DEVELOPMENT IMPACT FEE ANNUAL REPORT
The City of Costa Mesa has adopted four types of development impact fees that it
imposes on development projects: Park Development Fees, Drainage Impact Fees,
Traffic Impact Fees and Fire System Development Fees. Pursuant to the Mitigation Fee
Act, as provided in Section 66006 of the California Government Code, the City is required
to make available for public review a summary of its development impact fees.
Type of Development Impact Fees
The City imposes the following four development impact fees:
1.Park Development Impact Fees (Quimby Act Fees): This fee provides funding for
additional or improved park and/or recreation facility improvements for which the
need is generated by new development within the City.
2.Drainage Impact Fees: This fee provides funding for additional construction and
maintenance of the City’s drainage system for which the need is generated by new
development or redevelopment within the City.
3.Traffic Impact Fees: This fee provides funding for additional or improved traffic
signal, operation, and infrastructure improvements for which the need is generated
by new or expanding development within the City.
4.Fire System Development Fees: This fee provides funding for additional fire
protection facilities and equipment for which the need is generated by future
development within the North Costa Mesa area. This fee is only levied against five
identified developments: Home Ranch, South Coast Plaza Town Center, South
Coast Metro Center, and Sakioka Farms’ Lots 1 and 2.
Amount of Fees
The amounts of development impact fees are described below:
1.Park Development Fees (Quimby Act Fees): The table below indicates the
applicable park development fee per unit that will be applied to new residential
projects based on the net increase in residential units.
Development Type Fee per Unit
Single-family Dwelling Unit $13,572.00
Multi-family Dwelling Unit $13,829.00
Apartment Dwelling Unit $5,000.00
ATTACHMENT 1
2. Drainage Fees: The table below indicates the applicable drainage impact fee per
acre that will be applied to new or redeveloped projects.
Development Type Fee per Acre
Low Density Residential Use $3,141.50
Medium Density Residential Use $3,769.50
High Density Residential Use $5,026.00
Commercial / Industrial Use $5,654.50
3. Traffic Impact Fees: The citywide Traffic Impact Fee is assessed on the increased
number of average daily trips generated by the proposed project. The fee was
$181 per daily trip from November 21, 2017 to November 13, 2018 and increased
to $235 per daily trip beginning November 14, 2018.
4. Fire System Development Fees: The fee is $0.285 per square foot of new
commercial, industrial or residential development.
Summary of Development Impact Fee Activities Including Fees Collected, Interest
Earned and Beginning and Ending Fund Balances
A summary of activities in each type of development impact fee for fiscal year ended June
30, 2019 is described below:
Park
Development
Fees
Drainage Fees Traffic Impact
Fees
Fire System
Protection Fees
Revenues
Fees 2,299,373$ 268,800$ 182,166$ -$
Investment Earnings 254,347 57,202 177,173 5,865
Revenue Subtotal 2,553,720 326,002 359,339 5,865
Expenditures 1,909,263 56,979 67,090 -
Transfers in/(out)(3,842) - - -
Change in Fund Balance 640,615 269,023 292,249 5,865
Beginning Fund Balance 5,199,671 1,202,490 4,259,249 150,981
Ending Fund Balance 5,840,286$ 1,471,513$ 4,551,498$ 156,846$
Summary of Development Impact Fees for Fiscal Year Ended June 30, 2019
Expenditures
State law requires an identification of each public improvement on which fees were
expended and the amount of expenditures on each improvement, including the total
percentage of the costs of the public improvement that was funded with fees. A summary
of improvements is provided below:
Construction Commencement Date for Incomplete Improvements
Not applicable at this time.
Interfund Transfers and Loans
The Park Development Fees Fund transferred $3,842 to the Capital Improvements Fund
for Fairview Park Vernal Pool Watershed Restoration project.
Amount of Refunds
No refunds of any of these funds were made or required in fiscal year 2018-19.
Improvement Fee Used
Amount of Fees
Expended
% of Cost
Funded by Fees
Fairview Park Bluffs Park Development Fees 151,406 100%
Fairview Park Improvements Park Development Fees 198,810 100%
Fairview Park Master Plan Habitat Restoration Park Development Fees 54,854 100%
Jack Hammett Field Upgrade Park Development Fees 63,634 100%
Neighborhood Community Center - Library
Development Park Development Fees 1,430,824 100%
Citywide Storm Drain Improvements Drainage Fees 56,979 100%
Hyland/MacArthur Intersection Improvements Traffic Impact Fees 58,148 100%
West 17th Street Design Newport Westside Traffic Impact Fees 5,842 100%
Newport Boulevard Widen 19th to 17th Street Traffic Impact Fees 3,100 100%
Expenditures by Improvements for Fiscal Year 2018-19
CITY COUNCIL AGENDA REPORT
MEETING DATE: DECEMBER 17, 2019 ITEM NUMBER: CC-6
SUBJECT: DEVELOPMENT IMPACT FEES ANNUAL REPORT FOR THE FISCAL
YEAR ENDED JUNE 30, 2019
DATE: NOVEMBER 25, 2019
FROM: FINANCE DEPARTMENT/ADMINISTRATION DIVISION
PRESENTATION
BY:
KELLY A. TELFORD, CPA, FINANCE DIRECTOR
FOR FURTHER INFORMATION
CONTACT:
JENNIFER KING, ASSISTANT FINANCE
DIRECTOR, AT (714) 754-5219
RECOMMENDATION:
Staff recommends that the City Council receive and file the Development Impact Fees
Annual Report for the Fiscal Year ended June 30, 2019.
BACKGROUND:
Pursuant to Section 66006 of the California Government Code, local agencies are
authorized to condition approval of development projects on the payment of
development impact fees for the purpose of defraying all or a portion of the cost of
public facilities related to the development project. The Mitigation Fee Act, as provided
in Section 66006 of the California Government Code, regulates the means by which
public agencies collect, maintain, and spend development impact fees imposed on
development projects. The regulations include specific requirements pertaining to
governmental accounting, spending, and annual reporting of development impact fees.
Each year, within the first 180 days following the previous fiscal year, the City is
required to make available to the public an annual report of each mitigation fee account.
This annual report must include the following:
1) A brief description of the type of fee in the account or fund;
2) The amount of the fee;
3) The beginning and ending balance of the account or fund;
4) The amount of the fees collected and interest earned;
2
5) Identification of each public improvement on which fees were expended and the
total amount of the expenditures on each improvement, including the total
percentage of the cost of the public improvement that was funded with fees;
6) An identification of an approximate date by which the construction of the public
improvements will commence if the local agency determines that sufficient funds
have been collected to complete financing on an incomplete public improvement,
and the public improvement remains incomplete;
7) A description of each interfund transfer or loan made from the account or fund,
including the public improvement on which the transferred or loaned fees will be
expended, and, in the case of an interfund loan, the date on which the loan will
be repaid, and the rate of interest that the account or fund will receive on the
loan; and
8) The amount of any refunds made pursuant to Section 66001(e) and the amount
of any allocations pursuant to Section 66001(f).
Moreover, after a 15-day public review period, the City is required to review the Annual
Report at the next regularly scheduled public meeting. This report was filed with the
City Clerk’s Office and available for public review on December 2, 2019.
ANALYSIS:
The attached Development Impact Fees Annual Report provides a detailed summary of
the City’s development impact fees for the fiscal year ended June 30, 2019. The City of
Costa Mesa has adopted four (4) types of development impact fees, including Park
Development Impact Fees, Drainage Impact Fees, Traffic Impact Fees, and Fire System
Development Fees. A brief summary of the fees are referenced herein:
1) Park Development Impact Fees: provide funding for additional or improved park
and/or recreation facility improvements for which the need is generated by new
development within the City.
2) Drainage Impact Fees: provide funding for additional construction and maintenance
of the City’s drainage system for which the need is generated by new development
or redevelopment in the City.
3) Traffic Impact Fees: provide funding for additional or improved traffic signal,
operation, and infrastructure improvements for which the need is generated by new
or expanding development within the City.
4) Fire System Development Fees: provide funding for additional fire protection
facilities and equipment for which the need is generated by future development
within the North Costa Mesa area.
3
In accordance with Section 66008 of the Mitigation Fee Act, these fees must be expended
for public improvements solely and exclusively for the purpose for which it is collected and
cannot be levied, collected or imposed for general revenue purposes. These fees have
been collectively spent on the projects below with a more detailed breakdown referenced
in Attachment 1:
1) Citywide Storm Drain
Improvements
2) Fairview Park Bluffs
3) Fairview Park Improvements
4) Fairview Park Master Plan Habitat
Restoration
5) Hyland/MacArthur Intersection
Improvements
6) Jack Hammett Field Upgrade
7) Lions Park Campus Improvements
8) Newport Boulevard
Improvements, 17th to 19th Street
9) West 17th Street Design, Newport
Staff recommends that the City Council receive and file this Annual Report.
ALTERNATIVES CONSIDERED:
The City Council may choose to reject all or part of the Annual Report as presented.
California Government Code Section 66006 requires that the report be reviewed at a
public meeting.
FISCAL REVIEW:
There is no fiscal impact by the recommended action as this report is not requesting that
City Council adopt new development impact fees, but is reporting development impact fee
activity for the Fiscal Year ended June 30, 2019.
LEGAL REVIEW:
The City Attorney’s Office has reviewed and approved this agenda report.
CITY COUNCIL GOALS & PRIORITIES:
This item is administrative in nature.
CONCLUSION:
Staff recommends that the City Council receive and file the Development Impact Fees
Annual Report for the Fiscal Year ended June 30, 2019.
4
_________________________________ _________________________________
AMBER HASTON JENNIFER KING
Management Analyst Assistant Finance Director
_________________________________ _________________________________
KELLY A. TELFORD, CPA KIMBERLY HALL BARLOW
Finance Director City Attorney
Attachments: 1. Development Impact Fee Annual Report for Fiscal Year Ended
June 30, 2019.