att. Sec. (cont
4
2
8
35.5 2x4 Pris.
284
4
2
8
27 2LEBFBO32LP
216
5 Comer Office
2
4
8
35.512x4 Pris.
284
56
2
2
4
39 2LEBF032HP
156
1 PIR
21T 1
5 Comer Off. (cont'd)
2
2
4
35.5 2x2 Pris.
142
2
2
4
27 2LEBFB032LP
108
518197 Page 1 10:45 AM
9410165 Workbook 5-5-97
SCOPE OF WORK
City of Costa Mesa - City Hall
11 _ -- _
518197 Page 2 10:45 AM
GAJn11y +-19 Iuny
rroposea Lrgnting system
Proposed Control System
Type
Control
N PP Ceiling Sensor Scope
#
Lam
Total
Watts! Fixl/Lamp
Font
# Lam
Total
Watts/
# Re
Type
Fir Room Name
# Fixt
ps
Lamps
Lamp Desc.
Total Watts
Candle
# Fixt
ps
Lamps
Lamp Strategy Desc.
# TIN' Total Watts I
Qtv Type
# PP Ceiling I3C Zone SM
5 Copy Rm.
2
4
8
35.5 2x4 Pris.
284
56
2
2
4
39 2LEBF032HP
156
1 PIR
2 T 1
Library
6
4
24
35.5 2x4 Pris,
852
51
6
2
12
39 4LEBF032HP
3
468
1 W200
2
Library (cont'd)
4
2
8
35.5 4' Rec. Pris.
284
4
2
8
39 2LEBF032HP
312
5 Office
2
4
8
35.5 2x4 Pris.
284
53
2
2
4
39 4LESF032HP
1
156
1 WS
5 City Att. Asst.
2
4
8
35.5 2x4 Pris.
284
47
2
2
4
39 2LEBF032HP
156
1 WS
5 Office
3
4
12
35.5 2x4 Pris.
426
49
3
2
6
39 4LESF032HP
2
234
1 WS
5 City Attorney
3
4
12
35.5 2x4 Pris.
426
74
3
2
6
39 2LEBF032HP
234
1 PIR
1 T
5 Office
6
4
24
35.5 2x4 Pris.
852
92
6
2
12
39 4LEBF032HP
3
468
1 PIR
1 T
5 Fire Chief Sec.
3
2
6
35.5 2x4 Pris.
213
35
3
2
6
39 4LEBF032HP
2
234
1 WS
5 Office
4
4
16
35.5 2x4 Pris,
568
66
4
2
8
39 4LEBF032HP
2
312
1 WS
5 Fire Chief
4
4
16
35,5 2x4 Pris.
568
138
4
2
8
39 4LEBF032HP
2
312
1 PIR
1 T
5 Fire Chief (cont'd)
2
2
4
35.5 2x2 Pris.
142
1 2
2
4
27 2LEBFBO32LP
108
5 J. Richey
2
2
4
35.5 2x4 Pris.
142
1171
2
2
4
27 4LESF8032LP
1
108
1 IWS
5 J. Richey (cont'd)
4
4
16
35.5 2x4 Pris.
568
4
2
8
39 2LEBF032HP
312
5 Secretary
4
21
8
35.5 2x2 Pris.
284
41
4
2
8
27 2LEBF8032LP
2161
1 W500
1 T
• Fire Admin,
10
4
40
35.5 2x4 Pris,
1,420
77
101
2
20
39 4LEBF032HP
5
780
1 W100
1 T
• Fire Admin. (cont'd)
4
2
8
35.5,2x2 Pris,
284
41
2
8
27 2LEBFBO32LP
216
• Outdoor Patio
1
1
1
1411' Battery Bili
14
1
1
1
1
14 No Change
14
• Outdoor Patio
1
1
1
14 1' Battery BIU
14
1
1
1
14 No Change
14
• Outdoor Patio
1
1
1
14 1' Battery BIU
14
1
1
1
14 No Change
14
Outdoor Patio
1
1
1
14 1' Battery BIU
14
1
1
1
14 No Change
14
Outdoor Patio
1
1
1
14 1' Battery BIU
14
1
1
1
141N0 Change
14
Stairwell
1
1
1
14 1' Battery B/U
14
3
1
1
1
141 No Change
14
' Stairwell (cont'd)
1
2
2
35.5 4' Wrap
71
1
2
2
27 2LEBF032LP
54
Stairwell
1
1
1
14 1' Battery BIU
14
31
1
1
1
14 No Change
14
' Stairwell (cont'd)
1
2
2
35.5 4' Wrap
71
1
2
2
27 2LEBF032LP
54
Stairwell
1
1
1
14 1' Battery B1U
14
3
1
1
1
14 No Change
14
Stairwell (cont'd)
1
2
2
35.5 4' Wrap
71
1
2
2
27 2LEBF032LP
54
Stairwell
1
1
1
14 1' Battery B!U
14
3
1
1
1
14 No Change
14
Stairwell (cont'd)
1
2
2
35.5 4' Wrap
71
1
2
2
27 2LEBF032LP
54
Stairwell
1
1
1
14 1' Battery BIU
14
3
1
1
1
14 No Change
14
Stairwell (cont'd)
1
2
2
35.5 4' Wrap
71
1
2
2
27 2LEBF032LP
54
Stairwell
1
1
1
14 1' Battery BIU
14
3
1
11
11
14 No Change
14
Stairwell (cont'd)
1
2
2
35.5 4' Wrap
71
1
2
2
27 2LEBF032LP
1
54
Stairwell
1
1
1
14 1' Battery BIU
14
311
14 No Change
14
518197 Page 2 10:45 AM
9410165 Workbook . .. 5-5-97
SCOPE OF WORK
City of Costa Mesa - City Hall
518197 Page 3 10:45 AM
txlsnng LIgming
Proposed Lighting System
Proposed Control System
Type
Control
#PP Ceiling
Sensor Scope
Flr Room Name
#
# Fix(
Lam
s
Total
Lamps
Watts ! Fixt/Lamp
Lamp Dew.
TOW Watts
Foot
Candle
Al Fiat
# Lam
ps
Total
Lamps
Watts !
Lamp StrattRy Dew.
# T\F Total
# Rel
Watts I
Qty Typt
Tyne
# PP Ceiling
DC Zane Sit
Stairwell (cont'd)
1
2
2
35.5 4' Wrap
71
1
2
21
27 2LEBF032LP
541
Stairwell
1
1
1
14 1' Battery BIU
14
3
1
1
1
14 No Change
14
A
Stairwell (cont'd)
1
2
2
35.5 4' Wrap
71
1
2
2
27 2LEBF032LP
54
Stairwell
1
1
1
14 1' Battery BIU
14
3
1
1
1
14 No Change
14
Stairwell (cont'd)
1
2
21
35.5 4' Wrap
71
1
2
2
27 2LEBF032LP
54
Stairwell
1
1
1
1411' Battery BIU
14
3
1
1
1
14 No Change
14
Stairwell (cont'd)
1
2
2
35.5 4' Wrap
71
1
2
2
27 2LEBF032LP
54
4 W. Morris
4
4
16
35.5 2x4 Pris.
568
116
4
2
8
39 4LEBF032HP
21
312
1,W500
2 T
1
4 W. Morris (cont'd)
1
2
2
35.5 2x2 Pris.
71
1 1
2
2
27 2LEBFBO32LP
54
Public Serv. Recept
3
4
12
35.5 2x4 Pris.
426
26
3
2
61
39 4LEBF032HP
2
234
1 W500
1 T
Public Serv. (cont'd)
1
2
2
35,5 2x2 Pris.
71
11
2
2
27 2LEBFBO32LP
54
4 Halfway
41
2
8
35.5 4' Rec. Pris.
284 16-22
4
2
8
27 2LEBF032LP
216
4 See. Office
2
41
8
35.5 2x4 Parabolic
284
50
2
2
4
39 4LEBF032HP
1
156
1 PIR
1 T
4 Sec. Office (cont'd)
1
2
2
35.5 2x2 Parabolic
71
1
21
2
27 2LEBFBO32LP
54
41F. Reichle
4
4
16
35.5 2x4 Parabolic
568
103
4
2
8
39 4LEEF032HP
2
312
1 PIR
1 T
41F. Reichle (cont'd)
2
2
4
35.5 2x2 Parabolic
142
2
2
4
27 2LEBF8032LP
108
Planning
32
4
1281
35.5 2x4 Pris.
4,544
124
32
2
64
39 4LEBF032HP
16
2,496
2 W200
2 T
Planning (coned)
2
2
4
35.5 2x2 Pris.
142
2
2
4
27 2LEBFBO32LP
108
4 Ping. Back OR.
4
4
16
35.5 2x4 Pris.
568
84
4
2
8
39 4LEBF032HP
2
312
1 W500
2 T
1
4 Planning Off.
3
4
12
35.5 2x4 Pris.
426
60
3
21
6
39 4LE13FO32HP
2
234
1 WS
A Planning Off.
5
4
20
35.5 2x4 Pris.
710
157
5
2
10
39 4LEBF032HP
3
390
1 WS
4 Planning Conf. Rm.
2
41
8
35.5 2x4 Pris.
284
47
2
2
4
39 4LESF032HP
1
156
1 PIR
2 T
1
4 Computer Rm.
7
4
28
35.5 2x4 Pris.
994
102
7
2
14
39 4LEBF032HP
41
546
2 W500
1 T
4 Repro Rm.
2
4
8
35.5 2x4 Pris.
284
70
2
2
4
39 4LEBF032HP
1
156
1 WS
4 Conf. Rm.
8
4
32
35.5 2x4 Pris,
1,136
1021
81
2
16
39 4LEBF032HP
4
624
4 Conf. Rm. (cont'd)
2
2
4
35.5 2x2 Pris.
142
1
2
2
4
27 2LEBFBO32LP
108
4 Lobby/Hall
4
4
16
35.5 2x4 Pris.
568
61
4
2
8
27 2LEBF032LP
216
4 Lobby/Hall (cont'd)
4
1
4
75 ER
300
4
1
4
131 ER30-600
52
4 LobbylHall (cont'd)
11
2
22
35.5 4' Rec. Pris,
781
11
2
22
27 2LESF032LP
594
4 LobbylHall (cont'd)
2
2
4
35.5 2x4 Pris.
142
2
2
4
27 2LEBFBO32LP
108
4 lnspectors Off.
4
2
8
35.5 2x2 Pris.
284
53
4
2
8
27 2LEBFBO32LP
216
1 W100
1 T
4 Inspec. Off. (cont'd)
4
4
16
35.5 2x4 Pris.
568
4
2
8
39 2LESF032HP
312
4 File Room
6
2
12
41 4' SM Strip
4921
20
6
2
12
39 2LEBF032HP
468
1 W500
1 NT
Proj. Admin.
15
4
601
35.5 2x4 Pris.
2,130
94
15
2
301
39 4LEBF032HP
8
1,1701
3 W500
3 T
Proj. Admin. (cont'd
2
2
4
35.5 4' Rec, Pris.
142
1
21
2
41
27 2LESF032LP I
108
518197 Page 3 10:45 AM
9419165 Workbook a 5-5-97
SCOPE OF WORK
City of Costa Mesa
• CI Hall
Existing Lighting
Proposed Lighting System
Proposed Control System
I
Type
Cantrol
#PP Ceiling SensarSrope
Fir Room Name
#
# Fie!
Lam
ps
Total
Lamps
Watts l FixtlLamp
Lamp Desc.
Total %Vatts
Foot
Candle
# Fix1
# Lam
ps
Total
Lamps
1Vatls!
Lamp SlrategyDesc.
# T1V Total
Al Rel
Wans 1
Qty ITvpe#PP
Type
Ceiling BC Zant SM
4 Office
4
4
16
35.5 2x4 Pris.
568
123
4
2
$
39 4LEBF032HP
2
312
1 VV500
1 T
4 Office (cont'd)
2
2
4
35.5 2.2 Pris.
142
2
2
4
27 2LEBFBO32LP
108
4 P. Naghavi Trans.
8
4
32
35.5 2x4 Pris.
1,136
130
8
2
16
39 4LE6 032HP
4
6241
1 W500
1 T
Trans. Bullpen
27
4
108
35,5 2x4 Pris.
3,834 46.107
27
2
54
39 4LEBF032HP
14
2,106
4 W100
4 T
Trans. SIP
2
2
4
35.5 2x2 Pris.
142
92
2
2
4
27 4LEBFBO32LP
1
108
1 PIR
1 T
4 D. Sorge
2
4
8
35.5 2x4 Pris_
284
1 21
2
41
39 2LEBF032HP
156
4,D. Theriault
2
4
8
35.5 2x4 Pris, 41K
284
621
2
2
4
39 4LEBF032HP
1
156
1 IVVS
4 Mike's Sec.
4
4
16
35.5 2x4 Pris.
568
661
4
2
8
39 4LEEF032HP
2
3121
1 W500
1 T
4 Mike's Sec. (cont'd)
2
2
4
35.5 2x2 Pris.
142
2
2
41
27 2LF-BFBO32LP
10811
4 Mike Waters
2
4
8
35.5 2x4 Pris,
284
164
2
2
4
39 4LEBF032HP
1
1561
1 W500
1 T
4 Mike Waters (cont'd
1
2
2
35.5 2x2 Pris.
71
1
2
2
27 2LEBFBO32LP
54
4 K. Adams
4
4
16
35.5 2x4 Pris.
568
169
4
21
8
39 4LEBF032HP
1 2
312
1 PIR
2 T 1
4 K, Adams (cont'd)
1
2
2
35.5 2x2
71
1 1
22
27 2LEBFBO32LP
54
Risk Mgmt. BIP
10
4
40
35.5 2x4 Pris.
1,420
$9
10
2
20
39 4LEBF032HP
5
780
1 W100
2 T
Risk Mgmt. SIP (co
5
2
10
35.5 2x2 Pris.
355
5
2
2
2
10
4
27 2LEBFBO32LP
39 2LEBF032HP
270
156
1 W500
1 WS
T
3 Supervisor
2 4 8 35.5 2x4 Pris. 284 77
3 Supervisor (cont'd)
4
2
8
35.5 2x2 Pris,
284
4
2
8
27 2LEBF8032LP
216
3 Supervisor (cont'd)
1
2
2
35.5 4' Rec. Pris.
71
1
2
2
27 2LEBF032LP
54
Word Processing
28
4
112
35.5 2x4 Pris.
3,976
105
28
2
56
39 4LEBF032HP
14
2,184
2 VV100
4 T
Mailroom
20
4
80
35.5 2x4 Pris.
2,840
92
20
2
40
39 4LEBF032HP
10
1,560
1 W200
1 T
3 Conf. Rm. 8
6
4
24
35.5,2x4 Pris.
852
140
6
2
12
39 4LEBF032HP
4
468
3 Conf. Rm, A
10
A
40
35.5 2x4 Pris.
1,420
94
10
2
20
39 4LEDF032HP
5
780
3 Conf. Rm. A (cont'd
1
2
2
35.5 2x2 Pris.
71
1
2
2
27 2LEBF032LP
54
3 Lobby Hall
2
4
8
35.5 2x4 Pris,
284
30
2
2
4
27 2LEBF032LP
108
3 Lobby (cont'd)
12
2
24
35.5 4' Rec. Pris,
852
12
2
24
27 2LEBF032LP
648
Personnel
8
4
32
35.5,2x4 Pris.
1,136
152
8
2
16
39 4LEBF032HP
4
624
1 W100
3 T
Personnel (cont'd)
2
21
4
35.5 2x2 Pris.
142
2
2
4
27 2LEBFBO32LP
108
Personnel (cont'd)
3
2
6
35.5 4' Rec. Pris.
213
3
2
6
27 2LEBF032LP
tfi2
3 File Rm.
4
2
8
41 4' SM Strip
328
60
4
2
8
27 4LEBF032LP
2
2161
1 WS
3,H. Perkins
2
4
8
35.5 2x4 Pris,
284
104
2
2
4
39 4LEBF032HP
1
1561
1 W500
2 T
3 H. Perkins (cont'd)
41
2
8
35.512x2 Pris.
284
4
2
8
27 2LEBFBO32LP
216
3 Comm. Serv. Hall
5
2
10
35.5 4' Rec. Pris.
355 6-20
5
210
27 2LEBF032LP
270
CommunityServ.
13
4
52
35.5 2x4 Pris.
1,846
102
13
2
26
39 4LEBF032HP
7
1,014
2 W100
4 T
Comm Serv. (cont'd
7
2
14
35.5 2x2 Pris.
497
7
2
14
27 2LEBFBO32LP
378
3L327 Rec. Supt.
3
4
12
35.5 2x4 Pris.
426
102
3
2
6
39 4LEBF032HP
2
234
1 W500
2 T
518197
Page 4
10:45 AM
SCOPE OF WORK
Citv of Costa Mesa - City Hall
9410165 Workbook i, .. 5-5-97
518197 Page 5 10:45 AM
Existing Lighting
Proposed Lighting System
Proposed Control System
Contral
#PP
.rare
Ceiling SrusorScope
Fir Room Name
#
is Fixt
Lam
ps
Tolat
Lamps
Walk! Fixt/Lamp
Lamp nese.
Total Watts
Foot
Candle
#
# Fixt
lam
ps
Twat
Lampe
Walls/
Lamp Strategy Dec.
# TNV Total
# Ret
Walls t
Qty Type
# PP
Type
Ceiling BC Tone SAI
3 327 Rec. Supt. (con
6 2 12 35.52x2 Pris. 426
6 2 12 27 2LEBF8032LP 324
3 R. Brunette
2
41
8
35.5 2x4 Pris_
284
113
21
2
4
39 4LEBF032HP
1
156
1 PIR
2 T
3 R. Brunette (cont'd)
4
2
8
35.5 2x2 Pris.
284
4
2
8
27 2LEBFBO32LP
216
3 T. Nuzum
2
4
8
35.5 2x4 Pris.
284
115
2
2
4
39 4LEBF032HP
1
156
1 WS
3 T. Nuzum (cont'd)
4
2
8
35.5 2x2 Pris.
284
4
2
8
27 2LEBFBO32LP
216
3 Office
2
4
8
35.5 2x4 Pris.
284
63
2
2
4
39 4LEBF032HP
1
156
1 WS
3 Office (cont'd)
4
2
8
35.5 2x2 Pris_
284
4
2
8
27 2LEBFBO32LP
216
31K. VanHolt
4
4
16
35.5 2x4 Pris.
568
108
4
2
8
39 4LEBF032HP
2
312
1 WS
3 K. VanHolt (cont'd)
2
2
4
35.5 2x2 Pris.
142
2
2
4
27 2LEBFB032LP
108
3 BackOffice
2
4
8
35.5 2x4 Pris.
284
64
2
2
4
39 4LEBF032HP
1
156
1 WS
3 Back Off. (cont'd)
2
2
4
35.5 2x2 Pris.
142
2
2
4
27 2LEBFBO32LP
108
3 C. Blueu
4
4
16
35.5 2x4 Pris.
568
73
4
2
8
39 4LESF032HP
2
312
1 1N500
2 T
3,C. Blueu (cont'd)
2
2
4
35.5 2x2 Pris,
1 142
2
2
4
27 2LEBFBO32LP
108
3 Personnel Dir.
4
4
16
35.5 2x4 Pris.
568
158
4
2
8
39 4LEBF032HP
2
312
1 WS
3 Personnel Dir. (con
2
2
4
35.5 2x2 Pris.
142
2
2
4
27 2LESF8032LP
108
2 Inspectors
4
4
16
35.5 2x4 Pris.
568
86
4
2
8
39 4LEBF032HP
2
312
1 W500
2 T
2 Inspectors (cont'd)
2
2
4
35.5 2x2 Pris.
142
2
2
4
27 2LEBFBO32LP
108
2 Admin.
4
4
16
35.5 2x4 Pris.
568
80
4
2
8
39 4LEBF032HP
2
312
1 W5001
2 T
2 Admin. (cont'd)
2
2
4
35.5 2x2 Pris.
142
2
2
4
27,2LEBFBO32LP
108
2 D. Lamm
9
4
36
35.5 2x4 Pris.
1,278
122
9
2
18
39 4LEBF032HP
5
702
2 Hall
5
2
10
35.5 4' Rec. Pris,
355 5-18
5
2
10
27 2LEBF032LP
270
2 M. Robinson
2
4
8
35.5 2x4 Pris.
284
921
2
2
4
39 4LEBF032HP
1
156
1 WS
2,M. Robinson (cont'd
4
2
8
35.5 2x2 Pris.
284
4
2
8
27 21-ESF60321-P
216
Planning
14
4
56
35.5 2x4 Pris.
1,988
117
14
2
28
39 4LE6F032HP
7
1,092
1 VV200
2 T
Planning (cont'd)
1
2
2
35.5 2x2 Pris.
71
1
2
2
27 2LEBFBO32LP
54
1 PIR
T
Planning B/P
24
4
96
35.5 2x4 Pris.
3,408 89-114
24
2
48
39 4LEBF032HP
12
1,872
1 W700
6 T
Planning BIP (cont'd)
0
0
0
0
2 W500
T
2,P. Valentine
2
4
8
35.5 2x4 Pris.
1 284
58
2
2
4
39 2LEBF032HP
156
2 P. Valentine (cont'd)
4
2
8
35.5 2x4 Pris.
284
4
2
8
27 2LEBF8032
216
7 WS
2 Code Enforcement
4
4
16
35.5 2.4 Pris.
568
60
4
2
8
39 2LEBF032HP
312
1 W200
2 T
2 Code Enforcement (
8
2
16
35.5 2x2 Pris.
568
8
2
16
27 2LEBFBO32LP
432
1 W500
IT
Lounge'
4
4
16
35.5 2x4 Pris.
568
76
4
2
8
39 2LEBF032HP
312
1 W500
1 T
Lounge (cont'd)
1
2
2
35.5,2x2 Pris.
71
1
2
2
27,2LEBFBO32LP
54
Lounge'
4
4
16
35.5 2x4 Pris.
568
76
4
2
8
39 2LEBF032HP
312
1 W500
1 T
Lounge (cont'd)
1
2
2
35,512x2 Pris.
71
1
2
2
27 2LEBFBO32LP
54
518197 Page 5 10:45 AM
9410165 Workbook .. 5-5-97
SCOPE OF WORK
City of Costa Mesa - Ci Hall
Existing Lighting
Proposed Lighting System
Proposed Control System
Type
Control
NPI? Ceifing Srnsorscope
#
Lam
Total
watts / Fixt/Lamp
Font
# Lam
Total
Watts 1
# Rel
Tv
Fir Room Name
# Flxl
ps
Lamps
Lamp Dna
Total Watt%
Candle
# Fixt
ps
[.amps
Lamp StralrgyDesc.
#,111, Total \Facts 1
Qtv Type
# PP Ctil C g BC Zone Sm
2 N. Stallcup
3
41
12
35.5 2x4 Pris.
426
71
3
2=6
39 2LEBF032HP
234
1 W500
2 T
2 N. Stallcup (cont'd)
1 6
21
12
35.5 2x2 Pris.
426
6
21
121
27 2LEBFB032LP
324
Devp. Serv. Lobby
11
4
44
35.5 2x4
1,562
89
11
21
22
39 4LEBF032HP
6
858
2 11V200
2 T
Devp. Serv. (cont'd)
3
2
6
35.5 2x2
213
3
2
6
27 2LEBF8032LP
162
Devp. Serv, (coni'd)l
8
1
8
35.5 4' Rec. Pris_
284
1
8
1
8
27 1 LEBF032LP
216
2 Blueprint Rm.
6
2
12
35.5 2x4 Wrap
426
35
6
2
12
39 4LEBF032HP
3
468
1 WS
Bldg. Safety
42
41
168
35,5 2x4 Pris_
5,964
130
42
2
84
39 4LEBF032HP
21
3,276
1 W200
6 T
Bldg. Safety (cont'd)
8
21
16
35.5 2x2 Pris.
568
18
2
161
27 2LEBF032LP
1
432
1.W1000
T
2 Hall
3
2
6
35.5 4' Rec. Pris.
213 6-19
3
2
6
27 2LEBF032LP
162
2 Conf. Rm.
8
4
32
35.512x4 Pris.
1,136
8
2
16
39 4LEBF032HP
4
624
2 Conf. Rm. (cont'd)
4
2
8
35.5 2x2 Pris.
284
4
2
8
27 2LEBF032LP
216
2 T. C'De Baca
6
4
24
35.512x4 Pris.
852
6
2
12
39 4LEBF032HP
3
468
1 V11500
2 T
2 T. C'De Baca (cont'
3
2
6
35.5 2x2 Pris.
213
3
2
6
27 2LEBF032LP
162
2 Hall
1
4
4
35.5 2x4 Pris.
142
1
21
2
27 2LEBF032LP
54
2 Hall (cont'd)
1
2
2
35.5 2x2 Pris.
71
1
2
2
27 2LEBF032LP
1
54
2 R. Cochran
4
41
16
35.5 2x4 Pris,
568
4
2
8
39 4LEBF032HP
21
312
1 W5002
T
2 R. Cochran (cont'd)
2
2
4
35.5 2x2 Pris,
142
2
2
4
27 2LEBF032LP
108
2 Comer Off.
Locked
0
0
2 Finance Dir.
4
4
16
35.5 2x4 Pris.
568
4
21
8
39 4LEBF032HP
2
312
1 W500
2 T
2 Finance Dir. (cont'd)
2
2
4
35.5 2x2 Pris.
142
2
21
4
27 2LEBF032LP
108
Finance BIP
25
4
100
35.5 2x4 Pris.
3,550
25
2
50
39 2LESF032HP
1,950
1 W200
3 T
Finance BIP (cont'd
9
2
18
35.5 2x2 Pris.
639
9
2
18
39 4LEBF032HP
5
702
1 W1000
T
Finance BIP (cont'd
4
2
8
35.5 4' Rec. Pris. 1
284
4
2
8
39 2LEBF032HP
312
1 VV5001
T
1 Budget 8 Resource
2
4
8
35.5 2x4 Pris, 1
284
53
2
2
4
39 4LEBF032HP
1
156
1 WS
1 Budget 8 Resource
4
2
8
35.5 2x2 Pris.
284
1
4
2
8
27 2LEBFBO32
216
1 Asst. Fin. Dir,
2
4
8
35.5 2x4 Pris.
284
49
2
2
4
39 4LEBF032HP
1
156
1 W5
1 Asst. Fin. Dir. (cant'
4
2
8
35.5 2x4 Pris.
284
4
2
8
27 2LE13FBO32LP
216
Purchasing
7
4
28
35.512x4 Pris. 41K
994
64
7
2
14
39 4LEBF032HP
4
546
2 VV5001
2 T
Purchasing (cont'd)
5
2
10
35.5 2x2 Pris.
355
5
2
10
27 2LEBFB032LP
270
1 Vault
81
2
16
35.5 4' SM Strip
568
27
8
2
16
27 4LEBF032LP
4
432
1 W100
2 NT
1 Purch. Super,
4
4
16
35.5 2x4
568
70
4
21
81
39 4LEBF032HP
2
312
1 WS
Computer (MIS)
8
2
16
35.5 2x4 Pris.
568
52
8
2
16
27 4LESF032LP
4
432
1 W100
2 T
Computer (MIS)
4
2 F
8
35.5 2x2
284
4
2
$
27 2LEBFBO32LP
216
1 Computer Rm.
0
0
16
0
0
Treasury
24
q
96
35.5 2x4
3,408
86r24
2
48
39 4LEBF032HP
12
1,872
1 W200
0
7 T
518197
Page 6
10:45 AM
9410165 Workbook I. .. 5-5-97
SCOPE OF WORK
(City of Costa Mesa - City Hall
Bullpen Areas
518197 Page 7 10:45 AM
nxi5ung ugnring
Nroposed Lighting System
Proposed Control System
Control
Type
# PP Ceiling Sensor Scope
Fir Room Name
#
# Fixl
Lam
ps
Total
Lamps
\Valle 1 Fixt/Lamp
Lamp heat.
Foot
Tolal Walls Candle
#
# F'iit
Lam
PS
Total
LaRIpS
Watts!
tamp Slrale-gy best.
# Rel
# TAY Total Watts 1
Qty Typt
Type
Opp Ceiling RC Zone 5111
Treasury (cont'd)
11
21
22
35.5 2.4
781
11
2
22
39 2LEBF032HP
858
1 IW1000 T
1 Mens RIR
7
2
14
35.5 4' Rec. Pris,
497
20
7
2
14
27 2LESF032LP
378
1 W100
1 NT
1 Info. Desk
3
4
12
35.5 2x4
426
58
3
2
6
39 2LEDF032HP
234
1 W500
2 T
1 Info. Desk (cont'd)
3
2
6
35.5 2x4
213
3
2
6
27 2LEBFBO32LP
162
1 City Clerk
6
4
24
35.5 2x4 Pris.
852
6
2
12
39 4LEBF032HP
3
468
1 W500
2 T
1 City Clerk (cont'd)
4
2
81
35.5 2x2 Pris.
284
88
4
2
8
27 2LEBF6032LP
216
1 City Clerk Elliott
2
4
8
35.5 2x4 Pris.
284
53
2
2
4
39 4LEBF032HP
1
156
1 1 lvvs
1 City Clerk Elliott (co
4
2
8
35.5 2x2 Pris.
284
4
2
8
27 2LEBFBO32LP
216
1 Vault
3
2
6
41 4' SM Strip
246 11-15
3
2
6
27 2LEBF032LP
2
162
1 WS
1 Ladles RIR
5
2
10
35.5 4' Rec, Pris,
355
14
5
2
10
27 4LEBF032LP
3
270
1 W100
1 NT
1 Hall
4
2
6
35.5 4' Rec. Pris.
284 7-84
4
2
8
27 2LESF032LP
216
1 Conf. Rm. A
8
4
32
35.5 2x4 Pris.
1,136
68
8
2
16
39 2LEBF032HP
624
1 Conf. Rm, A (cont'd
5
2
10
35.5 2x2 Pris.
355
5
2
10
27 2LEBFBO32LP
270
1 Conf. Rm. 8
1 5
4
20
35.5 2x4
710
52
5
2
10
39 4LESF032HP
3
390
I Conf. Rm. S (cont'd
2
2
4
35.5 2x2
142
1
2
2
4
27 2LEBFBO32LP
108
MIS
23
4
92
35.5 2x4 1
3,266
87
23
2
46
39 4LEBF032HP
121
1,794
2 W200
4 T
MIS (cont'd)
11
2
22
35.5 2x2
781
11
21
22
27 2LEBFB032LP
594
1 W500
T
I MIS Office
2
4
8
35.5 2x4
284
93
2
2
4
39 2LEBF032HP
156
1 WS
1 MIS Off. (cont'd)
1
2
2
35.5 2x2
71
1
2
2
27 2LEBFBO32LP
54
1 Print Shop
21
4
84
35.5 2x4
2,982.40-74
21
2
42
39 2LEBF032HP
1,638
2 W200
21T
1 Lounge
4
4
16
35.5 2x4
568
53
4
2
8
39 4LEBF032HP
2
312
1 Conf. Rm. C
12
4
48
35.5 2x4
1,704
66
12
2
24
39 4LEBF032HP
6
936
1 W100
2 T
1 Council Chambers
43
1
43
75 Rec. ER {dim
3,225
43
1
43
75 No Change
3,225
1 Council Chambers (
2
1
2
75 A -Lamp Eyeb
150
2
1
2
75 No Change
150
1 Council Chambers (
11
1
11
150 PAR Lamp
1,650
11
1
11
150 No Change
1.650
1 I Council Chambers (E2011
20
41 Soff.Hs
820
20
1
20
27 2LEBF032LP
10
540Total
6
3587
130612.4
1166
2227
80509 0
125
E. 7 0 p
Bullpen Areas
518197 Page 7 10:45 AM
SCOPE OF WORK
City of Costa Mesa
City Hatt -Add on
96136-07 Workbook
5!8!97
TW 1 10;52 AM
Existing Lighting
Proposed Lighting System
Proposed Control System
Control Sensor Scope
Fir Room Name
#
FixL
#
Lamps
Total
Lamps
Watts! Fixt/Lamp
Lamps Descrip.
Total Foot
Watts Candles
# #
Fixt Lamps
Total
Lamps
Watts! Tandem
Lamps Strategy Description # Fk Qty Lens
Total
Watts
# Type
Qty Type PP Ceiling BC Zone SM
CITY HALL
5 HALLWAY
2
2
4
20 X
80
2 1
2
3 XLSA7G2 PROLIGHT
6
HALLWAY
4
2
8
20 W
160
4 1
4
3 XLSA7G1 PROLIGHT
12
4 HALLWAY
2
2
4
20 X
80
3 1
3
3 XLSA7G2 PROLIGHT
9
HALLWAY
4
2
8
20 W
160
3 1
3
3 XLSA7G1 PROLIGHT
9
3 HALLWAY
2
2
4
20.X
80
2 1
2
3 XLSA7G2 PROLIGHT
6
HALLWAY
5
2
10
201W
200
5 1
5
3 XLSA7G1 PROLIGHT
15
2 HALLWAY
2
2
4
20 W
80
2 1
2
3 XLSA7G1 PROLIGHT
6
HALLWAY
4
2
8
20 X
160
4 1
4
3 XLSA7G2 PROLIGHT
12
EAST STAIR
1
2
2
20 Z
40
4 1
4
3 XLSA7G1 PROLIGHT
12
1,1 FLQOR
5
2
10
20 X
200
6 1
6
3 XLSA7G2 PROLIGHT
18
1ST FLOOR
10
2
20
20 W 1
400
9 1
9
3 XLSA7G1 PROLIGHT
27
BASEMENT
31
21
6
20 Y 1
1201
31 11
31
3 XLSA7G1 PROLIGHT I I i i
9
Total
"1
1
881
1 1
17601 1
471 1
471
1 1 01 01 01
1411
01 1 01 1 01 01 0
5!8!97
TW 1 10;52 AM
EXHIBIT A
CITY OF COSTA MESA
POLICE DEPARTMENT
EXECUTIVE OVERVIEW
City of Costa Mesa
Police Department
Basis
A mutual applications survey of all areas designated was conducted by Lighting Technology
Services, Inc.
A lighting load audit/inventory was conducted during the applications survey in all designated
areas. The existing lamps, ballasts and proposed changes are detailed in our scope of work room
list. Current operating costs are based upon all existing loads and proposed costs are based upon
recommended changes.
Several lighting day hours were used to calculate operating costs, existing and proposed, please
refer to Scope of Work Room List for a detailed list of those hours.
Energy saving calculations are based upon the average cost of $.10 per kilowatt hour of the SCE
rate schedule. Additional savings will be obtained as utility rates rise since it is unlikely they
will remain constant in future years. A (3%) three percent increase was included in the Financial
Analysis.
Cost and Savings
Based on the quantity of the fixtures referenced on our scope of work room lists, our proposal
included all lamps, ballasts, miscellaneous materials, labor, tax, permit fees, disposal and
equipment necessary for full implementation of the project. The total cost is $50,549.37. The
annual energy/operational savings for this project is $31,068.82 which will yield a 1.63 year
payback.
Scope of Work
The scope of work includes retrofitting of all T12 Fluorescent lamps and magnetic ballasts with
new T8 Lamps and Electronic Ballasts, replacement of all incandescent fixtures with new
compact fluorescent lamps or fixtures, and install occupancy sensors in selected spaces. In
addition to the energy savings referenced below, the facility will save substantial maintenance
and lamp replacement costs.
Lighting Technology Services, Inc. will provide, install and render fully operational all control
systems components, lighting fixtures, lamps, ballasts and fixture conversions. Included in our
quotation is all materials, labor, supervision, direct job expenses and/or equipment necessary to
fully execute the project scope reference and enumerated in our quotation.
Construction Schedule
Professional crews will work at night to avoid any disruption. Individual offices or areas will be
completed in one (1) night to ensure a smooth transition. Estimated time to complete is 12-14
working days.
SCOPE OF WORK DESCRIPTION
City of Costa Mesa
Police Department
Basis
A mutual applications survey of all areas designated was conducted by Lighting Technology
Services, Inc.
A lighting load audit/inventory was conducted during the applications survey in all designated
areas. The existing lamps, ballasts and proposed changes are detailed in our scope of work room
list. Current operating costs are based upon all existing loads and proposed costs are based upon
recommended changes.
Several lighting day hours were used to calculate operating costs, existing and proposed, please
refer to Scope of Work Room List for a detailed list of those hours.
Energy saving calculations are based upon the average cost of $.10 per kilowatt hour of the SCE
rate schedule. Additional savings will be obtained as utility rates rise since it is unlikely they
will remain constant in future years. A (3%) three percent increase was included in the Financial
Analysis.
EPA approved disposal of all lamps and ballasts. Method of disposal is incineration of
hazardous parts and recycling of balance of materials. Certificate of destruction will be provided
for incineration of hazardous parts, as applicable. If PCB ballasts are found to exist, then an
additional cost of $3.50 ea. will be required for proper EPA disposal.
Occupancy Sensor Room Selection Criteria
The following factors are taken into consideration when LTS makes a selection of whether or not a room
or area gets an occupancy sensor and which type of sensor may be utilized in the selection process.
1. The net resulting wattage - post lighting retrofit: As a general guideline 100 watts minimum for a
wall sensor, 300-350 watts minimum for a ceiling sensor.
2. Hours of operation - weekly, monthly or annually.
3. Cost of kilowatt hours.
4. Room shape or size and ceiling construction (suspended T -Bar vs non T -Bar i.e. plaster, concrete,
spline tile or open) dictates the type and model or sensor required.
5. Payback period or ROI required by customer.
6. Wall Sensor - room size generally 250 sq. ft. or less, room shape - wall switch must face into the
room.
7. Ceiling Sensors; a) rooms that, due to obstructions, cannot use a wall sensor and meet minimum
load, hours, kWh costs; b) rooms that meet minimum ceiling sensor requirements of numbers 1, 2, 3
and 4 above.
8. Ceiling construction - This significantly impacts installation costs due to access difficulty of non T -
Bar. A room with non T -Bar ceiling requiring a ceiling sensor with items 2 and 3 being equivalent
will require greater wattage (item No. 1) for justification.
Page 1
Qualifications
• Project quotation is limited to rooms or areas stipulated in Scope of Work description.
• Any items or fixtures missed in an LTS surveyed / audited room or area are provided at no
cost.
• Rooms or areas not included in project scope can be added and Lighting Technology
Services, Inc. will be happy to provide a quotation for rooms or areas not included in this
proposal.
• Any improper wiring of fixtures, switches or circuits that pre-existed LTS' performance of
this scope of work, will be customers responsibility. LTS will submit a written .change to
correct any improper wiring before proceeding with any work in the immediate area of the
problem.
• If asbestos is found to exist above the ceiling, customer will provide LTS with current
certified airborne particle count for verification of safety and LTS will quote the extra cost
for working in an area where asbestos is present.
Customer Responsibility
• Access to facility - To fully execute scope customer will need to grant LTS full access to
work areas at a reasonable time period. All installation will be performed evenings or off
hours at no extra cost.
• Parking - Availability of parking will need to be supplied to Lighting Technology Services
installation staff for duration of installation of project.
Page 2
EXISTING FIXTURE LEGEND
City of Costa Mesa
Police Department
Fixture Code
Description
Total # ofFixture
A
2x4x4 Recessed Troffer w/ F40T12 Lamps
330
B
2x2x4 w/ F20T12 Lamps
181
C
1 x4x2 Recessed Troffer w/ F40T12 Lamps
221
D
1x4x2 Open Strip w/ F40T12 Lamps
55
E
Incandescent Dimming wl 150w Lamp
45
F
1x1 Incandescent 75w
9
G
1x1 Incandescent 150w
46
H
2x4x4 Surface Mount wl F40T12 Lamps
13
i
2x4x2 Recessed Troffer wl F40T12 Lamps
4
J
1x4xl Open Strip wl F40T12 Lamps
1
M
2x4x2 Wrap Around wl F40T12 Lamps
4
N
150w Incandescent
10
O
2x4x2 Incandescent Hood w/ F40T12 Lamps
1
P
2x4x4 Wrap Around w/ F40T12 Lamps
3
Q
150w High Pressure Sodium HID
1
R
70w High Pressure Sodium HID
6
S
22w Circular Fluorescent
2
T
1x4xl Outdoor Fluorescent 20w Circular
20
D
1x1 x1 22w Circuline/Outdoor
39
V
400w 2x2 Mercury Vapor HID
6
W
Exit - 1 Side Ceiling Mount 6w
13
X
Exit - 2 Side Ceiling Mount 6w
3
Y
Exit - 1 Side Flush Wall Mount 6w
2
8127196 10:27 AM
96136-07 Workbook
PROPOSED LEGEND
City of Costa Mesa
Police Department
Code
Description
Total # of
Fixtures
2LEBF017LP
Standard Conversion Using Low Watt Electronic Ballast & F017 Lamps
55
4LEBF017LP
Standard Conversion Using Low Watt Electronic Ballast & F017 Lamps
124
1 LEBF032LP
Standard Conversion Using Low Watt Electronic Ballast & F032 Lamps
21
2LEBF032LP
Standard Conversion Using Low Watt Electronic Ballast & F032 Lamps
111
4LEBF032LP
Standard Conversion Using Low Watt Electronic Ballast & F032 Lamps
455
250WMHFK
250w Metal Halide Fit Kit
g
45W HALOGEN
Convert Incandescent to 45w Halogen
45
13WCFHW
Convert 60190 watt Incandescent Fixture to 13 watt Compact Fluorescent
3
22WCFHW
Convert 60190 watt Incandescent Fixture to 22 watt Compact Fluorescent
36
22WCFS1
Convert Incandescent to 22w Compact Fluorescent Screw-in
10
XLSA7G1 PROLIGHT
Exit Signs - 1 Side
15
XLSA7G2 PROLIGHT
Exit Signs - 2 Sides
3
13WCFSI
13W Compact Fluor, Screw -In
11
N1C
No Change
130
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
3B
39
40
41
42
43
44
45
46
47
SCOPE OF WORK
City of Costa Mesa
Police Department
96136-07 Workbook
8/27196
TW 1 1028 AM
Existing Lighting
Proposed Lighting System
Proposed Control System
Control
Sensor Scope
Annual I
Fir Op. Hrs, Room Name
#
Flxt.
#
Lamps
Total
Lamps
Wattsl FixtlLamp
Lamps Deschp.
Tota! Foot
Watts Candles
#
Fixt.
#
Lamps
Total
Lamps
WattV
Lamps Strategy Description # Fk
Tandem
Oty Lens
Total
Watts
Qty Type
# Type
PP Ceiling BC Zone SM
2000 LIBRARY
6
4
24
29 A
696 97
6
2
12
25.2 4LEBF032LP
6
3
302.4
1 W500 1
2 T
2000 LIBRARY (CONT -0
2
4
8
31 B
248
2
4
8
14 4LEBF017LP
112
3125 TRAINING BUREA
4
4
16
29 A
464 109
4
2
8
25.2 4LEBF032LP
4
2
205.6
1 W500
2 T
3125 TRAINING BUREA
4
4
16
31 B
496
4
2
8
14 ZLEBF017LP
4
112
3125 STORAGE
2
4
8
29 A
232
2
2
4
25.2 4LEBF032LP
2
1
100.8
3125 RESOURCES BU
2
4
8
29 A
232 48 1
2
4
8
25.2 4LEBF0321.P
201.6
1 W500
2T
3125 RESOURCES BU
2
41
8
31 B
248
2
4
8
14 4LEBF0171-P
11
112
3125 RESOURCES BU
2
2
4
29 C
116
21
2
4
25.2 4LEBF032LP
1
100.8
3125 TRAINING SUPER
4
4
16
29 A
464 76
4
2
8
25.2 4LEBF032LP
4
2
201.6
11 W500 I
31T
3125 TRAINING SUPER
2
4
8
311 B
248
2
2
4
14 2LEBF017LP
2
56
3125 TRAINING SUPER
2
2
4
29 C
116
2
2
4
25.2 4LEBF032LP
1
100.8
3125 CONFERENCE R
8
4
32
29 A
928 77
a
2
16
25.2 4LEBF032LP
8
2
403.2
1 W500
2 T
3125 CONF_ RM_ (CON
4
4
16
31 B
4961
4
2
8
14 2LEBF017LP
112
3125 POLICE CHIEF
el
41
24
29 A
696
6
2
121
25.2 4LEBF032LP
6
3
302.4
1 W500
2 T
8760 RIR
1
2
2
29 C
58
1
2
2
26 2LEBF032LP
52
3125 PIC SEC
4
4
16
29 A
464
4
2
8
25,2 4LEBF032LP
4
2
201.6
11 W500
41T
3125 PIC SEC (CONT'D
2
4
8
29 A
232
2
2
4
26 2LEBF032LP
104
3125 PIC SEC (CONT'D
3
4
12
311B
372
3
2
6
14 2LEBF017LP
84
8760 MENS RIR
1
4
4
291A
116
1
2
2
26 2LEBF032LP
1
52
1 W500
2 T
8760 MENS RIR (CONT'
1
4
4
31 B
124
1
2
2
14 2LEBF017LP
1
28
8760 WOMENS RIR
1
41
4
29 A
116
1
2
2
26 2LESF032LP
1
52
1 W500
2 T
8760 WOMENS RIR (C
1
4
4
31 B
124
1
2
2
14 2LESF017LP
1
28
3125 COMMANDER
2
4
8
29 A
232
2
2
4
25.2 4LEBF032LP
2
1
100.8
1 WS
3125 COMMANDER (C
4
4
16
31 B
496
4
2
8
14 2LEBF017LP
4
112
3125 CAPTAIN
2
4
8
29 A
232
2
4
8
25.2 4LEBF032LP
2
11
201.6
1 WS
3125 CAPTAIN (CONT'
4
4
16
311B
496
4
2
8
14 2LEBF017LP
4
112
3125 CAPTAIN
21
4
8
29 A
232 72
2
21
4
25.2 4LEBF032LP
2
1
100.8
1 WS
3125 CAPTAIN (CONT
4
4
16
31 B
496
4
2
8
14 2LEBF017LP
4
112
3125 CAPTAIN
2
4
8
29 A
232 72
2
2
4
25.2 4LEBF032LP
2
1
100.8
1 WS
3125 CAPTAIN (CONT'
4
4
16
31 B
496
4
2
8
14 2LEBF017LP
4
112
3125 AREA COMMAND
2
4
8
29 A
232
2
2
4
25.2 4LEBF032LP
2
1
1008
3125 AREA COMMAND
4
4
16
29 B
464
4
2
8
14 2LEBF017LP
4
112
7000 LOUNGE
4
4
161
291A
464
4
21
8
25.2 4LEBF032LP
4
2
201.6
1 W500 I
21T
7000 LOUNGE (CONT'D
4
4
16
31 B
496
4
2
81
14 2LEBF017LP
4
112
8760 MENS RIR
1
4
4
29 A
116
1
2
2
26 2LEBF032LP
1
52
1 W500
2 T
8760 MENS RIR (CONT'
1
4
4
31 B
124
1
2
2
14 2LEBF017LP
1
28
8760 MENS RIR (CONT'
1
2
2
29 C
58
1
2
2
26 2LEBF032LP
52
2000 JANITOR CLOSET
1
2
2
29 D
58
1
2
2
26 2LEBF032LP
521
1 TS -200
8760 WOMENS RIR
2
4
8
29 A 1
232
2
21
4
26 2LEBF032LP
104
1 W500
2 T
8760 HALL
441
2
881
29 C
2552
44
21
68
25,2 4LEBF032LP
22
2217.6
8760 HALL (CONT'D)
6
2
12
29 C
348
6
2
12
26 2LEBF032LP
312
8760 HALL (CONTD)
35
0
0
6 C
210
35
0
0
6 NO CHANGE
210
8760 HALL (CONT'D)
1
4
4
29 A
116
1
4
4
25 2LEBF032LP
1
1
104
8760 CEILING
fi
1
6
459 V
2754
6
1
6
259 25OWMHFK
1554
3125 AUDITORIUM
24
4
96
29 A
2784
24
2
48
25,2 4LEBF032LP
24
12
1209.6
1 W2000
2 T
3125 AUDITORIUM (CO
2211
22
150E 1
33001 1
22
1
22
45 45W HALOGEN
990
11 1 31251 PHONE RM_
2
21
41
29 D 1
1161
1 21
21
41
25,2 4LEBF032LP
1
100.8
1 WS
8/27196
TW 1 1028 AM
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
SCOPE OF WORK
City of Costa Mesa
Police Department
95136-07 Workbook
8127/96
TW 2
10:28 AM
Existing Lighting
Proposed Lighting System
Proposed Control System
Control Sensor Scope
Annual
Fir Op. Hrs. Room Name
3125 CONTROL RM.
3125 ELEC. RM.
#
Ftxt.
1
2
#
Lamps
2
2
Total
Lamps
2
4
Watts/ Fixt/Lamp
Lamps Descrip.
29 D
29 D
Total Foot
Watts Candles
58
116
#
Fixt_
1
2
#
Lamps
2
2
Total
Lamps
2
4
Watts/
Lamps Strategy Description # Fk
26 2LEBF032LP
25.2 4LEBF032LP
Tandem
Qty Lens
1
Total
Wafts
52
100.8
Qty Type
1 WS
# Type
PP Ceiling BC Zone SNI
1 3125 LAB 113
3125 PHOTO LAB 18
2000 STORE
1 4
4
1
4
4
4
16
16
4
29 A
29 A
29 A
464 40
464
116
4
4
1
4
41
4
16
16
4
25.2 4LEBF032LP
25.2 4LEBF032LP
25.2 4LEBF032LP
1
403.2
403.2
100.8
3125 LAB
3125 LAB
3125 HOLDING AREA
4
2
2
4
4
4
16
8
8
29 A
29 A
31 B
464 42
232
248 60
4
2
2
4
4
4
16
8
B
25,2 4LEBF0321-P
25,2 4LEBF032LP
14 4LEBF017LP
403.2
201.6
112
8760 HALL
15
4
60
29 A
1740
15
4
60
25.2 4LEBF032LP
1
1512
8760 CAGES
2
1
2
75 F
150
2
1
2
13 13WCFHW
1
26
8760 KITCHEN
4380 TRUSTEES
8760 RIR
8
6
1
2
2
41
16
12
4
29 C
150 G
29 A
464 52
1800
1161
8
6
1
21
2
2
16
12
2
25.2 4LEBF032LP
26 22WCFHW
26 2LEBF032LP 1
4
403.2
312
52
1 PIR
2
8760 SHOWER
1
11
1
75 F
75
1
1
1
13 13WCFHW
13
3125 FELONY CELLS
7
21
14
150 G
2100
7
2
14
26 22WCFHW
364
3125 MISDIFELONY
7
2
141
150 G
2100
7
2
14
26 22WCFHW
364
3125 MISD
7
2
14
150 G
2100
7
2
14
26 22WCFHW
364
2000 JANITOR
1
2
2
150 G
300
1
2
2
25 22WCFHW
52
3125 SAFETY CELL 2
2
2
4
150 G
600
2
2
4
26 22WCFHW
104
3125 SAFETY CELL 2
2
2
4
150 G
600
2
2
4
26,22WCFHW
104
3125 HOLDING TANK
2
2
4
150 G
600
2
2
4
26 22WCFHW
104
3125 RM, 117
2
4
8
29 A
232152
2
4
8
25.2 4LEBF032LP
201,6
1 W500
2 T
3125 RM, 117 (CONTD)
2
4
B
31 B
248
2
4
81
14 4LEBF017LP
112
3125 RM, 116
2
4
8
31 B
248 58
2
4
8
14 4LESF017LP
112
1 WS
3125 RM. 115
2
4
8
29 A
232 56
2
4
8
25.2 4LEBF032LP
201.6
1 W500
21T
3125 RM. 115 (CONT'D)
4
4
16
31 B
496 56
4
4
16
14 4LEBF017LP
224
3125 OFFICE
21
4
B
31 B
248 54
2
4
8
14 4LEBF017LP
112
1 WS
3125 RW 114
1
4
4
29 A
116 55
1
4
4
25,2 4LEBF032LP
100.8
3125 RM. 114 (CONTD)
3125 RM. 109
3125 SPECIAL/ DUI
2
2
10
4
4
4
8
8
40
31 B
31 B
29 A
248
248 56
1160 177
2
2
10
4
4
2
6
$
20
14 4LEBF017LP
14 4LEDF017LP
25.2 4LEBF032LP 10
4
112
112
504
1 WS
1 WS
1 W500
21T
3125 TRAFFIC
5
4
20
29 A
580 67
5
2
10
26 2LEBF032LP 5
260
1 W500
21T
3125 OFFICE
2
4
8
29 A
232 71
2
2
4
26 2LEBF032LP 2
104
1 W500
21T
3125 TRAFFIC CDR.
2
4
8
29 A
232 41
2
4
8
25.2 4LEBFD32LP
201.6
1 W500
2 T
3125 RM. 105
3
41
12
291A
a48150
3
4
12
25.2 4LEBF032LP
3024
3125 OFFICE
8760 HALL 103
3125 YOUTH SRVCS O
3125 VISITOR
3125 INTERVIEW 1
8760 HALL / INTERVIE
2
6
2
3
2
3
4
4
4
4
4
4
8
24
8
12
B
12
291A
31 B
29 A
29 A
31 B
31 B
232 1
744
232 65
348
248
372
2
6
2
3
2
3
41
4
4
4
4
4
8
24
8
12
8
12
25.2 4LEBF032LP
14 4LEBF017LP
25,2 4LEBF032LP
25.2 4LEBF032LP
14 4LEBF017LP
14 4LEBF017LP
1
201.6
336
201,6
302,4
112
168
1 PIR
1 W500
2 T 1
2 NT
3125 INTERVIEW 2
2
4
8
31113
248
2
4
8
14 4LEBF017LP
112
2000 STORAGE
3125 INTERVIEW 3
3125 INTERVIEW 4
2
2
1
4
4
4
8
8
4
31 B
29 A
29 LOCKED
248
232
116
2
2
1
41
4
4
8
8
4
14 4LEBF017LP
25.2 4LEBF032LP
25.2 4LEBF032LP
112
201.6
100,8
1 W500
2 T
3125 INTERVIEW 4 (CO
1
4
4
31 LOCKED 1
1241
1
4
4
14 4LEBF017LP
56
5840 101 DETECTIVE71-61
41
24
29 A 1
696148
6
4
24
25.2 4LEBF032LP
604,8
1 W1000
2 T
8127/96
TW 2
10:28 AM
95
96
97
98
99
10C
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
SCOPE OF WORK
City of Costa Mesa
Police Department
96136-07 Workbook
8/27196
TW 3 10:28 AM
Existing Lighting
Proposed Lighting System
Proposed Control System
Control
Sensor Scope
Annual
Fir Op. Hrs. Room Name
#
Fitt_
#
Lamps
Total
Lamps
Watts/ FixtlLamp
Lamps Descrip.
Total Foot
Watts Candles
#
Fixt.
#
Lamps
Total
Lamps
Watts/ Tandem
Lamps Strategy Description # Fk Qty Lens
Total1
Watts
Qty Type
# Type
PP Ceiling
80 Zone SM
5840 101 DETECTIVE (
4
4
15
31 B
496
4
4
16
14 4LEBF017LP
224
3125 OFFICE
2
4
8
29 A
232 67
2
4i
8
25 2 4LEBF032LP
2016
1 W500
21T
3125 OFFICE
4
4
16
31 B
496
4
4
16
14 4LEBF017LP
224
8760 HALL
1
2
2
29 C
58
11
21
2
26 2LEBF032LP
52
7000 BULLPEN
51
41
32
29 A
928 50-60
8
4
32
25.2 4LEBF032LP
806.4
1 W1000
2 T
1
7000 BULLPEN (CONT'
2
4
8
31 B
248 50-60
2
41
8
14 4LEBFG17LP
112
7000 BULLPEN (CONT
4
4
16
29 A
464 50-60
4
4
16
25.2 4LEBF032LP
403.2
1 PIR
2 T
1
7000 BULLPEN (CONT'
1
4
4
311B i
124 50-60
1
4
4
14 4LEBF017LP
56
7000 BULLPEN (CONT'
4
4
161
29 A
464 50-60
4
4
16
25.2 4LEBF032LP
4032
1 PIR
2 T
1
7000 BULLPEN (CONT'
1
4
4
31 B
124 50-60
1
4
4
14 4LEBF017LP 1
56
7000 BULLPEN (CONT'
4
4
16
29 A
464 50-60
4
4
16
25.2 4LEBF032LP 1
4032
1 PIR
2 T
1
7000 BULLPEN (CONT'
1
4
4
31 B
124 50-60
1
4
4
14 4LEBF017LP
56
7000 BULLPEN
2
4
8
29 A.
232 50-60
2
4
8
25.2 4LEBF032LP
201.6
1 PIR
2 T
7000 BULLPEN (CONT
1
4
4
31 B
124 50-60
1
4
4
14 4LEBF017LP
56
7000 BULLPEN (CONT'
2
4
B
29 A
232 50-60
2
4
8
25.2 4LEBF032LP
201.6
1 PIR
2 T
7000 BULLPEN (CONT'
1
4
4
31 B
124 50-60
1
41
41
14 4LEBF017LP
56
7000 BULLPEN (CONT'
3
4
12
29 A
348 50-60
3
4
12
25.2 4LEBF032LP
302.4
1 PIR
2 T
7000 BULLPEN (CONT'
3
4
12
29 A
348 50-60
3
4
12
25.2 4LEDF032LP
302.4
1 PIR
2 T
7000 BULLPEN (CONT'
3
4
12
29 A
348 50-60
3
4
12
25.2 4LESF0321-13
302.4
1 PIR
2 T
7000 BULLPEN (CONT'
2
4
8
29 A
232 50-60
2
4
8
25.2 4LEBF032LP
201.6
1 PIR
2 T
7000 BULLPEN (CONT'
21
4
8
29 A
23215G-60
2
4
8
25.2 4LESF032LP
201.6
1 PIR
2 T
3125 OFFICE
3
4
12
29 A 1
348 45
3
4
12
25.2 4LESF032LP
302.4
1 W500
21T
3125 OFFICE (CONT'D)
3
4
121
31 B
372
3
4
12
14 4LESF017LP
168
3125 OFFICE
3
4
12
31 B
372 47
3
41
12
14 4LEBF017LP
168
11 W500
21T
3125 OFFICE (CONT'D)
1
4
4
29 A
116
1
4
4
25.2 4LEBF032LP
100.8
8760 HALL
10
2
20
29 C 1
580
10
2
20
25.2 4LEBF032LP
5
504
8760 HALL (CONT'D)
2
2
4
29 C
its
2
2
4
26 2LEBF032LP
104
8760 HALL (CONT'D)
8
01
0
6 C
481
8
0
01
6 NO CHANGE
48
3125 MAIN ENTRY
6
4
24
29 H
696
6
2
12
26 2LEBF032LP
61 1
312
3125 MAIN ENTRY
6
4
24
29 H
696
6
2
12
26 2LEBF032LP
6
312
3125 MAW ENTRY
3
4
12
31 B
372
3
2
6
14 4LEBF017LP
3 3
84
3125 MAIN ENTRY
3
0
0
4 8
12
3
0
0
4 NO CHANGE
12
8760 MENS RIR
2
2
4
291
116
2
2
4
26 2LEBF032LP
104
1 W500
2 T
2000 JANITOR
2
4
8
31 B
248
2
4
8
14 4LEBF017LP
1121
1 TS -200
8760 WOMENS RJR
21
21
4
291
1161
2
2
4
25,2 4LEBF032LP
1
1008
1 W500
2 T
8760 WOMENS R/R (C
1
1
1
29 J
29
1
1
1
32 1LEBF032LP
32
3125 RECORDS MGR.
4
4
16
31 B
496 6C
4
4
16
14 4LESF017LP
224
1 PIR
2 T
3125 RECORDS CDR.
2
4
8
29 A
232
2
4
8
25.2 4LEBF032LP
201.6
1 PIR
2 T
3125 CPU RM.
2
2
4
291D
116 60
2
2
4
25.2 4LESF032LP
1
100.8
1 DT100
3
1
3125 CPU RM. (CONTD
2
4
8
311B
248 1
2
2
4
14 2LEBF017LP
2
56
3125 CPU RM. (CONT'D
8
4
32
29 A
928
8
2
16
25,2 4LEBF032LP
8 4
403.2
3125 OFFICE
121
41
48
29 A
1392 66
1 12
2
24
25.2 4LEBF032LP
8 4
604.8
1 W1000
2 T
1
3125 LARGE OPEN AR
22
4
88
29 A
2552 72
22
2
44
25.2 4LEBF032LP
22 8
1108.8
3125 LARGE OPEN AR
10
4
40
31 B
1240
10
2
20
14 4LEBF017LP
5
280
7000 BREAK RM
4
4
16
29 A
464
4
2
8
26 2LEBF032LP
4 2
208
1 PIR
2 T
7000 WOMENS RIR
1
4
4
29 A
116
11
41
41
25,2 4LEBF032LP
100.8
1 W500
2 T
7000 WOMENS RIR (C
1
2
21
291C
58
11
21
21
26 2LEBF032LP
52
8/27196
TW 3 10:28 AM
14:
I<
14�
14�
14E
141
14E
145
15C
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
152
183
184
185
186
187
188
SCOPE OF WORK
City of Costa Mesa
Police Department
96136-07 Workbook
8127196
TW 4 10,28 AM
Existing Lighting
Proposed Lighting System
Proposed Control System
Control
Sensor Scope
Annual
Fir Op. Hrs. Room Name
#
Fixt.
#
Lamps
Total
Lamps
Watts/ Fixt/Lamp
Lamps Descrip_
Total Foot
Watts Candles
#
Fixt.
#
Lamps
Total
Lamps
Watts! Tandem
Lamps Strategy Description # Fk Qty Lens
Total
Watts
City Type
# Type
PP Ceiling EIC Zone SM
7000 WOMENS LOCKE
S 7000 WOMENS LOCKE
1
4
4
2
4
829
31 B
C
124
232
1
4
4
2
4
8
14 2LE:BF0171-P
25.2 4LESF032LP
2
56
201.6
I 7000 MENS RIR
1
4
4
31 B
124
1
4
4
14 4LEE13FOl71-13
56
I 7008 MENS RIR (CONT
1
41
4
29 A
116
1
2
2
26 2LEBF032LP
1
52
1 W500
2 T
i 7000 MENS RIR {CONT'
2000 STORAGE
1
2
2
2
2
4
29 C
29 D
58
116
1
2
2
2
2
4
26 2LEBF032LP
25.2 4LEBF032LP
1
52
100.8
3125 WATCH CDR.
4
4
16
29 A
464
4
41
16
25.2 4LEBF032LP
4032
1 W500
2 T
3125 WATCH CDR. (CO
3125 REPORT RTG. R
2
3
4
4
8
12
31 B
29 A
248
348 85
2
3
41
21
8
6
14 4LEBF017LP
26 2LEBF032LP
3
112
156
1 VV500 1
2 T 1
3125 REPORT RTG. R
61
4
24
31 B
7441
6
2
12
14 2LEBF017LP
6
168
8760 HALL
7
4
28
31 B
868
7
4
28
14 4LEBF017LP
392
3125 RM, 107
4
4
16
31 B496
4
4
16
14 4LEBF017LP
224
3125 RM. 108
4
4
16
29 A
464
4
2
8
25.2 4LEBF032LP
4 2
201,6
1 W500 IT
3125 RM. 108 (CONT'D)
4
4
16
31 8
496
4
2
8
14 2LEBF017LP
4
112
2000 STORAGE
2
2
41
29 D
116
2
2
4
25.2 4LE9F032LP
1
100.8
3125 RM. 111
2
4
81
29 A
232 67
2
41
8
25.2 4LEBF032LP
201.6
1 W500
2 T
3125 RM_ 111 (CONT'D)
4
4
16
311B
496
4
4
16
14 4LEBF017LP
224
8760 HALLWAY
4
2
8
29 C
232
4
2
8
25.2 4LEBF0321-13
4 2
201.6
8760 HALLWAY (CONT'
2
0
0
6 C
12
2
0
01
6 NO CHANGE
12
3125 BACK PROPERTY
4
4
16
29 A
464
4
4
161
24.2 4LEBF032LP
387.2
3125 BACK PROPERTY
9
2
18
29 D
522
9
2
18
26 2LEBF032LP
468
3125 BACK PROPERTY
4
41
16
29 A
464
4
4
16
24.2 4LEBF032LP
387.2
3125 BACK PROPERTY
3
1
31
13 LOCKED
39
3
1
3
13 NO CHANGE
39
8760 HALLWAY
10
2
20
29 C
584
10
2 1 1
20
25.2i 4LESF032LP
5
504
8760 HALLWAY (CONT'
4
2
8
29 C
232
4
21
8
26 2LEBF032LP
208
8760 HALLWAY (CONT
8760 N_ STAIRS
10
1
0
2
0
2
6 C
29 M
60
58
10
1
01
21
❑
2
6 NO CHANGE:
26 2LESF032LP
60
52 1
1
2000 WEAPONS STOR
3
1
3
75 LOCKED
225
3
1
3
13 13WCFSI
39
1 WS
2000 WEAPONS STOR
31
1
3
75 LOCKED
225
3
1
3
13 13WCFSI
39
1 WS
8760 GUN CLEAN RM_
41
4
161
29 A
464 60
4
4
16
25.2 4LEBF032LP
403.2
1 W500
2 T
8760 MENS LOCKER
61
4
24
29 A
696
6
2
12
26 2LEBF032LP
6 6
312
1 W500
2 NT
8760 MENS RIR
21
2
4
29 C
116
2
2
4
26 2LEBF032LP
104
1 W500
2 NT
8760 MENS RIR (CONT'
21
2
4
29 C
116
21
2
4
25.2 4LEBF032LP
1
100 8
8760 RIR HALL
21
2
4
29 C
116
2
21
4
25.2 4LESF032LP
10081
1
8760 SHOWER
4
1
4
60 F
240
4
1
4
13 13WCFSI
52
8760 LOCKER RM.
24
2
48
29 C
1392
24
2
481
25.2 4LEBF032LP
8
1209,6
2 W500
2 NT
8760 LOCKER RM. (CO
3
2
6
29 C
174
3
2
61
25.2 4LE13FO32LP
151,2
2000 B-13
4
21
8
29.1)
232
4
2
8
25.2 4LEOF032LP
2
201.6
1 TS -200
2000 B-14 TELCO.
4
2
8
291D
232
4
2
8
25.2 4LEBF032LP
2
201.6
1 TS -200
2000 B-15
8-
1
8
150IN
12001
8
1
8
26 22WCFSI
208
2000 B-15 (CONT'D)
1
4
4
2911-1
116
1
4
4
25.2 4LEBF032LP
100.8
2000 B-15 (CONT'D)
2000 B-15 (CONT -0)
1
1
2
2
2
2
29 O
29 M
58
58
1
1
2
2
2
2
26 2LEBF032LP
26 2LEBF032LP
52
52
8760 S. STAIRWELL
2
2
4
29 M
116
2
2
4
26 2LEBF032LP
104
5840 PROPERTY
4
4
16
29 A
464 50
4
4
16
252 4LEBF032LP
403.2
1 W500
27-
T5840
5840 PROPERTY RM.
2
2
4
29 D
116 10-45
2
2
4
25.2 4LE8F032LP
1
100.81
11 W500
2 NT
5840 PROPERTY RM_ {
1
2
2
29 D
58110-45
2
2
4
26 2LEBF032LP
104 11
1
8127196
TW 4 10,28 AM
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
SCOPE OF WORK
City of Costa Mesa
Police Department
96136-07 Workbook
8/27196
TW
10'28 ,''M
Existing Lighting
Proposed Lighting System
Proposed Control System
Control
Sensor Scope
Annual
Fir Op. Hrs. Room Name
#
Fixt
#
Lamps
Total
Lamps
Watts/ FixtlLamp
Lamps Descrip.
Total Foot
Watts Candles
#
Fixt.
#
Lamps
' Total
Lamps
Watts/
Lamps Strategy Description # Fk
Tandem
Qty Lens
Total
Watts
My Type
# Type
PP Ceiling BC Zone SM
5840 PROPERTY RM.
2
2
4
29 D
116 1045
2
2
4
25.2 4LEBF032LP
1
100.8
1 W500
2 NT
5840 PROPERTY RM. (
1
2
2
29 D
58 1045
1
2
2
26 2LEBF032LP
52
68401 NARCOTICS STA
6
4
24
29 A
696
6
4
24
25.2 4LEBF032LP
60481
1 W500
2 T
2000 STORE RM.
21
41
8
291A
232
21
41
8
25.2 4LESF032LP
201.6
8760 WOMENS LOCKE
3
4
12
29 A
3481
1 3
4
12
25.2 4LESF032LP
302.4
11 W500
21 NT
8760 WOMENS RJR
1
4
4
29 A
116
1 1
2
2
26 2LEBF032LP 1
52
1 W500
2 NT
8760 WOMENS RIR (C
1
4
4
31 B
124
1
2
2
14 2LEBF017LP 1
28
8760 WOMENS RIR (C
1
1
1
75 F
75
1
1
1
13 13WCFS1
13
3125 OFFICE
3
4
12
31 B
372
3
4
12
14 4LEBF017LP
168
1 PIR
2 T
3125 OFFICE
4
4
16
31 B
496
4
4
16
14 4LEBF017LP
2241
1 WS
7000 B-8 EXERCISE R
2
41
8
311B
248
2
4
81
14 4LEBF017LP
112
7000 B-8 EXERCISE R
23
1
23
150 E
3450 1
231
1
23
45 45W HALOGEN
1035
7DDD B-8 EXERCISE R
17
4
68
29 A
1972
17
4
68
25.2 4LEBF032LP
1713.6
11 W20001
31T
2000 STORAGE
D
LOCKED
0
0
0
2000 JANITOR CLOSET
1
2
2
29 D
58
1
2
2
26 2LEBF032LP
52
1 TS -200
7000 B-7 SQUAD RM.
8
4
32
31 B
992 95
8
2
16
14 4LEBF017LP 8
4
224
11 W1 0001
21T
7000 B-7 SQUAD RM. (
8
4
32
29!A
928
8
2
16
26 2LEBF032LP 3
416
5840 B4 HALL
31
4
12429
B
372
3
4
12
14 4LEBF017LP
168
3125 GANG DETAIL
4
4
16B
496 67
4
4
16
14 4LEBF017LP
224
1 W500
2 T
3125 GANG DETAIL (C
4
4
16A
454
4
4
16
25.2 4LEBF032LP
403.2
5840 TARGET
2
4
8A
232 53
2
4
8
25.2 4LEDFO32LP
201,6
1 W500
2 T
5840 TARGET (CONT'D
2
4
BB
248
2
4:
8
14 4LEBF017LP
112
2000 STORAGE
0LOCKED
0
0
0
5840 SED
4
4
16A
464 76
4
2
8
26 2LEBF032LP 4
208
1 W500
2 T
5840 $ED (CONT'D)
4
41
16
31 8
496
41
41
16
17 4LEBFOI7LP
272
5840 RANGE ENTRY
1
2
2
29 D
58
1
2
2
26 2LEBF032LP
52
5840 WEAPON STORE
3
2
6
29 D
1741
3
2
6
26 2LEBF032LP
156
1 W500
2 T
5840 ENTRY
1
4
4
31 B
124
1
2
2
14 2LEBF017LP
28
2000 STORAGE
1
2
2
29 C
58
1
2
2
26 2LEBF032LP
52
1 TS -200
5840 RANGE CONTRO
3
4
12
29 P
34B
3
4
12
25.2 4LEBF032LP
302.4
1 W500
NT
2000 RANGE
to:2
20
29 0
580
10
2
20
252 4LEBF032LP
5
504
2000 RANGE (CONTD)
5
2
10
29 D
290
51
21
10
26 2LEOF032LP
260
2000 RANGE (CONT'D)
2
2
4
29 C
116
2
2
4
25.2 4LEBF032LP
1
100.8
2000 RANGE (CONT'D)
1
2
2
29 C
58
1
2
2
26 2LEBF032LP
52
8760 HALLWAY
12
2
24
41 C
984
12
2
24
25.2 4LEBF032LP
6
604.8
8760 HALLWAY (CONT
4
2
8
29 C
2321
4
2
B
26 2LEBF032LP
208
8760 HALLWAY (CONT'
121
0
0
6 C
72
12
0
0
6 NO CHANGE
72
3640 OUTSIDE
1
1
1
150 0
150
1
1
1
150 NO CHANGE
150
3640 OUTSIDE (CONT'
4
1
4
70 R
280
1
1
1
70 NO CHANGE
70
3640 JAIL DRIVE
12
1
12
150 G
1800
12
1
12
150 NO CHANGE
1800
3640 OUTSIDE
2
2
4
22 S
88
2
2
4
22 NO CHANGE
88.
36DO HELD PAD
20
1
20
29 T
580
20
1
20
32 1LEBF032LP
6401
1 TCIPC
36DO HELO PAD (CONT
1
1
1
70 R
70
1
1
1
70 NO CHANGE
70
3640 OUTSIDE FRONT
1 11
1
1
70 R
70
1
1
1
70 NO CHANGE
70
3640 WALKWAY 11
391
1
39
22 U
858
39
1
39
22 NO CHANGE
858
1 PC
2 8760 EXIT LIGHTS 11
81
2
16
20 W
320
8
1 I
XLSA7G1 PROLIGHT 1
24
2 8760 EXIT LIGHTS
0 21
2
4
201X
80
21
11
21
3 XLSA7G2 PROLIGHT
6
8/27196
TW
10'28 ,''M
236
237
238
239
240
241
SCOPE OF WORK
City of Costa Mesa
Police Department
96136-07 Workbook
8127198
TW 6
10:28 AM
Existing Lighting
Proposed Lighting System
Proposed Control System
Control Sensor Scope
Annual
Fir Op. Hrs. Room Name
#
Fixt.
#
Lamps
Total
Lamps
Watts! Fixt/Lamp
Lamps Descrip.
Total Foot
Watts Candles
# #
Fiat. Lamps
Total
Lamps
Watts/ Tandem
Lamps I Strategy Description # Fk City Lens
Total
Watts
# Type
Qty Type PP Ceiling BC Zane SM
1 8760 EXIT LIGHTS
3
2
6
20 W
124
3 1
3
3 XLSA7G1 PROLIGHT
9
1 8760 EXIT LIGHTS
1
2
2
20 X
40
1 1
1
3 XLSA7G2 PROLIGHT
3
1 8760 EXIT LIGHTS
2
2
4
20 Y
80
2 1
2
3 XLSA7G1 PROLIGHT
6
Viso OUTSIDE COVE A
2
1
2
75 N
150
1 21 11
2
26 22WCFSI
521
1 PC
8760 OUTSIDE COVE A
1
21
21
751F 1
150
21 11
21
26 22WCFHW I
52
B 8760 BASEMENT
21
21
41
201W
8
1 21 11
21
3 XLSA7G1 PROUGHT
6
Total
1 1026
1
28071
1 1
1026401
1 10251 1
22781
1 237 141 8
55188.41
921 1 1391 al 01 0
8127198
TW 6
10:28 AM
EXHIBIT B
FEE SCHEDULE
L T S
LIGHTING TECHNOLOGY SERVICES, INC.
Project Quotation
Quote #9410165
REFER TO TERMS/CONDITIONS SECTION
QUOTATION IS VALID FOR 90 DAYS
DATE: 8 -May -97
TO: Mike Waters
City of Costa Mesa
77 Fair Drive, 4th Floor
Costa Mesa, California
714-754-5164
FOR: City of Costa Mesa - City Hall
Qty Work/Material Description
323 112 Lamp Electronic Ballast LP
154 112 Lamp Electronic Ballast HP
16 4 Lamp Electronic Ballast LP
290,4 Lamp electronic Ballast HP
1764 1 T8 4' F032 Lamp 841 Series
384 T8 2' FB03216 U-tube Lamps 841 Series
384 T8 2' FB03216 U-tube Lampholders
8 Prolite ER30
31 WS Wall Sensor wl Switchplate
43,W500 Ceiling Sensor
24 W1000 Ceiling Sensor
15 W2000 Ceiling Sensor
12 PIR Ceiling Sensor
136 A2771 120v Powerpack
Applications/Design Engineering
Installation
Project Supervision
System Performance Guarantee
Permit Fee
Shipping
Sales Tax
TOT!5LLf ROJECT QUOTATION
$63,941.37
Presented by:
Accepted by:
Date:
Date:
1715 E. Wilshire Ave., Suite 724, Santa Ana, California 92705 ♦ Tel -(714)550-7223 • Fax -(714)550-7226
L T S
DATE: 27 -Aug -96
T0: Mike Waters
City of Costa Mesa
77 Fair Drive. 4th Floor
Costa Mesa, California 92627
714-754-5164
FOR: City of Costa Mesa - Police Department
LIGHTING TECHNOLOGY SERVICES, INC.
Project Quotation
Quote #96139-07 Revised
City of Costa Mesa
REFER TO TERMS/CONDITIONS SECTION
QUOTATION IS VALID FOR 90 DAYS
Qty Work/Material Description
21 1 Lamp Electronic Ballast
165 2 Lamp Electronic Ballast
422 4 Lamp Electronic Ballast
133 Electronic Ballast Tandem Wire Connection _
1485 IT8 4' F032 Lamp
566 T8 2' F017 Lamp
45 45w Capsylite
6 250w Metal Halide _
15 LED Exit Sign - 1 Side New Fixture
3 LED Exit Sign - 2 Side New Fixture
7 13w Compact Fluorescent Hardwired 370OH-L
7 22w Quad Compact Fluorescent Hardwired 5900-L
38 22w Quad Compact Fluorescent Hardwired 390OH-L
8 26w 2 Lamp Compact Fluorescent Drum Fixture 1026-L
8 2x4 A-12 Lens
170 2x4 Fit Kit
62 2x2 Fit Kit
5 1x4 Fit Kit
6 Advanced #72C -6082 -N -P HID Ballast
3 Time Clock Photo Cell _
6 TS -200 Digital Timers
13 WS Wall Sensor wl Switchplate
47 W500 Ceiling Sensor _
4 W1000 Ceiling Sensor _
2 W2000 Ceiling Sensor
1 DT -100L Ceiling Sensor
15 PIR Ceiling Sensor
139 A277 ! 120v Powerpack
Applications/Design Engineering
Installation
Project Supervision
System Performance Guarantee
Permit Fee
Shipping
Sales Tax
TOT OJECT QUO TION $50,549.37
Pres rated by-
'5-1-
y-
Accepted by:
Date:
'5=5,--�77
1715 E. Wilshire Ave., Suite 724, Santa Ana, California 92705 ♦ Tel: (714) 550-7223 ♦ Fax: (714) 550-7226
L T S
LIGHTING TECHNOLOGY SERVICES, INC.
Project Quotation
Quote #96139-07
City of Costa Mesa
REFER TO TERMS/CONDITIONS SECTION
QUOTATION IS VALID FOR 90 DAYS
DATE: 22 -Aug -96
TO: Mike Waters
City of Costa Mesa
77 Fair Drive, 4th Floor
Costa Mesa, California 92627
714-754-5164
FOR: City of Costa Mesa - City Hall Exit Signs
Qty Work/Material Description
27 Exit Sign - 1 Side New Fixture
17 Exit Sign - 2 Side New Fixture
Applications/Design Engineering
Installation
Project Supervision
System Performance Guarantee
Shipping
Sales Tax
TOTAL ROJECT QUOTATION
$4,623.19
Prese ►ted by:
Accepted by:
Date:
Date:
1715 E. Wilshire Ave., Suite 724, Santa Ana, California 92705 ♦ Tel: (714) 550-7223 ♦ Fax: (714) 550-7226
EXHIBIT C
TIME SCHEDULE
PROFESSIONAL SERVICES AGREEMENT BETWEEN THE CITY
OF COSTA MESA AND LIGHTING TECHNOLOGY SERVICES,
INC., FOR THE RETROFITTING OF THE LIGHTING AT THE
CIVIC CENTER
TIME SCHEDULE
FACILITY WORK DAYS TO COMPLETE THE WORK
City Hall 17 to 20
Police Department 12 to 14
Total work days will not exceed 34.