HomeMy WebLinkAbout- - 10-10 Attachment 2 - 9/20/2011LILTAC.HmMT 2 ARRA WILSON STREET REHABILITATION PROJECT R.J. NOBLE COMPANY FEDERAL PROJECT NO. 5312-081 CITY PROJECT NO. 10-10 Accounting Summary for Change Order No. 4 """""CHANGE ORDERS TO DATE*"''""' DESCRIPTION AMOUNT PERCENT TOTAL % Original Contract Amount $719,765.40 CCO #1 DELETION OF QUALITY CONTROL MATERIALS TESTING ($3,078.75) CCO #2 EXTRA WORK AT AGREED LUMP SUM PRICE - ADD DLC CONDUIT AND PULL BOX $7,085.40 -0.4277% -_0.4277% 0.9844% 0.5567% CCO #3 CCO #4 EXTRA WORK AT NEGOTIATED UNIT PRICES - MODIFY 4 TRAFFIC LOOPS TO TYPE D $924.00 EXTRA WORK AT FORCE ACCOUNT - 3 PAVING DAYS AND FINAL QUANTITY ADJUSTMENTS $13,446.79 0.1284% 0.6850% 1.8682% 2.5533% TOTAL: $18,377.44