HomeMy WebLinkAbout88-75 - Certifying Earlier EIR for Triangle Square DevelopmentRESOLUTION NO. 88-75
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
COSTA MESA, CALIFORNIA, CERTIFYING AN EARLIER
ENVIRONMENTAL IMPACT REPORT AND MAKING FINDINGS
REGARDING THE ENVIRONMENTAL IMPACT OF THE PRO-
POSED TRIANGLE SQUARE DEVELOPMENT.
WHEREAS, the guidelines for implementation of the California Environ-
mental Quality Act (Title 14, California Code of Regulations Section 15153)
provide authority for the City Council of the City of Costa Mesa (the "City
Council") to use an earlier Environmental Impact Report prepared in connec-
tion with an earlier project as the Environmental Impact Report for a later
project if the circumstances of the projects are essentially the same; and
WHEREAS, on December 18, 1985, by Resolution Nos. 76-85 and 85-109,
respectively, the Costa Mesa Redevelopment Agency (the "Agency") and the
City Council certified an Environmental Impact Report (the "earlier EIR")
for the proposed development of commercial and retail space in a project
area which included the 4.5 acres bordered by Newport Boulevard, 19th
Street, and Harbor Boulevard in the City of Costa Mesa; and
WHEREAS, the City staff, relying on the earlier EIR, has prepared and
circulated for public review, an initial study for the Triangle Square
Development, a proposed retail and commercial development on the 4.5 acres
bordered by Newport Boulevard, 19th Street, and Harbor Boulevard in the
City of Costa Mesa (the "project site"); and
WHEREAS, the Agency proposes the development of commercial and retail
space on the project site by a private developer (the "developer") under
Disposition and Development Owner Particiption Agreement (the "agreement");
and
WHEREAS, proper notice has been given and duly noticed public hearings
were held by the Agency on September 14, 1988, and the City Council on
September 19, 1988, at which time all interested persons were given an
opportunity to be heard;
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
Costa Mesa, California, as follows:
1. The City Council hereby determines and certifies that:
A. The information contained in the earlier EIR has been reviewed
and considered by the members of the City Council with respect
to the proposed develpment of the project site and the proposed
agreement; and
B. The earlier EIR is adequate and has been prepared in compliance
with the provisions of the California Environmental Quality
Act, the State CEQA guidelines, and the local guidelines of
the City of Costa Mesa for implementing CEQA; and
C. Based on the Findings of Fact and Statement of Overriding
Considerations regarding the environmental impacts on the
Triangle Square Development attached to this resolution and
incorporated herein by this reference, the Triangle Square
Project will not have a significant effect on the environment.
PASSED AND ADOPTED this 19th day of September, 1988.
ATTEST:
My Clerk of the City of Costa sa Mayor of the City of Costa Mesa
STATE CF CALIFORNIA )
COUNTY OF ORANGE ) ss
CITY OF COSTA MESA )
V LLI' i
I, EILEEN P. PHINNEY, City Clerk and ex -officio Clerk of the City
Council of the City of Costa Mesa, hereby certify that the above and fore-
going Resolution No. 88-75 was duly and regularly passed and adopted by the
said City Council at a regular meeting thereof, held on the 19th day of
September, 1988.
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the Seal
of the City of Costa Mesa this 20th day of September, 1988.
�27 / to a — ) 61 -
Ci y Clerk and ex -officio Clerk the
City Council of the City of Cost Mesa
FINDINGS OF FACT AND
STATEMENT OF OVERRIDING CONSIDERATIONS
REGARDING THE ENVIRONMENTAL IMPACT
OF THE TRIANGLE SQUARE DEVELOPMENT
1. The City Council of the City of Costa Mesa hereby
finds:
A. That the circumstances of the Triangle
Square Development Project (the "Project") and the project
analyzed in EIR 1026 (the "earlier EIR" certified by this
City Council in December, 1985) are essentially the same.
The earlier EIR adequately describes the general
environmental setting of the Project, the significant
environmental impacts of the Project, and alternatives and
mitigation measures related to each significant effect of
the Project;
B. That substantial changes have not been
proposed in the Triangle Square Development Project (the
"Project") which would have required major revisions of the
earlier Environmental Impact Report;
C. That substantial changes have not occurred
with respect to the circumstances under which the Project
is being undertaken which would have required major
revisions in the earlier Environmental Impact Report; and
D. That new information, which was not known
and could not have been known at the time the earlier
Environmental Impact Report was certified as complete, has
not become available.
1. Hvdrologv
A. impact
The City Council finds that potential adverse
drainage impacts may result from development of
the Project.
B. Mitigation
1. An erosion/siltation control plan for
project grading shall be submitted to the
California Regional Water Quality Control
Board prior to the commencement of any
constructtun activities.
fik tf i 81 Y --- R F S o i. O -ri a N s8 -,7s7
Echibit for
Resolution No. 88-75
Page 1 of 21
2. The City should continue to make available
the funding sources to pay for needed
drainage system improvements.
3. The project site should be graded to.
maximize drainage efficiently.
4. Buildings and subterranean parking garages
shall be designed to prevent or minimize
flooding potential.
5. The project sponsor shall -submit hydrology
calculations prepared by a Civil Engineer or
Architect prior to approval of the grading
plan.
�. �. . � IST -TTM
This City Council finds that incorporation of the
above mitigation measures into the conditions of
approval for the Project or the Agreement
concerning development of the Project will result
in full mitigation of drainage impacts.
2. Air Quality
A. Zmvact
A short-term construction phase of the
development of the Project will produce two
sources of air pollution emissions: exhaust
emissions during construction, and dust
generation as a result of earth movement and
equipment traffic over temporary roads. The
long-term impacts associated with the proposed
development consist of emissions generated from
stationary and mobile sources. Stationary
sources will include the off-site generation of
electricity and the on-site use of natural gas.
Motor vehicles will comprise the only significant
source of mobile emissions within the project
area.
r •9
1. Regular wetting of soil piles and exposed
dirt areas to minimize dust generation
during excavation and grading.
2. Tarping of trucks hauling dirt away during
excavation when necessitated by soil and
weather conditions, as required by the City.
6766h/2353/08 -2-
Exhibit for
Resolution No. 88-75
Page 2 of 21
C.
6766h/2353/06
3. Discontinuing demolition, excavation and
grading during first and second stage smog
alerts.
The following measures should be considered,
where applicable:
4. orientation of air intakes for building
ventilation away from major traffic areas.
5. Use of separate air intakes for each floor
to minimize the buildup of pollutants
originating either indoors or outdoors.
6. Maximize use of air filters or electrostatic
precipitators in hotel ventilation systems.
Filters should be changed frequently once
the building is in use. Incorporate air
conditioners into retail buildings.
7. Provision of well -ventilated areas for
smoking and zerozing to help prevent the
indoor buildup of related pollutants.
a. Restricting the use of synthetic buildup
materials, such as plastic products
containing vinyl chloride, urea -formaldehyde
foam insulation, and other building
materials containing formaldehyde.
9. Transportation systems management measures,
such as encouragement of alternative means
of travel (i.e., buses, bicycles and
walking) and energy efficient vehicles
(i.e., preferred parking for compact cars,
car pools and motorcycles) would help reduce
vehicle emissions associated with the
proposed project.
10. The implementation of the energy
conservation measures presented in
Section 12 herein will also reduce air
quality impact.
Finding of Significance
This City Council finds that the individual air
quality impacts of this project alone are
potentially insignificant or reduced to a level
of insignificance by implementation of the above
mitigation measures. However, the cumulative air
quality impacts of this Project and other
development in the South Coast Air Basin are
-3-
Echibit for
Resolution No. 88-75
Page 3 of 21
significant and will only be partially mitigated
by implementation of the above measures.
Although the above mitigation measures shall be
required to be implemented in the conditions of
approval or the Agreement concerning development
of the Project, this City Council adopts a
Statement of Overriding Considerations with
regard to the cumulative air quality impact of
this Project (See Statement of Overriding
Considerations below).
3. Oeoloov
A. The project as proposed will require significant
amounts of excavation to accommodate retail uses
and two levels of parking structure below street
grade. Excavation will exceed any fill
requirements of the proposed development and will
require the hauling of excess fill., -Off-site.
Furthermore, proposed site excavation may
encounter high ground water levels.
B.
1. Prior to the issuance of any grading
permits, a detailed geotechnical analysis
shall be prepared and submitted to the City
Engineer for review and approval. Should
dewatering be required for the project, a
study assessing potential impacts of
dewatering on adjacent properties shall be
included in the analysis.
2. If dewatering'is necessary and the discharge
of wastewater to receiving waters is
proposed, an PPDES permit (Waste Discharge
Requirements) must be obtained from the
California Regional Water Quality Control
Board - Santa Ana Region, prior to
initiating the discharge.
3. The proposed haul route(s) shall be
submitted to the Engineering Department for
review and approval.
This City Council finds that implementation of
the above mitigation measures either as
conditions of approval or as inclusions in the
Agreement concerning development of the Project
will reduce the geological impacts of the Project
to a level of insignificance.
6766h/2353/08 -4-
achibit for
Resolution No. 88-75
Page 4 of 21
t '-,s�
l ,-
4. Noise
A. ImRacts
There will be a significant increase in noise and
vibration levels on and adjacent to the
development site during demolition, excavation,
grading and other construction activities. The
long-term noise impacts resulting from the
Project are due to an increase in average daily
trips for traffic in the area. Presently, every
major street in the Project area exceeds 60.dB
CNEL at a distance of 50 feet from the nearest
travel lane. The resulting incremental increase
in average daily trips is not expected to result
in perceptible increases to the human ear in
noise levels over existing conditions and is not
considered significant.
Y • 1
1. The City's Noise Ordinance restricts
construction activities between the hours of
8:00 p.m. and 7:00 a.m. seven days a week.
2. In compliance with the provisions of the
California Code of Regulations, Title 25,
Chapter 1, Sub -chapter 1, Article 4, the
applicant shall submit an acoustical
analysis of the proposed development,
prepared under the supervision of a person
experienced in the field of acoustical
engineering. .Two copies of said report
shall be submitted with the application for
building permits. The acoustical analysis
shall evaluate existing and projected noise
levels, noise attenuation measures to be
applied, and the noise insulation
effectiveness of the proposed construction.
The person preparing the report shall, under
the direction of a person experienced in the
field of acoustical engineering, perform an
inspection of the project to or at the time
of the framing inspection to certify that
construction techniques comply with
recommendations contained within the
acoustical analysis. Upon completion of the
subject structures, field tests may be
required under the provisions of Title 25.
6766h/2353/08 -5-
Exhibit for
Resolution No. 88-75
Page 5 of 21
MINE • } • • • ! 15
1
This City Council finds that the long-term noise
impacts of the.Project are insignificant.
However, short-term construction noise impacts
are significant and cannot be fully mitigated.
Implementation of the above mitigation measures
as conditions of approval or as incorporated in
the Agreement concerning development of the
Project will partially mitigate the short-term
noise impact, but a Statement of Overriding
Considerations has been adopted. (See Statement
of Overriding Considerations below.)
A. Impact
The proposed development will have an incremental
impact on the level of fire service in Costa Mesa
which will result in an increase in medical aid
and other types of responses and will add to the
fire inspection work load.
1. The Project sponsor shall coordinate with
the City Fire Department to ensure adequate
access for fire apparatus is maintained
during construction.
2. An increased demand will be placed on
existing fire, protection capabilities and
the developer will be required to pay an
equitable share of the costs of providing
fire fighting services within a designated
service area, in accordance with a formula
devised by the City.
3. Superior types of building construction may
be required for the larger buildings.
4. Installation of fire protection systems
Including fire sprinklers will be required
In order to tailor fire flow requirements to
water availability.
C. Finding of Sianif cance
This City Council finds that upon implementation
of the above mitigation measures as either
conditions of approval for the Project or as
incorporated in the Agreement concerning
6766h/2353/06 • -6-
Exhibit for
Resolution No. 88-75
Page 6 of 21
development of the Project, that the potential
fire protection impacts of the Project are
reduced to a level of insignificance.
6. Protection
A. Impact
Development of the Project will increase the
intensity of use of the Project site which, in
turn, may be expected to result in an increased
demand for police protection services. The.
proposed subterranean parking structures could
provide an attractive environment for criminal
activity, which would also increase police
service.
B. Mitigation
1. The Project sponsor shall coordinate with
the Police Department during the preliminary
stages of the project design to review
safety features, determine their adequacy,
and suggest improvements.
2. All areas of the development shall be
well -lighted and easy to identify
numerically, in order to facilitate response
by officers.
3. Built-in areas such as alcoves and walkways
should be avoided, and easy access to roof
areas should be discouraged. Emergency
telephone numbers should be easy to locate.
Rooftop identification is encouraged for
aerial patrols.
4. The project shall comply with the
recommendations of the Ralph Anderson and
Associates model for service level impacts
of new development on police services, as
adopted by the City of Costa Mesa and as
applicable to the project.
C. Finding of Significance
This City Council finds that implementation of
the above mitigation measures either as
conditions of approval for the Project or as
Incorporated in the Agreement concerning
development of the Project, will reduce potential
police protection impacts to a level of
insignificance.
6766h/2353/08 -7-
Exhibit for
Resolution No. 88-75
Page 7 of 21
7. solid Waste
A. The Project as proposed will increase solid waste
generation at the Project site as well as adding
to the incremental increase of solid waste
generated in the Downtown Redevelopment Area.
y LTTZ • +
1. A recycling collection program for reusable
items such as paper, aluminum, and glass
shall be implemented.
+• +• •+ 14+
This City Council finds that implementation of
the above mitigation measure as a condition of
approval for the Project or as incorporated in
the Agreement concerning development of the
Project will mitigate the solid waste generation
impact of the Project to a level of
insignificance.
S. Traffic/Circulation Imvact
To assess the potential impacts of the Project on the
circulation system, a traffic impact analysis was
prepared by Weston Pringle and Associates. Under
"worst case" conditions, the proposed Project is
expected to generate 11,750 daily trips of which 1,005
(550 in, 455 out) will occur during the PM peak hour.
Until such time as the Costa Mesa Freeway is complete,
Newport Boulevard will continue to carry traffic
volumes in excess of its design capacity.
Implementation of the Project will incrementally
increase the traffic volumes on the links of Newport
Boulevard. However, all affected intersections are
expected to maintain acceptable (LOS D or better)
operations.
KNEEF"MM-141MOVITY-31
1. Provide a southbound right -turn lane on
Newport Boulevard at the project access at
Broadway.
2. Improve turning radius from southwest bound
Newport Boulevard to northbound Harbor
Boulevard.
3. Eliminate on -street parking on Harbor
Boulevard.
6766h/2353/08 I -8-
Exhibit for
Resolution No. 88-75
Page 8 of 21
4. Restrict project access/egress on 19th
Street to right -turn in and right -turn out
only.
5. Seven (7) feet back of curb shall be
dedicated and constructed for public
sidewalk around the entire project site.
6. Should any work be necessary in the State
right-of-way, the developer shall submit
plans to and obtain an encroachment permit
from Cal Trans.
7. The proposed development shall assist in
implementation of planned highways by
dedicating or reserving necessary
rights-of-way.
8. Driveways will utilize a curb return or
widened flare design and sufficient exit
lanes to accommodate traffic volumes. At
the 19th Street right turn only access, only
one outbound lane will be permitted.
9. Streetscape plans will allow for bus
shelters, bus turnouts, bike racks,
pedestrian facilities and other amenities to
encourage transit usage, bicycling and
walking.
10. Adequate turning areas shall be designed to
accommodate trash trucks, delivery trucks,
and fire engines.
11. The City Traffic Engineer will review and
approve proposed haul routes and schedules
for excavated soil. If trucks entering and
leaving the site cause significant traffic
congestion, the City Traffic Engineer will
require a change in procedures to correct
the problem.
12. Precise plans for parking, internal site
access and internal circulation will be
analyzed by the City Staff and reviewed at
public meetings prior to approval of the
site plans.
13. The City of Costa Mesa shall continue to
coordinate with the County of Orange to
achieve consistency between the City and
County Master Plan of Bikeways.
14. The applicant shall participate on a
pro -rata basis in the funding of the
following intersection improvements to (a)
6766h/2353/08 -9-
Exhibit for
Resolution No. 88-75
Page 9 of 21
Newport Boulevard/18th Street/Rochester
Street, (b) Newport Boulevard/17th Street,
and (c) 17th Street/Superior Avenue/Anaheim
Avenue. The required fee shall be paid
prior to the issuance of certificates of
occupancy.
a. Newport Boulevard/18th Street/Rochester
Street: provide signal modification
for protected left -turn phasing and
dual left -turn for the eastbound to
northbound movement; and restripe.both
the east and west lanes of the
intersection.
b. Newport Boulevard/17th Street: Provide
a southbound right -turn -only pocket and
southbound right -turn overlap signal
phase with five (5) section vehicle
detection.
C. 17th Street/Superior Avenue/Anaheim
Avenue: widen the west leg and
restripe to provide two (2) eastbound
through lanes and restripe the east leg
to provide eastbound left -turn storage;
prohibit right turns on red for
northbound traffic.
F4RMMMFJVMTV .;
This the City Council finds that upon
implementation of the above mitigation measures
either as conditions of approval or by
incorporation in the Agreement concerning
development of the Project, that no significant
adverse impacts will result to intersection
operations or traffic circulation in the Project
area. However, implementation of the above
mitigation measures will only partially mitigate
the incremental impact of additional vehicular
trips on Newport Boulevard. Because the impact
on Newport Boulevard remains significant, a
Statement of Overriding Considerations has been
adopted by this City Council. (See Statement of
Overriding Considerations below.)
9. Land Use
A. Impact
The proposed Project will require the demolition
of 35,000 square feet of existing retail uses to
accommodate approximately 202,576 square feet of
6766h/2353/08 I -10-
Exhibit for
Resolution No. 88-75
Page 10 of 21
retail, theaters and restaurant uses. This
proposed development is similar to the project
analyzed in the earlier EIR, although reduced in
scale and intensity. The Project has an estimate
floor area ratio of 1.04 versus 1.74 for the
previous project. The Project will require a
zone change from C2 to PDC (Plan Development
Commercial).
H. Mitigation
1. The project shall blend with the
architectural trends being established by
other recent redevelopment projects in the
area, such as the Pacific Federal Plaza and
the Costa Mesa Courtyards. It shall also
comply with the requirements of the Planned
Development Commercial District and the
Redevelopment Plan and General Plan.
2. When possible, existing viable businesses in
the project area should be provided with
retail or office space in the finished
project buildings. If this is not possible,
all existing businesses must be relocated by
the Redevelopment Agency according to State
Law and the Agency's Relocation Plan for the
Downtown Redevelopment Project. (See
Section 11)
3. The Orange County Vector Control District
should be notified at least two weeks prior
to demolition or grading on any structures
that may have'the potential to harbor
rodents. This will allow the District
sufficient time to inspect or place
rodenticide bait prior to demolition and
thus reduce the potential for rodent
dispersal. The project site should be
graded for proper runoff to avoid standing
water that could breed mosquitoes. Also,
trash should be placed in fly -proof
containers and emptied weekly or preferably
bi-weekly.
4. During the landscape phase of the project,
plants that are attractive to rodents, such
as Algerian ivy, oleander, palm trees,
yuccas, bougainvillea, etc. should be
avoided. A list of alternative types of
ground cover less attractive to rodents is
provided in Appendix E of the earlier EIR.
6766h/2353/06 ' -11-
Exhibit for
Resolution No. 88-75
Page 11 of 21
This City Council finds that upon implementation
of the above mitigation measures as conditions of
approval for the Project or as incorporated into
the Agreement concerning development of the
Project, that the land use impacts of the Project
are mitigated to a level of insignificance.
The preliminary design plans for the Project
indicate an average building height of 35 feet
with architectural features (i.e., cupola/towers)
that reach 70 feet. The earlier EIR assessed the
potential impacts of a 68 foot high hotel located
adjacent to Newport Boulevard. The shadows from
that structure were contained primarily on-site
and were not expected to extend across 19th
Street. No impacts were anticipated on solar
access for energy production or for solar space
and water heating for off-site structures.
1. A shade/shadow analysis shall be prepared
prior to project approval to ensure that
project building heights do not adversely
impact surrounding land uses.
2. The project site design should provide
pedestrian amenities that take advantage of
both summer shade and winter sunlight.
�WiVt7-tTtT-W-3M3. } + -
A.
6766h/2353/08
This City Council finds that upon implementation
of the above mitigation measures as conditions of
approval for the Project or as incorporated into
the Agreement concerning development of the
Project, that no significant shade or shadow
Impacts will result.
•}
Whereas the project
estimated generation
employees and 93 new
analyzed in the earlier EIR
of a demand for 699 new
housing units, the Project
-12-
Exhibit for
Resolution No. 88-75
Page 12 of 21
a
tom% i.� •.�
as proposed will only generate a demand for 450
employees and 60 new housing units. Although the
Project creates fewer employment opportunities
and associated housing demands than the previous
project, a substantial increase over existing
conditions does result from implementation of the
Project. The project implementation may also
require displacement and relocation of businesses
existing on the Project site.
y • /
1. In accordance with the Redevelopment Pian
for the Downtown Redevelopment Project,
existing businesses and industry within the
project area will be given preference to
participate in the redevelopment project
through development of existing or acquired
properties or as business tenants.
Relocation advisory assistance for any
business will be made available through the
City of Costa Mesa. In the event that it
becomes necessary to relocate a business,
and the business cannot be relocated without
a substantial loss of patronage, and the
business is not part of a commercial
enterprise having at least one other
establishment engaged in the same or similar
business, the Redevelopment Agency is
authorized to pay to such a business a
relocation payment as provided in Section
7262 of the Government Code. The Agency is
also authorized to pay the actual and
reasonable moving expenses of a business as
required by State law, if the business is
required to relocate as a result of the
implementation of the Redevelopment Plan.
2. The Costa Mesa Redevelopment Advance
Briefing Report recommends that 60-70
percent of the 200 -acre Downtown
Redevelopment Area be put to residential
use. The intensification of residential
uses in the area would result in an
integrated mixed-use complex and would serve
to meet the demand for housing generated by
future employees of new commercial
development. In addition, the development
of new affordable housing should be
encouraged by the Redevelopment Agency.
6766h/2353/08 1 -13-
Exhibit for
Resolution No. 88-75
Page 13 of 21
,. ,. ., itis,
The resulting impact on employment and housing
demand from the Project is fully mitigated by
implementation of the above measures as
conditions of approval or as incorporated in the
Agreement concerning development of the Project.
However, the impact to existing businesses of
displacement and relocation is only partially
mitigated and remains significant. Therefore,
this City Council adopts a Statement of
Overriding Considerations for this impact. .(See
Statement of Overriding Considerations below.)
12. Energy/Utilities
A. Smvact
Implementation of the Project results in impacts
on energy, water supply, and sewer services. The
Project as proposed will consume 7.05 million
cubic feet of natural gas and 9.58 million
kilowatt hours of electricity each year. The
Project's daily water consumption will be
approximately 67,500 gallons per day and the
Project will generate approximately 30,386
gallons per day of sewage.
y • }
Site Planning and Street Design
1. Utility companies should utilize the same
trenches as much as possible when relocating
and/or upgrading their respective facilities
in the Project area, in order to minimize
the use of diesel fuel during this phase of
Project construction.
2. Bicycle racks shall be provided close to the
proposed buildings.
3. If active solar heating systems are
incorporated into the design of proposed
buildings, site planning must ensure that
incoming solar radiation is unobstructed.
4. Provision of pedestrian amenities (e.g.,
attractively landscaped walkways, street
furniture, etc.) would encourage greater
pedestrian activity, as an alternative to
driving.
6766h/2353/08 ; -14-
Exhibit for
Resolution No. 88-75
Page 14 of 21
5. Appropriate and well-placed landscaping can
be used to moderate temperature. For
example, deciduous trees located on south
and west exposures provide shade during
summer, yet allow light and heat to enter
during the winter months.
Building Design
1. All buildings constructed in the Project
area shall comply with the Energy
Conservation Standards set forth in Title 24
of the California Code of Regulations.
2. Orientation of the largest surface area and
the major openings of buildings toward the
south will maximize solar exposure and
natural heat gain during the winter months
and minimize heat gain during.the summer.
3. Walls,'ceilings, floors, windows and hot
water lines shall be insulated to prevent
heat loss or gain.
4. Active solar energy systems shall be
considered for use in heating of water.
This could achieve a 50-60 percent reduction
in energy consumption for water heating.
Recent studies have indicated the
cost-effectiveness (i.e., amortization of
initial cost) of the use of solar energy for
these purposes.
5. Energy efficient lighting (e.g., high
pressure sodium outdoors and fluorescent
indoors) shall be used rather than less
efficient types of lighting. Maximum use of
natural lighting opportunities shall be made
during daylight hours.
6. Nonessential, ornamental lighting shall be
avoided.
7. The Southern California Edison and Southern
California Gas Companies have "Energy
Management Programs" which provide
assistance in selecting the most effective
application of energy conservation
techniques, which could be incorporated into
Project design during the preliminary
planning stages of development. These
energy saving alternatives are readily
6766h/2353/06 -15-
Exhibit for
Resolution No. 88-75
Page 15 of 21
6766h/2353/08
available, easier
construction, and
long-term costs.
to install during
will not necessarily raise
1. New water mains sufficient to serve the
proposed site development as identified by
the Mesa Consolidated Water District shall
be constructed at the developer's expense.
2. The Mesa Consolidated Water District (the
local water purveyor) has appointed a task
force whose aim is to promote water
conservation and to reduce the demand for
potable water thereby offsetting the impacts
caused by the loss of Northern California
water. A detailed water analysis for the
project and its landscaping shall be
submitted to MCWD for review and approval
prior to submittal of construction plans to
the City. Landscape plans shall also be
submitted to MCWD prior to their approval by
the City.
3. The project shall use reclaimed water for
landscape/irrigation purposes when it
becomes available.
4. The following water conservation measures
shall be added:
(a) Low -flush toilets (Section 17921.3 of
the Health and Safety Code);
(b) Low -flow faucets (California Code of
Regulations, Title 24, Part 6, Article
1, T20 -1406F);
(c) Hot water lines will be insulated in
water recirculating systems (California
Energy Commission regulations);
(d) Supply -line water pressure will be
maintained at 50 pounds per square inch
or less by means of pressure -reducing
valves;
(e) Flush valve operated water closets (3
gallons per flush) shall be included;
-16-
Exhibit for
Resolution No. 88-75
Page 16 of 21
p
(f) Drinking fountains will be equipped
with self-closing valves;
(g) Hot water lines will be insulated to
provide hot water faster with less
water waste, and hot lines will be
separated from cold lines;
(h) Restaurants will use water conserving
dishwasher models or retrofit
dishwasher spray emitters;
(i) Restaurants will serve drinking water
upon request only;
(j) Conservation reminders will be posted
in restrooms;
(k) Thermostatically controlled mixing
valves will be used for bath/showers.
(1) Water conserving models of washers will
be used in laundry facilities.
5. The following water conservation measures
for landscape/irrigation purposes shall be
instituted:
(a) Drought -resistant planting materials
will be used for landscaping where
possible. The project's landscape plan
will be approved by the Planning
Division prior to the issuance of
building permits;
(b) The use of lawn will be minimized;
(c) Mulch will be applied extensively to
all landscaped areas;
(d) Efficient Irrigation systems which
minimize runoff and evaporation will be
installed;
(e) Previous paving materials will be used
wherever feasible to reduce surface
water runoff and facilitate ground
water recharge.
6766h/2353/08 -17-
Exhibit for
Resolution No. 88-75
Page 17 of 21
f) r--
"k Z!
Sewer
1. Development of the project site shall
require developer participation in the
cost of increasing sewer capacity
through the payment of fees and/or
upgrading off-site sewer lines. Any
off-site sewer facilities constructed
by the project sponsor shall be
dedicated to the Costa Mesa Sanitary
District.
2. The Costa Mesa Sanitary District will
charge the project developer a
connection fee based on a set fee
schedule.
C. Finding of Significance
The City Council finds that upon
implementation of the above mitigation
measures as conditions of approval for the
Project or as incorporated into the
Agreement which concerns development of the
Project, that the impacts of the Project on
energy, water supply and sewer services are
reduced to a level of insignificance.
13. Natural Resources
A. ImRact
Development of the Project will commit prime
agricultural soil for commercial and retail
development, and will commit building materials
to the construction of the Project. Energy
resources will be committed for short-term
construction activities and the long-term
operation of the proposed uses.
1. The energy conservation measures presented
in Section 12 will reduce both short-term
and long-term impacts on energy resources.
2. Demolition waste from project construction
activities shall be recycled, where feasible.
C. Finding of Significance
The City Council finds that upon implementation
of the above mitigation measures as conditions of
approval for the Project or as incorporated into
the Agreement which concerns development of the
6766h/2353/08 . -18-
Exhibit for
Resolution No. 88-75
Page 18 of 21
Project, that the
natural resources
insignificance.
13. Other Impacts
impacts of the Project on
are reduced to a level of
Based on the Initial Study and earlier EIR and the
Record before the City Council, this City Council
finds that implementation of the Project results in no
other significant adverse environmental impacts.
This City Council has considered each of the alternatives
presented in the earlier EIR and finds those alternatives
infeasible based on economic, social and other considerations
as set forth below.
The No Project Alternative would result in the Project
site remaining in an as -is condition, and would not
accomplish the goals and objectives of the
Redevelopment Plan. Adoption of the No Project
Alternative would serve only to delay the potential
adverse impacts associated with development of the
Project site (increased traffic, noise, air pollution
and natural resource/energy consumption). If private
development of the project site does not occur in the
near future, adoption of the No Project Alternative
would result in a direct loss of revenue to the
Redevelopment Agency as well as a potential indirect
loss since the values of.surrounding redevelopment
properties would be adversely affected. Uncertainty
In development of the site could make it more
difficult to generate developer interest in
redevelopment of the surrounding area. Accordingly,
this City Council finds the No Project Alternative
infeasible.
- MT XTT:M%T
Alternative No. 1 proposes a less intense development
of the Project site and surrounding area. Under
Alternative No. 1, a total of 166,500 square feet of
retail and office space is proposed over approximately
19.5 acres, with 81,000 square feet located on the 4.5
acre Project site. Buildings to be constructed under
Alternative No. 1 would be one or two stories high,
thus rendering shadow impacts negligible. Alternative
No. 1 would generate a need for employees and housing
6766h/2353/08 � -19-
Exhibit for
Resolution No. 88-75
Page 19 of 21
similar to the proposed Project. Because development
under Alternative No. 1 is spread over approximately
19.5 acres rather than consolidated on 4.5 acres, -it
is not an economically feasible project to develop.
Therefore, Alternative No. 1 is rejected by this City
Council as infeasible.
Alternative No. 2 consists of a total development of
421,000 square feet over approximately 19.5 acres,
including development of a 350 room hotel on the.
Project site consisting of 185,000 square feet.
Alternative.No. 3 consists of a total development of
545,000 square feet over approximately 19.5 acres
including development of retail and office space
consisting of 290,000 square feet on the 4.5 acre
project site. These alternatives result in a more
Intense use of the Project site and surrounding area
and correspondingly result in greater significant
adverse impacts than those which result from the
Project as proposed. Therefore, this City Council
rejects Alternatives Nos. 2 and 3 as infeasible.
4. Alternative NQ_,_A
Alternative No. 4 proposes a mixed-use development of
the 4.5 acre project site including a 150 room hotel,
150 residential units and retail and restaurant uses
totalling 115,000 square feet. The introduction of
residential housing on the Project site results in
impacts over and above those caused by retail and
commercial development alone. Therefore, this City
Council rejects Alternative No. 4 as infeasible.
Based on information set forth in the earlier EIR, the
Initial Study, and these Findings of Fact, this City Council
finds that the adverse environmental impacts related to air
quality, short-term construction noise, increased traffic on
Newport Boulevard, and the potential displacement of businesses
located on the Project site are significant environmental
impacts which cannot be entirely mitigated or avoided if the
Project is implemented.
However these unavoidable significant effects of the
Project are overridden by the benefits of the Project as
described below. Therefore, this City Council hereby approves
and adopts this Statement Of Overriding Considerations.
1. The proposed Project site is located in the Costa Mesa
Downtown Redevelopment Project Area and implements the
adopted Redevelopment Plan for said Project Area.
6766h/2353/08 . -20-
Exhibit for
Resolution No. 88-75
Page 20 of 21
2. The proposed Project will provide for a more efficient
use of land through integration of uses and structures
in a single development, and by removal of obsolete
development and subdivision patterns which now exist
on the site.
3. The proposed Project is consistent with the Commercial
Center General Plan designation and the Commercial
Redevelopment Plan designation for the site.
4. The proposed Project is an adopted policy of the
General Plan and a stated objective of the
Comprehensive Design Plan for the Redevelopment
Project Area.
S. The proposed Project permits a more efficient use of
land through shared parking for all uses.
6. The proposed Project will introduce an activity center
in the core of the Redevelopment Project Area, which
will be a significant enhancement of the overall
vitality and success of redevelopment efforts downtown.
7. The location of employment and shopping opportunities
downtown will have beneficial impacts on traffic.
8. The proposed Project implements the City's goal to
provide its citizens with a balanced community of
residential, commercial, industrial, recreational and
institutional uses to satisfy the needs of the social
and economic segments of the population; to meet the
competing demands for alternative developments within
each land use classification; and, to ensure the
long-term viability and ;productivity of the
community's natural and man-made environments.
6766h/2353/08 -21-
Exhibit for
Resolution No. 88-75
Page 21 of 21