HomeMy WebLinkAbout08 - CC-5 - Attachment 3 - 2/18/2014ATTACHMENT 3
PROJ.
CIP PROJECT NAME AND STATUS
NO.
1
ANAHEIM/SUPERIOR STORM DRAIN AND STORMWATER MITIGATION PROJECT:
This project consists of installation of Reinforced Concrete Box on Anaheim Avenue and
Detention/Infiltration system at Lions Park.
• Complete the construction documents and will advertise for construction by March 2014.
2
PACIFIC AVENUE AND CANYON DRIVE STREET IMPROVEMENT PROJECT:
This project consists of reconstruction of damaged curb & gutter, sidewalks, driveways, cross
gutters and mill and AC overlay.
• This project is being advertised for construction
• Begin construction in March 2014.
3
2013-2014 CITYWIDE STREET REHABILITATION:
This project consists of mill & AC overlay and/or slurry seal application of the streets located within
the Mesa North, Westside, Upper and Lower Bird tracks and area around the Trinity Church
neighborhoods.
• This project is being advertised for construction
• Begin construction in March 2014.
4
2013-2014 CITYWIDE PARKWAY REPAIR AND NEW SIDEWALK CONSTRUCTION:
This project consists of citywide removal and construction of damaged curb & gutter, sidewalks,
driveways and cross gutters
• This project is being advertised for construction.
• Begin construction by January 2014.
5
2013-2014 CITYWIDE UNIMPROVED ALLEYS:
This project consists of removal and replacement of the damaged pavement at several alleys
• This project is being advertised for construction
• Be in construction in March 2014.
6
2013-2014 CDBG STREET AND ALLEY IMPROVEMENT PROJECT:
This project consists of rehabilitation of alleys and streets within the CDBG area.
• This project is being advertised for construction
• Be in construction in March 2014.
7
VICTORIA/VALLEY INTERSECTION IMPROVEMENTS:
This project consists of reconstruction of the north leg of the intersection and traffic signal
modifications.
• A construction contract has been awarded.
8
WEST 19TH STREET IMPROVEMENTS:
This project consists of construction of a right -turn lane into the Tower on 19th Street, pedestrian
signal replacements, and street light modifications. This project is federally funded.
• A construction contract has been awarded.
9
PARKING LOT REHABILITATION PROJECT:
This project consists of rehabilitation of the following parking lots:
1. Vista Park parking lot
2. Balearic Center parking Lot
3. Canyon Park parking lot
4. Fire Station No. 5 parking lot
• This project is being advertised for construction.
ATTACHMENT 3
PROD.
CIP PROJECT NAME AND STATUS
NO.
10
DEL MAR AVENUE MEDIAN IMPROVEMENTS:
This project consists of construction of a raised landscaped median on Del Mar Avenue just east of
Newport Boulevard.
• This project is in the design phase.
11
EAST 17TH STREET LANDSCAPE ENHANCEMENT:
This project consists of construction of raised landscaped median on 17th Street from Santa Ana
Avenue to Irvine Avenue and intersection widening at Tustin Avenue and 17th Street.
• The construction contract has been awarded.
12
DOWNTOWN COSTA MESA GATEWAY LANDSCAPE IMPROVEMENT:
This project consists of construction of a monument sign at the end of SR 55 FWY near 19th street
and landscaped improvement at the median and the east side of the freeway.
• The construction contract has been awarded.