HomeMy WebLinkAbout05 - CC-7 - City Proj. 11-03 Energy Efficient Chille - 6/7/2011CITY COUNCIL AGENDA REPORT MEETING DATE: JUNE 7, 2011 ITEM NUMBER: SUBJECT: AMERICAN RECOVERY AND REINVESTMENT ACT — ENERGY EFFICIENT CHILLER COMPRESSOR REPLACEMENT — CITY HALL & POLICE FACILITY - CITY PROJECT - NO. 11-03 DATE: MAY 26, 2011 FROM: PUBLIC SERVICES DEPARTMENT/ENGINEERING DIVISION PRESENTATION BY: PETER NAGHAVI, DIRECTOR, DEPARTMENT OF PUBLIC SERVICES FOR FURTHER INFORMATION CONTACT: ERNESTO MUNOZ, CITY ENGINEER AT (714) 754-5335 RECOMMENDATION: Adopt plans, specifications, and working details for the American Recovery and Reinvestment Act — Energy Efficient Chiller Compressor Replacement at City Hall and Police Facility, City Project No. 11-03. 2. Award a construction contract to Liberty Climate Control, Inc., 2447 N. Chico Avenue, South EI Monte, California 91733 in the amount of $545,600.00. 3. Authorize the Mayor and City Clerk to execute the Public Works Agreement for this project. BACKGROUND: The chiller compressors at City Hall and the Police Facility are currently exhibiting advanced deterioration and wear. The design and age of these components result in the City utilizing very high rates of energy to run the air conditioning systems in these two facilities. The replacement of the chiller compressors was identified as an energy conservation opportunity in an energy audit report prepared for the California Energy Commission. Replacing this equipment will yield significant savings in energy costs due to the higher efficiency of the more technologically advanced equipment. In March of 2009, the Federal Government announced plans to invest $3.2 billion in energy efficiency and conservation projects. The Energy Efficiency and Conservation Block Grant (EECBG) program was funded by the American Recovery and Reinvestment Act. The grant provides funding for projects that reduce total energy use and fossil fuel emissions, and improve energy efficiency nationwide. Staff successfully applied and received funding from the American Recovery and Reinvestment Act. The City of Costa Mesa's grant allocation amounts to $1,123,500 for eligible energy-saving projects. City staff has previously administered the replacement of the Corporation Yard and the City Hall roofs with energy efficient "cool roofs" under this grant funding. In addition to these projects, the City Council directed staff to include the replacement of the chiller compressors at the City Hall and Police Facility for funding under this program. ANALYSIS: On April 25, 2011, the City Clerk received and opened one bid for this project. Liberty Climate Control, Inc. was the apparent low bidder with a bid proposal of $545,600. The engineer's estimate for this work was $500,000.00 (see Attachment 1). Staff's review of the single bid finds that the bid amount exceeds the engineer's estimate by 9%. This is likely due to the unique nature of the equipment to be furnished for this project. There are very few contractors within this trade that hold the specialty certification required to install the specified equipment or have the bonding capacity to bid on public works projects of this magnitude. Since the competition from other bidders was limited with the current scope of work, it is anticipated that re -advertising a revised project will not result in lower bids. ALTERNATIVES CONSIDERED: The alternative to this Council action would be to reject the bid. If the bid is rejected, the City would need to readvertise or cancel the project. Staff believes that readvertising the project will not result in lower bids. Furthermore, the deadline for the obligation of funds under this grant is July 13, 2011. Re -advertising this project would result in the City missing this deadline and losing the grant funding. Therefore, this alternative is not recommended. FISCAL REVIEW: Funding for this project in the amount of $578,000 is available from the EECBG program funds, which provide for 100 percent reimbursement of the construction costs. LEGAL REVIEW: Liberty Climate Control, Inc. will furnish the necessary bonds and insurance prior to the commencement of work, scheduled for August 2011, subject to approval by the City Attorney. After the award and subsequent execution of the contract a Notice to Proceed will be issued. CONCLUSION: The City has received one bid for the American Recovery and Reinvestment Act, Energy Efficient Chiller Compressor Replacement Project at City Hall and the Police Facility, City Project No. 11-03. Staff has evaluated the bid in terms of contract compliance and grant guidelines and recommends that the City Council adopt the plans, specifications, and working details for said project; award the contract to the apparent low bidder Liberty Climate Control, Inc. in the amount of $545,600.00; and authorize the Mayor and the City Clerk to execute the Public Works Agreement. ERNESTO MUNOZ City Engineer LARRY HURST Interim Finance Director ATTACHMENT: "1" Bid Abstract PETER NAGHAVI, DIRECTOR Department of Public Services E DISTRIBUTION: Chief Executive Officer Assistant Chief Executive Officer City Attorney City Clerk Maintenance Services Manager Staff File CITY OF COSTA MESA DEPARTMENT OF PUBLIC SERVICES AMERICAN RECOVERY AND REINVESTMENT ACT ENERGY EFFICIENT CHILLER COMPRESSOR REPLACEMENT AT CITY HALL AND POLICE FACILITY CITY PROJECT NO. 11-03 SID OPENING RESULTS April 25, 2011 Bidder LIBERTY CLIMATE CONTROL, INC City SOUTH EL MONTE A'T_ AM I Total Bid $545,600.00 Engineer's Estimate: $ 500,000.00