HomeMy WebLinkAbout26 - CC-10 - Attachment 3 - 3/18/2014ATTACHMENT 3
CITY OF COSTA MESA
PUBLIC SERVICES DEPARTMENT
CONTRACT CHANGE ORDER NO. 1 SUPPL NO. REV.
Project: PARKWAY CONCRETE REPAIR SHEET 1 OF 1
FEDERAL NO. N/A CITY PROJECT NO. 13-19 To C.J. CONCRETE CONSTRUCTION Contractor:
You are hereby directed to make the herein described changes or do the following described work not included in the original scope of
work approved with the original contract or previously approved change orders.
NOTE: This change order is not effective until approved in accordance with Council Policy No. 700-1.
Description of work be done, estimate of quantities, and prices to be paid. Segregate between additional work at contract price,
agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually
used and no allowance will be made for idle time.
Change Requested by: The City of Costa Mesa
EXTRA WORK AT ORIGINAL CONTRACT UNIT PRICES
1. Remove and Reconstruct Curb & Gutter (Type C-6) @ $39/1-F
2. Remove and Reconstruct Sidewalk (4"PCC/4"CMB) @ $6/SF
3. Remove and Reconstruct Driveway (6"PCC/6"CMB) @ $7/SF
4. Install Truncated Dome @ $350/EA
5. Paint Curb Red @ $5/LF
6. Remove and Reconstruct Cross Gutter and Spandrel ( 8"PCC/8"CMB) @ $14/SF
7. Miscellaneous AC Paving @ $150/TON
8. Construct Type "A" Curb @ $40/LF
This sum shall constitute full compensation, including all markups, for this change and no additional payment will be made.
Project Summary:
CHANGE ORDER TOTAL INCREASE: $164,500
Amount %
Original Agreement Contract Amount: ......................................... $ 822,580.00
Previously Approved Change Orders: ......................................... $ 0.00
Amount this Change Order (CO#1): .......................................... $ 164,500.00 20%
Revised Contract Amount: ....................................................... $ 987,080.00 20%
By reason of this order the time of completion will be adjusted as follows: 60 working days
Submitted by:
Approval Recommended:
Date:
Date:
Approved: Date:
We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is
approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services
necessary for the work above specified, and will accept as full payment therefor the prices shown above.
Contractor C.J. CONCRETE CONSTRUCTION
By Title Date:
If the Contractor did not sign acceptance of this order, his attention is directed to the requirements of the specifications as to
proceeding with the ordered work and filing a written protest within the time therein specified.