HomeMy WebLinkAbout09 - CC-11 - Lions Park Sports Lighting Proj., 11-09 - 6/21/2011CITY COUNCIL AGENDA REPORT
MEETING DATE: JUNE 21, 2011
ITEM NUMBER:
SUBJECT: LIONS PARK (DAVIS FIELD) SPORTS LIGHTING PROJECT AT 570 WEST 18TH
STREET, COSTA MESA, CITY PROJECT NO. 11-09
DATE: JUNE 9, 2011
FROM: PUBLIC SERVICES DEPARTMENT/ENGINEERING DIVISION
PRESENTATION PETER NAGHAVI, DIRECTOR, DEPARTMENT OF PUBLIC SERVICES
BY:
FOR FURTHER INFORMATION CONTACT: ERNESTO MUNOZ, CITY ENGINEER, (714) 754-5335
RECOMMENDATION:
1. Adopt plans, specifications, and working details for the Lions Park (Davis Field) Sports Lighting
Project at 570 West 18th Street, Costa Mesa, City Project No. 11-09.
2. Waive a bid irregularity in the bid proposal submitted by RMF Contracting, Inc. dba R&M
Electrical Contracting, the apparent low bidder.
3. Award a construction contract to RMF Contracting, Inc. dba R&M Electrical Contracting, 26301
Dimension Drive, Lake Forest, California, 92630, in the amount of $309,066.25 (Base Bid minus
Bid Item No. 3 plus Alternate Bid Item No. 3A).
4. Authorize the Mayor and the City Clerk to execute the Public Works Agreement.
BACKGROUND:
On March 15, 2011 the City Council authorized the purchase of sports lighting equipment from
Musco Sports Lighting for Davis Field at Lions Park. Davis Field at Lions Park is currently used as
a multipurpose facility that allows the Recreation Manager flexibility to program different user
groups and to utilize the site as either a baseball field or a utility sports field. After the
improvements are completed, the City plans to continue to use the site in the same manner in order
to satisfy the demand for game and practice fields throughout the year.
Overall, the facility is well maintained; however, the existing sports lighting equipment generates a
high energy demand due to its advanced age. The electrical control system has also reached the
end of its useful life and needs to be replaced with energy efficient equipment. The construction
documents call for updating the existing lighting system to an energy efficient system similar to the
lighting systems that were installed at the TeWinkle Park Athletic Complex and the Farm Sports
Complex. The proposed lighting system includes the latest lighting control equipment designed to
be programmed for the hours of operation, and is also equipped to control the light fixtures so that
only those needed for the specific activity are activated. The new system is also designed to
provide a higher quality of light onto the field while reducing the amount of spilled light and glare
projected onto adjacent properties.
ANALYSIS:
The scope of work for this project includes the installation of City -purchased energy efficient sports
field lighting and light poles, including upgrading the system with a new transformer; removal and
replacement of the existing chain link fencing; installation of protective netting on the south and
west side of the field; repairing the landscaping and irrigation; and incidental work necessary to
complete the project as designed.
On June 1, 2011 the City Clerk received and opened four (4) bids for this project. RMF Contracting,
Inc. dba R&M Electrical Contracting was the apparent low bidder with a base bid proposal of
$296,156.25. The Engineer's estimate was $392,900.00. An analysis of the bids indicates that the
apparent low bidder submitted a base bid proposal that is 25% lower than the Engineer's estimate.
The variance between the low bidder and the Engineer's estimate may be attributed to the highly
competitive conditions prevalent in the construction industry at this time. The Bid Abstract is
included as Attachment 1 ".
Staff's review of the apparent low bid revealed that the extension of the unit bid prices did not match
the subtotal price that the bidder entered on Proposal Page P-1 a Rev1, yet the subtotal prices for
the two proposal pages added up to the total bid price that was submitted by the contractor. Based
on this analysis, it was determined that the bid proposal's total amount submitted by the bidder
reflects a true summation of the various bid items, and it is clearly written elsewhere in the bid
proposal indicating that the total price was the intended amount of the bid and it reflects the true
intent of the bidder. The City Council has the authority to waive minor irregularities in bids, and
waiving this minor irregularity does not give RMF Contracting, Inc. dba R&M Electrical Contracting
any advantage over the other bidders. Staff recommends that this bid irregularity be waived by
Council.
During the bidding process, staff required all of the bidders to submit a proposal for an alternate bid
item that was to be taken into consideration if the proposal for the base bid was below the
Engineer's estimate. Consideration would be given for the inclusion of the alternate bid item to the
contract award only if the bid price was favorable in cost and funding was available. Alternate Bid
Item No. 3A is for the installation of protective netting along the west side of Davis Field, which
would supplement the minimum netting requirements. The incorporation of this alternate bid item of
work will result in a net increase to the contract of $12,910.00. Considering the favorable bid
received for this work, staff recommends the inclusion of this Alternate Bid Item to the contract. The
recommended action results in the deletion of Bid Item No. 3 from the base bid and the addition of
the alternate Bid Item No. 3A to the base bid contract.
The license and references of RMF Contracting, Inc. dba R&M Electrical Contracting have been
checked and staff has found them to be in good standing. RMF Contracting dba R&M Electrical
Contracting successfully completed the installation of sports lighting at the Farm Sports Complex on
Field No. 5 & 6 in 2010.
ALTERNATIVES CONSIDERED:
City Council may chose not to waive the bid irregularity in the apparent low bidder's proposal and
direct staff to award the contract to the next apparent low bid. This action would require an
additional expenditure of $65,458.75 to complete the project at the price submitted by the second
lowest bidder.
Another alternative to this Council action would be to reject all the bids. If all the bids were rejected,
the City would need to readvertise or cancel the project. Staff believes that readvertising the project
will not result in lower bids and canceling the project is not recommended because the flood lighting
and controls are in need of replacement. The Council may also consider awarding only the base
bid. However considering the favorable bids received for this work, staff does not recommend this
option.
E
FISCAL REVIEW:
Funding for this project is available from the Costa Mesa Redevelopment Agency Capital
Improvement Project's budget.
LEGAL REVIEW:
RMF Contracting, Inc. dba R&M Electrical Contracting will furnish the necessary bonds and
insurance prior to the commencement of work, scheduled for July 2011, subject to the approval by
the City Attorney. After award and subsequent execution of the contract, a Notice to Proceed will
be issued.
CONCLUSION:
The City has received bids for the Lions Park (Davis Field) Sports Lighting Project at 570 West 18th
Street, City Project No. 11-09. Staff has evaluated all of the bids and recommends that the City
Council adopt the plans, specifications, and working details for said project; waive a bid irregularity
in the proposal submitted by RMF Contracting, Inc. dba R&M Electrical Contracting; and award the
contract to the apparent low bidder, RMF Contracting, Inc. dba R&M Electrical Contracting, in the
amount of $309,066.25 (Base Bid minus Bid Item No. 3 plus alternate Bid Item No. 3A); and
authorize the Mayor and the City Clerk to execute the Public Works Agreement.
ERNESTO MUNOZ
City Engineer
PETER NAGHAVI, Director
Department of Public Services
LARRY HURST
Interim Finance Director
ATTACHMENT: "1" Bid Abstract
DISTRIBUTION: Chief Executive Officer
City Attorney
City Clerk
Interim Development Services Director
Staff
File
3
ATTACHMENT
CITY OF COSTA MESA
DEPARTMENT OF PUBLIC SERVICES
LIONS PARK (DAVIS FIELD) SPORTS LIGHTING
570 W. 18TH STREET, COSTA MESA
CITY PROJECT NO. 11-09
BID OPENING DATE: JUNE 1, 2011
BID OPENING RESULTS
Bidder
City
Total Base
Bid
Alternate Bid
Total
1. RMF CONTRACTING, INC. DBA
R&M ELECTRICAL CONTRACTING
LAKE FOREST
$296,156.25
$309,066.25
2. MAC KENZIE ELECTRIC, INC.
HIGHLAND
$361,615.00
$374,915.00
3. ACE ELECTRIC, INC.
SAN DIEGO
$410,120.00
$422,620.00
4. NEI CONTRACTING &
ENGINEERING, INC.
CHULA VISTA
$480,568.00
$526,869.00
Average $387,114.81 $408,367.56