HomeMy WebLinkAbout07 - CC-6 - Presentation - 10/15/2019PINKLEY PARK
PLAYGROUND
RENOVATION
PROJECT
OCTOBER 15, 2019
v v
2PINKLEY PARK PLAYGROUND RENOVATION
PROJECT
PROJECT SUMMARY
•Contractor: Playcore Wisconsin, Inc., dba Game Time
•Contract Awarded: February 4, 2019
•Scope of Work: Removal of the old playground equipment at Pinkley Park and
installation of new playground equipment and surfacing
•Work Completed: May 24, 2019
v v
3PINKLEY PARK PLAYGROUND RENOVATION
PROJECT
PROJECT FUNDING SUMMARY
•Original Contract Amount: $92,237.69
•Final Contract Cost: $92,237.69
•Funding: Capital Improvement Fund approved in Fiscal Year 2018-19
4
PINKLEY PARK PLAYGROUND RENOVATION
PROJECT
BEFORE AFTER