HomeMy WebLinkAbout11 - CC-7 - Attachment 1 - 7/1/2014CONTRACT CHANGE ORDER NO
CITY OF COSTA MESA
PUBLIC SERVICES DEPARTMENT
SUPPL NO.
REV.
ATTACHMENT 1
Project: AS -NEEDED STAFF SUPPORT FOR VARIOUS CAPITAL IMPROVEMENT PROGRAM PROJECTS
To CIVIL SOURCE , Inc., 9890 Irvine Center Drive, Irvine, California 92618 PO No. 9209
Consultant:
You are hereby directed to make the herein described changes or do the following described work not included in the
original scope of work approved with the original contract or previously approved change orders.
NOTE: This change order is not effective until approved in accordance with Council Policy No. 700-1.
Description of work be done, estimate of quantities, and prices to be paid. Segregate between additional work at contract
price, agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only such time as
equipment is actually used and no allowance will be made for idle time.
Change Requested by: The City of Costa Mesa
Scope of Additional Work: provide a team of professional engineers and inspectors to implement and/or oversee the
design and construction of various CIP projects on an as -needed basis. This includes, but is not limited to, preparation of
Requests For Proposal for Professional Engineering and/or Architectural Services, review and plan check of construction
documents, review and approval of Water Quality Best Management Practices by developers, review and management of
consultants and/or contractors' activities and performance, advertisement of projects for construction, negotiation of
contract change orders, monitoring of project schedules, and providing construction management and inspection services
for CIP and private development within the public right-of-way.
CHANGE ORDER TOTAL INCREASE: $600,000
Project Summary
Amount
Original Agreement Contract Amount: ......................................... $ 200,000.00
Previously Approved Change Orders: ......................................... $ 0.00
Amount this Change Order (CO#1): .......................................... $ 600,000.00
Revised Contract Amount: ....................................................... $ 800,000.00
By reason of this order the time of contract will be extended from 6/30/2014 to 9/30/2015
Submitted by:
Approval Recommended:
Date:
Date:
Approved: Date:
We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is
approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services
necessary for the work above specified, and will accept as full payment therefor the prices shown above.
Consultant
By Title Date:
If the Contractor did not sign acceptance of this order, his attention is directed to the requirements of the specifications as to
proceeding with the ordered work and filing a written protest within the time therein specified.