HomeMy WebLinkAbout04 - CC-5 - 2011-12 CDBG Alley No. 122 Improvement - 9/4/2012CITY COUNCIL AGENDA REPORT MEETING DATE: SEPTEMBER 4, 2012 ITEM NUMBER: SUBJECT: 2011-2012 COMMUNITY DEVELOPMENT BLOCK GRANT (CDBG) ALLEY NO. 122 IMPROVEMENT PROJECT - CITY PROJECT NO.12-02 DATE: AUGUST 23, 2012 FROM: PUBLIC SERVICES DEPARTMENT/ENGINEERING DIVISION PRESENTATION BY: ERNESTO MUNOZ, PUBLIC SERVICES DIRECTOR FOR FURTHER INFORMATION CONTACT: FARIBA FAZELI, INTERIM CITY ENGINEER, (714) 754- 5335 RECOMMENDATION: 1. Accept the work performed by Sequel Contractors, Inc. and authorize the City Clerk to file the Notice of Completion. 2. Release the Labor and Material Bond seven (7) months after the filing date; release the Faithful Performance Bond one (1) year after the filing date; and release the retention monies 35 days after the Notice of Completion filing date. BACKGROUND: On May 1, 2012, a construction contract in the amount of $201,810.00 was awarded to Sequel Contractors, Inc., 13546 Imperial Highway, Santa Fe Springs, CA 90670. The pavement rehabilitation process for Alley No. 122 consisted of the removal of the existing asphalt concrete alley section, the construction of a new Portland Cement Concrete (PCC) pavement section, and other incidental work needed to complete the project in accordance with the contract documents. Before Construction Construction Completed ANALYSIS: The work required by the contract documents was completed on June 21, 2012, to the satisfaction of the City Engineer. The final contract cost amounted to $182,100.50. A report of the final costs is included herein as Attachment "1 ". A summary of the costs is as follows: Original Contract Cost: $201,810.00 Final Quantity Adjustments ($19,709.50) Final Contract Cost $182,100.50 The final contract price reflects a 9.8% decrease to the original contract as a result of the final quantity adjustments. As of this date, there are no Stop Notices filed against the monies due to Sequel Contractors, Inc. ALTERNATIVES CONSIDERED: There were no alternatives considered for this item. FISCAL REVIEW: This project was funded from appropriated CDBG funds in the Fiscal Year 2011-2012 budget. LEGAL REVIEW: There is no legal review required on this item. CONCLUSION: The 2011-2012 Community Development Block Grant (CDBG) Alley No. 122 Improvement Project has been completed. It is recommended that the City Council authorize staff to file the Notice of Completion; release the remaining retention monies 35 days after the Notice of Completion filing date; and release the bonds accordingly. 1�7r ERNESTO M NOZ Public Services Director ATTACHMENTS: DISTRIBUTION "1" Cost Summary Chief Executive Officer City Attorney City Clerk Staff File FARIBA FAZELI Interim City Engineer 2 ATTACHMENT 1st PAYMENTTO: PROJECT: Base Bid FOR PAYMENT ON THE WARRANT LIST OF: SEQUEL CONTRACTORS, INC. 13546 IMPERIAL HIGHWAY, SANTA FE SPRINGS, CA 90670 2010-11 CDBG PROJECT: IMPROVEMENT OF ALLEY NO. 122 CITY PROJECT NO. 12-02 CITY OF COSTA MESA 6/15/12 DATE: 05/25/12 PAGE: 1 OF 1 ITEM NO OIDOUANTITY DESCRIPTION UNIT PRICE PREVIOUS QUANTITY QUANTITY THIS ESTIMATE TOTAL QUANTITY TO DATE PREVIOUS AMOUN! AMOUNT THIS EST TOTAL TO DATE CONTRACT PRICE 1 1 LS MOBILIZATION $10000.00 0 % 100 % 100 %D $0.00 $10,000.00 $10,000.00 $10,000.00 2 1 LS CLEARING AND GRUBBING $17,500.00 0 %D 100 % 100 % $0.00 $17,500.00 $17,500.00 $17,500.00 3 26,440 SF REMOVE & CONSTRUCT 6" PCC OVER 6" CMB $ 5.50 0 SF 24,512 SF 24512 SF $0.00 $134,816.00 $134,816.00 $145,420.00 4 540 SF REMOVE & CONSTRUCT 6" PCC ALLEY INTERSECTION OVER 8" CMB $ 8.00 0 SF 246 SF 246 SF $0.00 $1,968.00 $1,968.00 $4,320.00 5 45 LF REMOVE & CONSTRUCT NEW C-8 CURB & GUTTER OVER 6" CMB $ 50.00 0 LF 42 LF 42 LF $0.001 $2,100.00 $2,100.0011 $2,250.00 6 280 SF REMOVE & CONSTRUCT 4" PCC SIDEWALK $ 6.00 0 SF 150 SF 150 SF $0.001 $900.00' $900.00' $1,680.00 7 310 SF REMOVE &CONSTRUCT 3' WIDE AC SLOT PAVING $ g,pp 0 SF 323.5 SF 323.5 SF $0.001 $2,911.501 $2,911.50 $2,790.00 8 1,630 SF REMOVE & CONSTRUCT 6" WIDE AC SLOT PAVING $ 5.00 0.00 SF 1,861.00 SF 1861 SF $0.00 $9,305.001 $9,305.001 $8,150.00 9 1 EA RELOCATE SIGN $ 200.00 0 EA 0 EA 0 EA $0.00 $0.00 $0.001 $200.00 10 10 LF INSTALL REDWOOD HEADER $ 50.00 0 LF 2 LF j 2 LF ' $0.00 $100.00 $100.00 $500.00 11 1 LS TRAFFIC CONTROL S 2,000.00 0 %D 100 %D 100 % $0.00 $2,000.00 $2,000.00 $2,000.00 12 2 EA SET NEW SURVEY MONUMENT AND CENTERLINE TIES $ 500.00 0.00 EA 0.00 EA 0 EA $0.00 $0.00 $0.00 $1,000.00 13 1 EA ADJUST SURVEY MONUMENT TO GRADE $ 500.00 0 EA 0 EA 0 EA $0.001 $0.00 $0.001 $500.00 141 FA PROJECT MANAGEMENT $ 5,000.00 0 FA 0 FA .0 FA $0.001 $0.00! $0.001 $5,000.00 15 1 LS POTHOLING $ 500.00 0 % 100 % 100 % $0.001 $500.00 $500.001 $500.00 TOTAL: $0.00 $182,100.50 $182,100.50 $201,810.00