HomeMy WebLinkAbout05. CC-6 - CITYWIDE SCHOOL ZONE TRAFFIC CALMING PROJECT1 CITY COUNCIL AGENDA REPORT MEETING DATE: JANUARY 2, 2018 ITEM NUMBER: CC-6 SUBJECT: CITYWIDE SCHOOL ZONE TRAFFIC CALMING PROJECT, FEDERAL PROJECT NO. SRTSL-5312 (090), CITY PROJECT NO. 15-04 DATE: DECEMBER 13, 2017 FROM: PUBLIC SERVICES DEPARTMENT/ENGINEERING DIVISION PRESENTATION BY: RAJA SETHURAMAN, PUBLIC SERVICES DIRECTOR FOR FURTHER INFORMATION CONTACT: BALTAZAR MEJIA, CITY ENGINEER, (714) 754-5335 RECOMMENDATION: 1. Approve Contract Change Order No. 2 (Attachment 1) in the amount of $12,972.00; 2. Accept the work performed by Asplundh Construction Group and authorize the City Clerk to file the Notice of Completion; 3. Release the Labor and Materials Bond seven (7) months after the filing date; release the Faithful Performance Bond six (6) months after the filing date; and release the retention monies after the Notice of Completion is filed. BACKGROUND: On April 19, 2016, the City Council awarded a construction contract to Asplundh Construction Group, 3972 Barranca Parkway, Suite J-283, Irvine, CA 92606, in the amount of $442,557.00 for the Citywide School Zone Traffic Calming Project. The scope of work for this project included the installation of speed feedback signs, pedestrian countdown timers, school zone flashers, minor striping, and signing improvements throughout Costa Mesa. ANALYSIS : The overall scope of work required by the contract documents was completed on February 14, 2017, to the satisfaction of the City Engineer. Before Installation After Installation 2 During the course of the project it became necessary to issue two change orders to adjust the unit prices of major bid items and to install radar speed feedback signs at two (2) additional locations that were identified as priorities. A report of the final cost summary is included herein as Attachment 2. A summary of the project costs is as follows: Original Contract Cost: $442,557.00 Change Order No. 1: $ 37,565.00 Change Order No. 2: $ 12,972.00 Final Contract Price: $493,094.00 Change Order No. 1 in the amount of $37,565.00 was issued to increase the number of radar speed feedback signs with new pole and foundation and decrease the number of signs on existing poles. Change Order No. 2 in the amount of $12,972.00 compensated Asplundh Construction Group for the extra work necessary to install radar speed feedback signs at two (2) additional locations, and final quantity adjustments. The work was completed by the contractor to the satisfaction of the City Engineer on February 14, 2017. However, with the total project cost well under the approved grant amount that reimburses the City up to $796,200.00, staff has been working with Caltrans to approve additional locations up to the maximum amount of the grant. The review and approval process is lengthy and the general contractor has requested that the project be closed out now. Staff will continue to work with Caltrans to obtain their approval to utilize the balance of the grant. Pursuant to Public Contract Code Section 7107(c), “within 60 days after the date of completion of the work of improvement the retention withheld by the public entity shall be released.” For purposes of this Code Section “completion” means not only acceptance by the public agency, but per Section 7107 (c)(1) includes, “the occupation, beneficial use and enjoyment of a work of improvement …accompanied by cessation of labor on the work of improvement.” As of this date, there are no Stop Notices filed against the monies due to Asplundh Construction Group. The applicable time periods within which Stop Notices could be brought against the contractor have expired. Therefore, staff recommends that the retention monies be released to Asplundh Construction Group immediately after the Notice of Completion is filed. ALTERNATIVES CONSIDERED: No alternatives are being considered for this item. FISCAL REVIEW: The project was funded by a federal grant and was appropriated in Fiscal Year 2012-2013. LEGAL REVIEW: There is no legal review required for this item. CONCLUSION: The overall scope of work for the Citywide School Zone Traffic Calming Project has been completed. Staff is recommending that the City Council approve Change Order No. 2 in the amount of $12,972.00; authorize staff to file the Notice of Completion; release the remaining 3 retention monies immediately after the Notice of Completion is filed, and release the bonds accordingly. RAJA SETHURAMAN BALTAZAR MEJIA, P.E. Public Services Director City Engineer ATTACHMENTS: 1 - 2 - Contract Change Order No. 2 Cost Summary DISTRIBUTION: City Manager Assistant City Manager City Attorney City Clerk Staff File CITY OF COSTA MESA PUBLIC SERVICES DEPARTMENT CONTRACT CHANGE ORDER NO. 2 SUPPL NO. REV. PROJECT CITYWIDE SCHOOL ZONE TRAFFIC CALMING PROJECT SHEET 1 OF 1 FEDERAL NO.(S) SRTSL-5312 (090) CITY SPECIFICATION NO. 15-04 To ASPLUNDH CONSTRUCTION GROUP Contractor You are hereby directed to make the herein described changes from the plans and specifications or do the following described work not included in the plans and specifications on this contract. NOTE: This change order is not effective until approved in accordance with Council Policy No. 700-1 Description of work to be done, estimate of quantities, and prices to be paid. Segregate between additional work at contract price, agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. Change Requested by: CITY BRIEF WORK DESCRIPTION This Change Order was required to authorize contractor to install Radar Speed Feedback Signs at two (2) additional locations: (1) West 19th Street west of Park Avenue and (2) West 19th Street west of Placentia Avenue, and final quantity adjustment. EXTRA WORK AT CONTRACT UNIT PRICE (The sums constitutes full and complete compensation for providing all labor, materials, equipment, tools, and incidentals, including all markups) Bid item No. 2: Furnish and Install Two (2) Radar Speed Feedback Signs with Pole and Foundation - 2 EA @ $17,865.00 for $35,730.00 FINAL QUANTITY ADJUSTMENT: Quantity Adjustment for various contract bid items for net deduction of ($22,758.00). CHANGE ORDER TOTAL INCREASE: $12,972.00 The sum shall constitute full compensation, including markups for this change and no additional payment will be made. Project Summary Amount % Original Contract Amount:…………………………………………………..$442,557.00 Previously Approved Change Orders (CO No.1)………………………$37,565.00 8.49% Amount this Change Order (CO No. 2):…………………………………………$12,972.00 2.9311% Revised Contract Amount:………….……………………………………….$493,094.00 11.4193% TOTAL COST: DECREASE INCREASE: $12,972.00 By reason of this order the time of completion will be adjusted as follows: 0.0 Prepared by: Irina Gurovich, Assistant Engineer Date: 12/10/2017 Submitted by: Date: Approval Recommended: Date: Approved: Date: CITY COUNCIL MEETING OF JANUARY 2, 2018 We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full payment therefor the prices shown above Accepted, Date Contractor: Asplundh Construction Group By Title If the Contractor did not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. ATTACHMENT 1 4 CITY OF COSTA MESA FINAL PAYMENT TO: ASPLUNDH CONSTRUCTION CORPORATION DBA ASPLUNDH ELECTRICAL CONTRACTOR 1428 N.LEMON ST. ANAHEIM, CA 92801 PROJECT: CITYWIDE SCHOOL ZONE TRAFFIC CALMING PROJECT FEDERAL PROJECT NO. SRTSL-5312 (090), CITY PROJECT No. 15-04 ITEM REVISED BID UNIT PREVIOUS QUANTITY TOTAL QUANTITY PREVIOUS AMOUNT TOTAL CONTRACT NO QUANTITY DESCRIPTION PRICE QUANTITY THIS ESTIMATE TO DATE AMOUNT THIS EST TO DATE PRICE 1 10 EA FURNISH AND INSTALL SCHOOL FLASKER WITH POLE AND FOUNDATION COMPLETE $7,240.00 10.0 EA 0.0 EA 10.0 EA $72,400.00 $0.00 $72,400.00 $72,400.00 2 16 EA FURNISH AND INSTALL RADAR SPEED FEEDBACK SIGN WITH POLE AND FOUNDATION COMPLETE $17,865.00 17.0 EA -2.0 EA 15.0 EA $303,705.00 -$35,730.00 $267,975.00 $285,840.00 3 5 EA FURNISH AND INSTALL RADAR SPEED FEEDBACK SIGN ON EXISTING POLE $14,450.00 4.0 EA 1.0 EA 5.0 EA $57,800.00 $14,450.00 $72,250.00 $72,250.00 4 33 EA FURNISH AND INSTALL LED COUNTDOWN PEDESTRIAN HEAD COMPLETE $501.00 25.0 EA 0.0 EA 25 EA $12,525.00 $0.00 $12,525.00 $16,533.00 5 187 EA FURNISH AND INSTALL LED COUNTDOWN PEDESTRIAN MODULE $177.00 182.0 EA 0.0 EA 182.0 EA $32,214.00 $0.00 $32,214.00 $33,099.00 $478,644.00 -$21,280.00 $457,364.00 $480,122.00 CO1 1 LS Modification of Contract Work: Adjustment of the Unit Prices of Major Bid Items (revised quantity is incorporated in the bid schedule)$37,565.00 2 EA Extra Work: Installation of 2 Radar Speed Signes with Poles on W. 19th St.$17,865.00 0 EA 2 EA 2 EA $0.00 $35,730.00 $35,730.00 $35,730.00 1 LS Quantity Adjustment for Various Contract Bid Items ($22,758.00)0 %0 %0 %$0.00 $0.00 $0.00 -$22,758.00 CHANGE ORDERS SUBTOTAL:$0.00 $35,730.00 $35,730.00 $12,972.00 TOTAL (BASE BID PLUS CHANGE ORDERS):$478,644.00 $14,450.00 $493,094.00 $493,094.00 TOTAL: CHANGE ORDERS CO2ATTACHMENT 2ATTACHMENT 2 5