HomeMy WebLinkAbout06 - CC-6 - Pinkley Park Playground Renovation Proj - 10/15/2019 CITY COUNCIL AGENDA REPORT MEETING DATE: OCTOBER 15, 2019 ITEM NUMBER: CC-6 SUBJECT: PINKLEY PARK PLAYGROUND RENOVATION PROJECT DATE: OCTOBER 9, 2019 FROM: PUBLIC SERVICES DEPARTMENT / ENGINEERING DIVISION PRESENTATION BY: RAJA SETHURAMAN, PUBLIC SERVICES DIRECTOR FOR FURTHER INFORMATION CONTACT: BALTAZAR MEJIA, CITY ENGINEER (714) 754-5335 RECOMMENDATION: Staff recommends that the City Council: 1. Accept the work performed by Playcore Wisconsin, Inc., dba Game Time, for the Pinkley Park Playground Renovation project and authorize the City Clerk to file the Notice of Completion. 2. Authorize City Manager to release the Labor and Material Bond one year after the filing date and to release the Faithful Performance Bond at the conclusion of the one-year warranty period. BACKGROUND: On February 4, 2019, the City awarded a construction contract in the amount of $92,237.69 to Playcore Wisconsin, Inc., dba Game Time, 150 Playcore Drive SE, Fort Payne, AL 35967. The scope of work for this project included the removal of the old playground equipment at Pinkley Park and the installation of new playground equipment and surfacing. Before Construction After Construction 2 ANALYSIS: The work required by the contract documents was completed on May 24, 2019, to the satisfaction of the City Engineer. A summary of the costs is as follows: Original Contract Cost: $ 92,237.69 Change Orders: $0 Final Contract Cost: $ 92,237.69 As of this date, there are no Stop Notices filed against the monies due to Playcore Wisconsin Inc., dba Game Time. ALTERNATIVES CONSIDERED: There are no alternatives considered for this item. FISCAL REVIEW: The Pinkley Park – Remove and Replace Playground Equipment project was included in the Fiscal Year 2018-19 Adopted Capital Improvement Program (CIP) with a total approved budget of $130,000 in the Capital Improvement Fund. The original and final contract amount for this project was $92,237.69, leaving a remaining unspent budget balance of $37,762.31. As part of the FY 2019-20 budget adoption, the City Council approved reducing the project budget by $32,000. Based on the final contract cost, this project was completed under budget, and the remaining unencumbered project balance of $5,762.31 will be returned to the unassigned fund balance in the Capital Improvements Fund. LEGAL REVIEW: The City Attorney’s Office has reviewed and approved this report as to form. CITY COUNCIL GOALS & PRIORITIES: In 2019, the City Council adopted a list of goals and priorities. This project works toward achieving the following City Council goals and objectives: Goal 2: Improve our Neighborhoods and Quality of Life: (a) Improve, expand, and add to our neighborhood parks. CONCLUSION: The installation of the playground equipment at Pinkley Park is completed to the satisfaction of the City Engineer. It is recommended that the City Council accept the work; authorize the City Clerk to file the Notice of Completion and authorize the City Manager to release the bonds at the conclusion of the warranty period. 3 _________________________________ _________________________________ BALTAZAR MEJIA RAJA SETHURAMAN City Engineer Public Services Director ________________________________ _________________________________ KELLY A. TELFORD, CPA KIMBERLY HALL BARLOW Director of Finance City Attorney