HomeMy WebLinkAbout- - Improvements Alley No. 28, 29, 30 No.12- - 6/5/2012CITY COUNCIL AGENDA REPORT
MEETING DATE: JUNE 5, 2012 ITEM NUMBER:
SUBJECT: IMPROVEMENTS OF HICKORY DRIVE ALLEY (ALLEY NO. 28); PEPPER TREE LANE
ALLEY (ALLEY NO. 29); AND HARBOR BOULEVARD ALLEY (ALLEY NO. 30) - CITY
PROJECT NO. 12-03
DATE: MAY 24, 2012
FROM: PUBLIC SERVICES DEPARTMENT/ENGINEERING DIVISION
PRESENTATION BY: ERNESTO MUNOZ, PUBLIC SERVICES DIRECTOR
FOR FURTHER INFORMATION CONTACT: FARIBA FAZELI, INTERIM CITY ENGINEER, (714) 754-
5335
RECOMMENDATION:
1. Adopt plans, specifications, and working details for the Improvements of Alley No. 28, Alley
No. 29, and Alley No. 30, City Project No. 12-03.
2. Award a construction contract to Black Rock Construction Company, 282 North St. Crispen,
Brea, CA 92821, in the amount of $428,000.25 (base bid).
3. Authorize the Mayor and the City Clerk to execute the Public Works Agreement.
BACKGROUND:
The City owns and maintains 129 alleys. A Citywide Alley Improvement Report was presented to
the City Council in September 2007. At that time the Council approved a City Alley Improvement
Priority List to address the City's Alley System beginning with those alleys in most need of
improvement. To date, 35 alleys have been fully improved, and with this project the following
alleys will be rehabilitated:
1) Hickory Drive Alley (Alley No. 28) located south of Baker Street;
2) Pepper Tree Lane Alley (Alley No. 29) located west of Harbor Boulevard;
3) Harbor Blvd Alley (Alley No. 30) located north of Ponderosa Street.
ANALYSIS:
The pavement rehabilitation process for Alley No. 28, Alley No. 29, and Alley No. 30 consists of
removal of the existing asphalt concrete alley sections, the construction of new Portland Cement
Concrete (PCC) pavement sections, storm drain improvements, and other incidental work needed
to complete the project in accordance with the contract documents.
The City Clerk received and opened seven (7) bids for this project on April 11, 2012. Black
Rock Construction Company was the apparent low bidder with a base bid proposal of
$428,000.25. The Engineer's estimate was $515,303.00; and the average of the seven (7) base
bids received amounted to $564,338.41. An analysis of the bids indicates that this apparent low
bidder submitted a base bid proposal that is seventeen percent (17%) lower than the Engineer's
estimate. The variance between the low bidder and the Engineer's estimate may be attributed to
the highly competitive conditions prevalent in the construction industry at this time. The Bid
Abstract is included as Attachment "I".
The license and references of Black Rock Construction Company were checked and staff has
found them to be in good standing. Black Rock Construction Company has successfully
completed other City projects including most recently rehabilitation of Alley No. 47 (between
Cleveland Avenue and Coolidge Avenue and from Baker Street to Paularino Avenue), Alley No.
116 (east of Newport Boulevard from 23rd Street to Wilson Street), the northerly portion of Alley
No. 75 (west of Fullerton Avenue and south of Flower Street), and Alley No. 76 (south of Flower
Street from Alley No. 75 to Fullerton Avenue).
ALTERNATIVES CONSIDERED:
The alternative to this Council action would be to reject all the bids. If all the bids are rejected, the
City would need to readvertise or cancel the project. Staff believes that readvertising the project
will not result in lower bids.
FISCAL REVIEW:
Funding for this project has been budgeted with the use of Gas Tax funds.
LEGAL REVIEW:
Black Rock Construction Company has furnished the necessary bonds and insurance, which were
approved as to form by the City Attorney. After the award and subsequent execution of the
contract, a "Notice to Proceed" will be issued.
CONCLUSION:
The advertisement and bid opening for the improvements of Alley No. 28, Alley No. 29, and Alley
No. 30, City Project No. 12-03, has been completed. It is recommended that the City Council
adopt the plans, specifications, and working details for said project; award the contract to the
apparent low bidder, Black Rock Construction Company, in the amount of $428,000.25 (base bid);
and authorize%rtor
d the City Clerk to execute the Public Works Agreement.
ERNESTO MFARI AZELI
Public ServiceInten City Engineer
ATTACHMENTS: "1" Bid Abstract
"2" Location of Alleys
DISTRIBUTION: Chief Executive Officer
City Attorney
City Clerk
Staff
File
ATTACHMENT
CITY OF COSTA MESA
DEPARTMENT OF PUBLIC SERVICES
ALLEY NO. 28, ALLEY NO. 29, AND ALLEY NO. 30 IMPROVEMENTS
CITY PROJECT NO. 12-03
BID OPENING RESULTS 04-11-2012
Bidder
City
Total Base Bid
Total Alternate
Bid
1. BLACK ROCK CONSTRUCTION
COMPANY
BREA
$428,000.25
$942,579.00
2. NOBEST, INC.
GARDEN GROVE
$496,001.00
$702,638.50
3. ENCORRE SERVICES, INC.
GLENDALE
$527,246.00
$575,864.75
4. GOLDEN STATE CONSTRUCTORS
HUNTINGTONBEACH
$533,291.00
$1,129,203.50
5. MARTINEZ CONCRETE
AZUSA
$587,554.60
$760,968.85
6. HILLCREST CONTRACTING, INC.
HUNTINGTONBEACH
$625,635.60
$549,585.60
7. RUIZ CONCRETE & PAVING, INC.
DBA RUIZ ENGINEERING CO.
LONG BEACH
$750,640.43
$814,778.18
Average $564,338.41 $782,231.20
Engineer's Estimate., $ 515,303.00 $665,078.00
P
I
CITY OF COSTA MESA ATTACHMENT 2
Public Services/Engineering
2011 —2012 ALLEY NO. 28, 29 & 30
REHABILITATION PROJECT NOT To scnLe
BAKER ST.
D ST.
DALWOOD ST
[WHITE OAK ST,
PRIMROSE ST.
F
C
MINORCA DR.L)W-Fv`,�--
aPONDEROSA ST.
Q
z
0
ELM ST.
ADAMS AVE.
J
a
J
Q
QILLJ.LLJ
0
0
J
m
F-
}
d
a
D-
LU
J (Y
Q O
m
LLJ
D'
Q
ALLEY
X29
MINORCA DR.L)W-Fv`,�--
aPONDEROSA ST.
Q
z
0
ELM ST.
ADAMS AVE.